Home Errors in documenting the subsoil and their impact on the investment implementation: Case study
Article Open Access

Errors in documenting the subsoil and their impact on the investment implementation: Case study

  • Marzena Lendo-Siwicka , Grzegorz Wrzesiński EMAIL logo and Katarzyna Pawluk
Published/Copyright: June 1, 2021
Become an author with De Gruyter Brill

Abstract

Improper recognition of the subsoil is the most common cause of problems in the implementation of construction projects and construction facilities failures. Most often, their direct cause is the mismatch of the scope of geotechnical diagnosis to the appropriate geotechnical category, or substantive errors, including incomplete or incorrect interpretation in the creation of a geological-engineering model and often overlooked hydrogeological conditions. In many cases, insufficient recognition and documentation of geotechnical and/or geological and engineering conditions leads to damage and construction failures, delays in consider construction, and the increase of the investment budget. That’s why, in order to avoid the above, particular attention should be paid to proper geotechnical and geological-engineering documentation at the design and construction stages. The selected example of the investment analyzed errors in the geological-engineering documentation, which mainly concerned the lack of recognition of locally occurring organic soils, the incorrectly determined location of the groundwater table and the degree of compaction of non-cohesive soils, and numerous errors of calculated values of soil uplift pressure. The detection of the errors presented in the paper made it possible to select the correct technology for the construction of the sanitary sewage system and to increase the thickness of the horizontal shutter made of jet grouting columns in the area of the excavation. In addition, the article discusses the principles of proper calculation of limit states and subsoil testing, which have a significant impact on the implementation of planned investments.

1 Introduction

The foundation of buildings includes not only the design of foundations, but also the way of transferring loads from foundations to the subsoil and preventing deformation of installations laid directly in the subsoil. Proper design requires precise identification of the subsoil in order to determine the existing soil and groundwater conditions. The design process should also take into account the purpose of the object, the type of construction, its deformation, production technology, and conditions of use [1,2,3].

The examples of problems in the implementation of construction works and failures of construction works known from engineering practice result from insufficient fulfillment of formal conditions. Their direct causes are most often substantive errors, including incomplete or incorrect interpretation in the preparation of geological-engineering and geotechnical documentation, including frequently overlooked hydrogeological conditions [4]. It also often happens that the scope of the subsoil research is not adjusted to the geotechnical category, i.e., the complexity of the planned investment [5,6].

There are inconsistent provisions in Polish legal regulations, which make it difficult to interpret them correctly. The greatest ambiguities occur in the case of documentation work on the recognition of the geological and engineering environment on the basis of subsoil tests [7]. Documentation issues are regulated in Poland by the following legal acts: the Construction Law Act [8], the Geological and Mining Law Act [9], and related ordinances: Minister for Transport, Construction, and Maritime Economy of 25 April 2012 on determining the geotechnical conditions for the foundation of construction works [10], Minister of Environment of November 18 on hydrogeological documentation and geological-engineering documentation [11], Minister of the Environment of December 20, 2011 on detailed requirements for geological work projects, including works that do not require a concession [12] and standards: EN 1997-1:2004: Geotechnical design – Part 1: General rules [13] and PN-B-02479: 1998 Geotechnical documentation [14]. The choice of the procedure in accordance with the regulations depends on the purpose of the study, the stage of investment implementation, the complexity of soil conditions, and the geotechnical category of the building [4,7,15]. Therefore, in practice, the foundation conditions are elaborated in the form of geotechnical documentation [8,10] or geological-engineering documentation [9].

Geotechnical documentation is created on the basis of research activities performed to determine the type, properties, strength properties and deformability of soils, their variability, groundwater level, and stability of excavations and embankments [8]. However, geotechnical investigation, in accordance with [14], includes field works that do not cause negative environmental changes, such as small-scale geotechnical drilling, static and dynamic sounding, pressure and dilatometer tests, geophysical (no explosives), outcrop foundations, research excavations, and laboratory determination of physical, mechanical, and chemical properties of soils and groundwater, etc. [8]. However, in the Act on Geological and Mining Law [16], the definition of geological-engineering documentation is not provided, but it only indicates when the documentation should be prepared, what should be included, and who accepts it.

The design should include predicted geological profiles of designed boreholes, execution of boreholes or excavations, description of testing of boreholes and excavations, including the method of geological sampling, the scope, number, and size of geological samples to be taken, as well as description and justification of the scope of laboratory tests and the graphic part should provide geological and technical profiles (borehole structure) of designed boreholes or excavations, along with an indication of the intended location of sampling sites.

Based on the above-mentioned basic definitions, it follows that the provisions of the construction law and geological law are inconsistent, which creates a problem in the correct interpretation of the regulations and placing the boundary between the geological-engineering documentation and the documentation of subsoil tests. In engineering practice, the documentation of subsoil tests contains similar elements to the geological-engineering documentation developed to determine the geotechnical conditions of the foundation. If there are complicated soil conditions in the field (the third geotechnical category and the second in complex soil conditions), separate geological and engineering documentation should be prepared in accordance with applicable regulations and subsoil documentation (geotechnical foundation conditions) developed in accordance with the law regulations or increasingly Eurocode 7. Geological-engineering documentation should include, among others, a forecast of the impact of designed objects on the environment, a description of geodynamic processes, if any, and information about the location and resources of mineral deposits that can be used in the implementation of the planned investment. In summary, there is no distinction in current practice, and the scope of geotechnical and geological works is often similar. Geotechnical documentation primarily concerns the characteristics of the subsoil of the designed object, and in geological-engineering documentation, problems related to environmental protection and the occurrence of geodynamic processes are also discussed in greater detail.

At present, significant development and growth of construction investments are observed all over the world, which in the case of emphasis on accelerated project implementation may be exposed to a number of threats. First of all, the importance of geotechnical investigations is underestimated at the design and implementation stages of construction works. In many cases, insufficient identification and documentation of geotechnical and/or geological and engineering conditions leads to construction failures, delays in the implementation of investments, and an increase in the investment budget. As a result of the implementation of a number of construction projects, the increase in expenditure in the initial stages of the construction investment process for geotechnical and geological research has significantly reduced the total construction costs. However, this approach to the planning and implementation of most investments is an exception [1,17,18,19]. Errors in the documentation regarding the recognition of subsoil conditions (soil and water) have contributed to many construction failures and disasters, among others collapse of tunnels [20,21,22,23,24], failure and collapse of foundations [19,25] and construction of buildings [24,26,27,28], damages to the surface and failures of road infrastructure and bridges [29,30,31,32], and damages and breakdowns of earthworks [3,31,33].

In connection with the above, this article indicates the need for proper geotechnical and geological-engineering documentation in order to avoid damage and failure of the resulting engineering structure/building structure, increase of general construction costs, and exceeding deadlines for investment implementation. The main goal of this study is to show the errors in documenting the subsoil as a result of overinterpretation of field test result. On the example of the construction of a sewage pumping station and sanitary sewage system with a gravitational run, the principles of proper calculation of limit states were discussed and errors in the original geological-engineering documentation were presented, which had a significant impact on the time and costs of a given investment.

2 Site characteristics

The analysis of geological-engineering documentation and its impact on the implementation of the investment was carried out on the example of documentation for the construction of a sewage pumping station and a sanitary sewage system with a gravitational run located in the Masovian Voivodeship. The bottom plate of the sewage pumping station is 6.6 m below ground level, whereas the sewer cavity varies from 2.02 m below ground level at the point of connection with the existing sewage section up to 5.48 m below ground level at the entrance to the pumping station. The pumping station is located on an undeveloped plot of land with an area of 0.11024 ha entirely covered with grass. The designed pumping station consists of the following elements:

  1. reinforced concrete monolithic cuboid chamber with dimensions of 3.0 × 4.0 × 2.59 m, covered with a ceiling made of two prefabricated panels,

  2. reinforced concrete prefabricated chamber with a circular cross section, diameter 3.0 m, and depth 6.8 m covered with a ceiling made of prefabricated slab,

  3. reinforced concrete prefabricated circular chamber, diameter 1.4 m and depth 5.3 m.

Gravitational sanitary sewage system is realized on a section of L = 876 m in stoneware pipes with a diameter of 0.2 m along a one-way street with an asphalt surface. In the road lane, there are utilities in the form of water supply, sewage, energy, and telecommunications networks. There are single-family housings on both sides of the street. Due to the existence of complicated soil conditions, the planned sewage section is divided into three sections different in terms of technology, i.e., in an open excavation, secured with steel sheet piles and horizontal shutter, trenchless method, and in an open excavation, protected with steel moldings or system shuttering. The section of the sewage network is armed with concrete wells from prefabricated elements with a diameter of DN 1.2 m, covered with cast iron manholes. The water supply connection for the area of the 10.9 m long compressor station with the water meter well is planned in the open excavation, with the reinforcement of the vertical walls of the shuttering, as required from steel moldings, plate reinforcements, or sheet piles made of steel.

Based on the tests included in the project documentation, it can be concluded that there is humus on the analyzed area in the soil surface or the nonconstruction embankments with a maximum thickness of 0.8 m. The remaining part of the subsoil is dominated by sandy soils of the Pleistocene and Holocene ages associated with the river accumulation of the overflow terrace. Sandy soils are usually fine sands, but also silty sands and medium sands with areas of thick sands interbedding. In the subsoil, the presence of cohesive soils of the Holocene age, i.e., sandy clay, silt with organic mud interbeddings, and silty clay with sand, was also found locally. Moreover, in the western and central parts of the planned sewage section, on the roof of sands, there is a layer of cohesive soils represented by clayey sands and locally by silty clays. On the analyzed area, there is a free groundwater table at a depth of 1.7 m below ground level and of a tensed nature at a depth of 10.0 m below ground level.

3 Methods

In the countries of the European Union, the superior documents constituting a set of guidelines developed by the European Committee for Standardization (CEN) regarding the design of engineering structures are Eurocodes. The main purpose of the introduction of the Eurocodes was to harmonize the design practice across Europe and provide a uniform framework for the design of various types of engineering structures [5].

In the documentation of the recognition of the geological and engineering environment based on subsoil test, Eurocode 7 [13] is used most often in engineering practice. According to its content, during designing two kinds of limit states are required [13]:

  1. Ultimate Limit States (ULS),

  2. Serviceability Limit States (SLS).

The following Ultimate Limit States ULS of destruction are checked: EQU – equilibrium, STR – structural, GEO – geotechnical, UPL – uplift, and HYD – hydraulic heave. The limit state of serviceability SLS refers only to the construction. Among the types of this state, mention is made of subsidence, settlement differences, structure rotation, and in special cases, additional impacts, e.g., caused by vibrations.

Geotechnical design according to Eurocode 7 is based on demonstrating in a way that there is no doubt that no limit state of load bearing capacity will be reached, which should refer to permanent, exceptional, and seismic computational situations.

Figure 1 
               Diagram of the limit state of displacement of the building structure: V
                  dst,d – vertical destabilizing permanent and variable interactions, G
                  stb;d – vertical stabilizing permanent interactions [13].
Figure 1

Diagram of the limit state of displacement of the building structure: V dst,d – vertical destabilizing permanent and variable interactions, G stb;d – vertical stabilizing permanent interactions [13].

In the case of designing engineering structures in which underground water is present or flows, its impact on the structure should be taken into account when designing. The influence of groundwater on engineering structures, including sewage pumping station and sanitary sewage system, can lead to limit states commonly referred to as hydraulic failure, which should be checked by design calculations. EN 1997-1:2004: Eurocode 7 [13] standard provides in Chapter 10 four types of hydraulic failure in the soil caused by water pressure in the pores or water flow in the soil, i.e., damage caused by displacement, hydraulic lifting of soil particles, internal erosion, and hydraulic failure. In the case of selected research objects, there is a limit state of uplift (UPL). Document states that “The displacement takes place when the value of the water pressure in the pores under the structure or below the soil layer with low permeability exceeds the average tensity (caused by the weight of the structure and/or obstructing the above soil layers)”. The limit state of displacement should be checked by comparing the permanent holding effects (e.g., building weight or soil and friction on the side walls) with permanent and variable destabilizing effects caused by water (Figure 1), which are given in a form of formulas (1) and (2) [13].

(1) V dst,d G stb;d + R d

(2) V dst,d = G dtb;d + Q dst;d

Where: V dst,d – vertical destabilizing permanent and variable interactions, G stb;d – vertical stabilizing permanent interactions, R d – the calculated value of additional resistance to counteracting the displacement, G dst;d – vertical destabilizing permanent interactions, Q dst;d – vertical destabilizing variable interactions.

In checking the conditions (1) and (2), the calculation values obtained on the basis of the characteristic values and coefficients given in Annex A of EN 1997-1:2004: Eurocode 7 of partial factors for the impacts and geotechnical parameters of the subsoil should be used. The evaluation of the possibility of the limit state of displacement is carried out by calculating the degree of utilization according to the formula [13]:

(3) Λ UPL = V d,dst V d,stb + R d 100 %

The degree of utilizations (safety coefficients) as the final effect of the design calculations are also determined by adopting calculation values.

4 Results

Taking into account the existing geological-engineering documentation of the analyzed objects, supplementary tests were carried out to randomly check the identified groundwater conditions with actual conditions. As part of supplementary tests, the following works were carried out: 1 drilling to a depth of 16.0 m, installation of 1 piezometer for observing the position of groundwater table, and 3 cone penetration tests CPT to a depth of 10.0 to 19.0 m (CPT-1, CPT-2, CPT-3). On the basis of the obtained test results and design documentation, calculations of the bearing capacity of the subsoil were made due to hydraulic failure – limit state of uplift (UPL) regarding the horizontal stability of the shutter from the columns planned to be made by high-pressure injection technique (the so-called jet grouting) in the subsoil of planned investments.

Drilling was made with a rotary-mechanical, mechanical, and semi-mechanized system in casing pipes. During the drilling conducted under the supervision of an authorized geologist, macroscopic soil studies were performed and their type and condition were recognized (Figure 2). Observations and measurements of the groundwater table were also carried out. A free groundwater table was drilled at a depth of 1.7 m below ground level and tensed at a depth of 10.0 m below ground level. The CPT-1 probes were made to a depth of 10.0 m. CPT-2 probing was made to a depth of 18.0 m, and CPT-3 probing to a depth of 19.0 m. When pressing the tip of the probe at a constant rate of 0.02 m/s, resistance values of the cone (q c) and friction on the sleeve (f s) were determined. These values were used to determine the condition of sandy and cohesive soils and to estimate the strength parameters of the subsoil of the analyzed object. The results of the tests are summarized in Table 1.

Figure 2 
               Geological profile (a) from the project documentation (b) from supplementary tests for the SD hole.
Figure 2

Geological profile (a) from the project documentation (b) from supplementary tests for the SD hole.

Table 1

List of subsoil test results from design and supplementary documentation

Supplementary documentation Design documentation
No. Corresponding calculation point Depth of diagnosis (m) Type of soil Depth of diagnosis (m) Type of soil
CPT-1 W11 10.0 In the subsoil to a depth of approx. 10.0 m there are alternating layers of cohesive and organic soils and permeable non-cohesive soils. Below is a layer of compacted non-cohesive soils 6.45 Organic soil at a depth of max. 0.8 m, below to a depth of 6 m MSa, no interbedding
CPT-2 W5 18.0 In the subsoil up to a depth of approx. 6 m, there are alternating layers of cohesive and permeable non-cohesive soils, less than 13 m there is a layer of non-cohesive soils, the last 2 m of the soil is a cohesive layer. Below 13 m there is a non-cohesive layer 8.0 Organic soil at a depth of 0.3 m, below to a depth of 5.4 FSa, to a depth of 3 m clSa, below FSa to a depth of 8 m
CPT-3 SD 19.0 Up to 14.5 m there is a layer of permeable non-cohesive soils with interbedded cohesive soils. Below it is 3.5 m thick non-cohesive soils 10 Organic soil at a depth of up to 0.4 m, below to a depth of 1.9 m clSa, below siSa to a depth of 3 m, organic soil, to a depth of 7.1 m MSa to a depth of 9 m and below clSa

The calculations were carried out in order to check whether the designed aperture from the horizontal columns planned for jet grouting presented in the design documentation has sufficient thickness to balance the destabilizing forces that affect the excavation bottom for the designed pumping station and sanitary sewage system. The scope of the calculation included checking the limit state of the trench housing: under the slider chamber (1 calculation point); drain well and press (1 calculation point); for wells (24 calculation points marked as W); and pipeline (8 calculation points marked as BH).

An example of a calculation scheme is shown in Figure 3.

Figure 3 
               An example of a calculation scheme for the S1 trench housing.
Figure 3

An example of a calculation scheme for the S1 trench housing.

The following values of volumetric loads were used in the calculations:

  1. volumetric weight of the compound 17 kN/m3,

  2. volumetric weight of native soil 18.0–20.05 kN/m3,

  3. volumetric weight of base concrete 24 kN/m3,

  4. volumetric weight of the aperture of the jet grouting columns 22 kN/m3,

  5. volumetric weight of water 9.81 kN/m3,

  6. volume weight of reinforced concrete 28 kN/m3.

Other data used in calculations and results of calculations made in accordance with formulas no. 1, 2, 3 are presented in Table 2.

Table 2

Data summary and results of UPL limit state calculations

Designed housing The thickness of the horizontal shutter from the jet grouting columns according to the design (m) The depth of the water table adopted for calculations below ground level (m) Weight of the well (kN) Value destabilizing force (kN) Value of stabilizing force (kN) Utilization factor (%) The proposed thickness of the horizontal shutter from the jet grouting columns (m) Degree of utilization for the proposed thickness of the jet grouting column (%)
W1 4 0.95 6.53 2900.92 2917.39 95.67
W2 4 0.95 6.88 2900.92 3032.59 95.66
W3 4 0.95 7.99 1352.87 1448.59 93.39
W4 3 1.6 6.39 1126.0 1026.81 109.66 3.8 94.71
W5 3 1.75 8.09 2743.04 2536.57 108.14 3.7 95.02
W6 3 1.6 7.45 1130.41 1028.34 109.93 3.8 94.96
W7 3 1.6 7.66 1129.31 1027.95 109.86 3.8 94.90
W8 3 1.6 8.02 1127.10 1028.27 109.61 3.8 94.69
W9 2.5 1.6 7.12 1047.62 926.187 113.11 3.4 94.51
W10 2.5 1.6 7.89 1039.90 926.88 112.19 3.3 95.50
W11 2.5 1.6 7.85 1032.17 926.84 111.36 3.3 94.79
W12 2.5 1.6 7.85 1017.81 926.84 109.81 3.2 95.24
W13 2 1.6 6.32 953.79 824.19 115.72 2.9 94.76
W14 2 1.6 7.01 935.02 824.81 113.36 2.8 94.75
W15 2 1.6 6.74 914.05 824.57 110.85 2.7 94.59
W16 2 1.6 6.54 878.72 824.39 106.59 2.5 94.93
W17 2 1.6 6.00 848.91 823.90 103.04 2.3 95.96
BH1 4 0.7 715.73 692.55 103.35 4.6 95.60
BH2 4 1.0 2008.85 1963.56 102.31 4.6 94.63
BH3 4 1.6 2302.11 3027.92 76.03
W18 3.5 1.2 5.82 1073.17 1168.40 91.85
W19 3.5 1.2 5.86 1082.88 1168.43 92.68
W20 3.5 1.2 7.00 1101.33 1169.46 94.17
W21 3.5 1.2 6.40 1109.10 1168.92 94.88
W22 3 1.2 7.05 1061.51 1080.41 98.25
W23 3 1.2 6.90 1072.19 1080.27 99.25
W24 3 1.2 6.17 1086.76 1079.61 100.6 3.4 94.43
BH4 3.5 1.6 1408.22 1516.10 92.88
BH5 3.5 1.6 1437.17 1487.13 96.64
BH6 3.5 0.5 2340.00 2353.10 99.44
BH7 3.5 0.79 1990.79 2023.13 98.40
BH8 3.5 0.95 1653.26 1693.16 97.64
SD and press 4.4 0.7 11.66 + 33.80 = 45.46 5868.88 5985.41 98.05
Valve house 4 0.7 50.31 377,121 3316.73 113.70 4.9 94.25

5 Discussion

The results of complementary field tests (drilling and CPT) partially confirmed the general nature of the subsoil described in the design documentation (Table 1). The previous recognition of the subsoil was carried out at much smaller depths, up to a maximum of 10 m, therefore the soils lying below this depth were not recognized (Figure 2). Both basic and complementary studies confirmed occurrence up to a depth of 10 m below ground level, alternating layers of cohesive soils (clay and silty clay in the plastic and soft plastic state) and permeable non-cohesive soils (medium and fine sands), while in both documentations the depth of retaining individual layers was different. Complementary CPT tests showed cone resistance q c greater than 50 MPa for sands occurring at a depth below 10 m which indicated that these soils are very dense, i.e., I D > 0.85. The results of CPT tests were taken into account in the technology of making a vertical diaphragm using steel sheet piles and a horizontal shutter from the jet grouting columns of the planned sewage pumping station. The piezometer installed in the borehole showed that the confined groundwaters drilled at the depth of 10.0 m below ground level stabilized initially at a depth of 1.7 m. After rainfall, the groundwater level in the piezometer stabilized at a depth of 0.7 m. The result of this study influenced the adopted design solutions, because in the previous documentation it was found that confined groundwater table occurs at a depth of about 2.0 m below ground level.

The analysis of the results of calculations consisting in checking the limit state of bearing capacity due to hydraulic failure (displacement) shows that the originally designed thickness of the horizontal shutter was appropriate in the case of W1–W3, W18–W23, and BH3–BH8. Calculations for the above-mentioned excavations showed that the load degree of utilization due to hydraulic failure with the design scheme adopted in the project was above 94%, except for the BH3 excavation, for which the degree of utilization was 76%. It should be noted that the calculated values of degree of utilizations indicate a small safety margin. If the degree of utilization exceeds 100%, stability to hydraulic failure is not maintained and the thickness of the shutter should be increased. In the case of excavations W4–W17, W24, BH1, and BH2 and gate valve chambers, the value of degree of utilization exceeds 100%, which indicates the possibility of exceeding the limit state of hydraulic displacement.

The calculations carried out on the basis of supplementary tests showed that the thickness of the horizontal shutter from the jet grouting columns in the area of excavations W4–W17, W24, BH1, and BH2 should be increased according to the values given in Table 2. For given values of horizontal thickness of the shutters, utilization ratio is around 95%. Increasing the thickness of the horizontal shutter from the jet grouting columns in the area of excavations W4–W17 and W24 as well as BH1 and BH2, as well as digging into the gate valves chamber in relation to the original concept, resulted from erroneous recognition of the subsoil in the existing documentation. In 18 research points, safety factors were exceeded, which accounted for more than 50% of test openings. The average thickness increase of the proposed jet grouting column was increased by 0.7 m (minimum 0.3 m for the W17 test point, maximum 0.9 m for S9 and W13 and the gate valve chamber). In addition, the variable trench width, on average, around 3 m at the excavation length from 1.81 to 7.41 m, increased the concrete mix volume needed by the aperture to approximately 109 m3. In the cost calculation, after adopting the average price of a concrete mix in the amount of 177 PLN/m3 and the norm of material inputs for 1 m3 of a column with a value of 1.03 m3 (without taking into account overheads and labor costs), the value of materials increased by about PLN 20,000, and thus additional costs of the planned investment increased the value of the works by approximately PLN 46,000 (Table 3).

Table 3

The value of the increase in the price of the jet grouting columns based on the Norma-Pro program

No. Base Description UM Outlays Unit cost R M S
Quantity survey
1 KNR 2-02 1101-01 Concrete foundation on the subsoil m3
BOQ = 109.000 m3
1* –R– Work hours 573.340 123.87 13502.16
Labor
5.26 r g/m3 · 23.55 PLN/work hour
2* –M– m3 112.270 182.57 19899.91
Plain concrete from natural aggregate
1.03m3/m3 · 177.25 PLN/work hour
3* Support materials 1.500 2.74 298.55
1.5% (from M)
Total direct costs: 33700.62 309.18 13502.16 20198.46
Total with markups: 46051.41 422.49 25852.95 20198.46
Unit price: 422.49 237.18 185.31 0.00

Summing up, it results from the research, calculations, and analyses that proper identification of the subsoil is of special importance in the case of designing an investment consisting in the construction of sewage pumping stations and sanitary sewage, especially on the soil characterized by high diversity in relation to the behavior under load. The use of appropriate technology for the construction of sewage system in the place of the occurrence of organic soils is of particular importance in order to prevent further deformation of sewage pipes. In addition to the higher costs of works, the implementation of a horizontal shutter based on the project documentation could contribute to the loss of stability of the structure and the occurrence of sewer deformations during its construction or operation.

6 Conclusion

The legal provisions in force in Poland are inconsistent and require uniformity in determining the difference between geological-engineering documentation and documentation of geotechnical subsoil research.

Incorrect interpretation of the regulations may lead to improper documentation, identification, and testing of the subsoil. Errors in the documentation result mainly from the lack of the obligation to perform subsoil tests for the majority of facilities. Therefore, these studies are very often marginalized and the funds allocated from the investment budget for this purpose are very low, which in turn leads to a significant reduction of their scope. Incorrect or incomplete subsoil test results may constitute a direct cause of nonissue of building permits, delays in the schedule and implementation of the investment, increase in the costs of the undertaking to carry out additional research and development and/or change of technology, or the occurrence of damage or failure in the resulting structures. Therefore, the solution may be to apply Eurocode 7 guidelines in the engineering practice. According to its provisions, it is required to properly design, implement, interpret, and evaluate the results of field and laboratory tests in order to properly document the subsoil conditions.

In the analyzed case, errors in the geological-engineering documentation included mainly the lack of recognition of locally occurring organic soils, the incorrectly determined location of the groundwater table, and the degree of compaction of non-cohesive soils. Early detection of the above errors contributed to the correct adoption of the sanitary sewer construction technology and the increase in the horizontal thickness of the jet grouting columns (in the range from 0.2 to 0.9 m) in the area of W4–W17, W24, BH1, and BH2 excavations. Completed calculations to check the UPL limit states showed that the load degree of utilization due to hydraulic failure with the design scheme adopted in the project was 76% to over 100%. In the case of excavations for which this index exceeded the value of 100%, the thickness of the horizontal shutter was increased in order to increase the safety level of the planned project. In complementary test in 18 per 34 test points, safety factors were exceeded, which accounted for more than 50% of test boreholes. The solutions adopted, taking into account the results of supplementary tests, prevented the difficulties with maintaining the stability of the structure and the occurrence of sewer deformations during its construction and/or operation. The adoption of the calculated values of the horizontal thickness of the apertures from the jet grouting columns increased the cost of the analyzed investment by approximately PLN 46,000. The necessity to carry out supplementary tests and the resulting change in the works technology extended the time of the planned investment by about 1 year.

The case study confirmed the need to properly document the subsoil in order to prevent the increase of costs and time of the planned investment and possible failures during construction works and during the period of operation. The most frequent cause of errors in documentation is the human factor resulting from incorrect interpretation of legal provisions, non-adjustment of the scope of subsoil diagnosis to soil conditions, and lack of experience of persons responsible for field research. The solution may be the unification of legal provisions regarding the documentation of the subsoil and the development of detailed guidelines defining the method of conducting the subsoil tests.

  1. Conflict of interest: Authors state no conflict of interest.

References

[1] Choudhury D, Sivakumar Babu GL, Towhata I. Sustainability in geotechnical engineering and related urban issues–editors’ note. Indian Geotech J. 2018;48(2):205–6.10.1007/s40098-018-0320-8Search in Google Scholar

[2] Kogut JP, Pilecka E, Szwarkowski D. Analysis of landslide effects along a road located in the Carpathian flysch. Open Geosci. 2018;10(1):517–31.10.1515/geo-2018-0041Search in Google Scholar

[3] Pilecka E, Tomaszkiewicz K. Stability analysis of the Kosciuszko Mound using terrestrial laser scanner and numerical modelling. E3S Web of Conferences. Cracow, Poland: EDP Sciences; 2018. p. 66.10.1051/e3sconf/20186601018Search in Google Scholar

[4] Abelev MY, Averin IV, Bakhronov RR, Kopteva OV. Experimental deformability characteristic studies in laboratory and field conditions. Ind Civ Eng. 2018;4:28–32.Search in Google Scholar

[5] Kumor M, Kumor Ł. Practical aspects of subsoil investigation and determination of geotechnical conditions of buildings’ foundation. GDMT Geoinżynieria Drogi Mosty Tunele. 2018;65(4):28–34.Search in Google Scholar

[6] Bogusz W, Godlewski T. Philosophy of geotechnical design in civil engineering–possibilities and risks. Bull Pol Acad Sci Tech Sci. 2019;67:2.10.24425/bpas.2019.128258Search in Google Scholar

[7] Majer E, Sokołowska M, Frankowski Z. Zasady dokumentowania geologiczno-inżynierskiego. Warszawa: PIB-PIB; 2018 (in Polish).Search in Google Scholar

[8] Ustawa prawo budowlane. Journal of Polish Laws of 1994 No. 89, item 414 (in Polish).Search in Google Scholar

[9] Ustawa prawo geologiczne i górnicze. Journal of Polish Laws of 2011, No. 163, item 981 (in Polish).Search in Google Scholar

[10] Rozporządzenie Ministra Transportu. Budownictwa i Gospodarki Morskiej z dnia 25 kwietnia 2012 roku w sprawie ustalania geotechnicznych warunków posadowienia obiektów budowlanych (Dz. U. 2012r., poz. 463). Journal of Polish Laws of 2012, item 463 (in Polish).Search in Google Scholar

[11] Rozporządzenie Ministra Środowiska z dnia 18 listopada 2016 r. w sprawie dokumentacji hydrogeologicznej i dokumentacji geologiczno – inżynierskiej. Journal of Polish Laws of 2016, item 2033 (in Polish).Search in Google Scholar

[12] Rozporządzenie Ministra Środowiska z dnia 20 grudnia 2011 r. w sprawie szczegółowych wymagań dotyczących projektów robót geologicznych, w tym robót, których wykonywanie wymaga uzyskania koncesji. Journal of Polish Laws of 2011, item 1696 (in Polish).Search in Google Scholar

[13] EN 1997-1:2004: Eurocode 7: Geotechnical design – Part 1: General rules. CEN.Search in Google Scholar

[14] PN-B-02479:1998. Dokumentowanie geotechniczne (in Polish).Search in Google Scholar

[15] Tarnawski M. Badania geologiczno-inżynierskie i geotechniczne w świetle nowych przepisów prawa geologicznego i budowlanego. Materiały XXVIII Ogólnopolskie Warsztaty Pracy Projektanta Konstrukcji, Wisła; 2013 (in Polish).Search in Google Scholar

[16] Prawo geologiczne i górnicze. Journal of Laws of 2016, item 1131 (in Polish).Search in Google Scholar

[17] Hoek E. Empirical strength criterion for rock masses. ASCE J Geotech Geoenviron Eng. 1980;106(GT9):1013–36.10.1061/AJGEB6.0001029Search in Google Scholar

[18] Juszczyk M, Kozik R, Lesniak A, Plebankiewicz E, Zima K. Errors in the preparation of design documentation in public procurement in Poland. Procedia Eng. 2014;85:283–92.10.1016/j.proeng.2014.10.553Search in Google Scholar

[19] Osiński P, Nowakowska E, Jeleniewicz K, Dohojda M, Koda E. Influence of the site investigation quality on ultimate and serviceability limit states analyses based on a case study. Acta Sci Pol Archit. 2018;17(3):47–55. 10.22630/ASPA.2018.17.3.28.Search in Google Scholar

[20] Shin EC, Jeong JP, Jeong KK. Stability analysis of underground tunnel for 2nd perimeter highway construction work in Incheon. Indian Geotech J. 2018;48:1–16.10.1007/s40098-017-0278-ySearch in Google Scholar

[21] Deere DU, Miller RP. Engineering classification and index properties for intact rock. Air force weapons laboratory technical report AFWL-TR-65-116, Kirtland Base, New Mexico; 1966.10.21236/AD0646610Search in Google Scholar

[22] Steiner W. Tunneling in squeezing rocks: case histories. Rock Mech Rock Eng. 1996;29(4):211–4.10.1007/BF01042534Search in Google Scholar

[23] Hoek E, Palmieri A. Geotechnical risks on large civil engineering projects. Proceedings of the 8th Congres IAEG. Vancouver, Canada: International Association of Engineering Geologists Congress; 1998.Search in Google Scholar

[24] Todo H. Paths to reduce failures caused by misinterpretation of ground conditions. Jpn Geotech Soc Spec Publ. 2019;6(2):13–8.10.3208/jgssp.v06.GIZ03Search in Google Scholar

[25] Goldsworthy JS, Jaksa MB, Kaggwa GWS, Fenton GA, Griffiths DV, Poulos DA. Cost of foundation failures due to limited site investigations. International Conference on Structural and Foundation Failures. Singapore: Springer; 2004. p. 398–409.Search in Google Scholar

[26] Ayedun CA, Durodola OD, Akinjare OA. An empirical ascertainment of the causes of building failure and collapse in Nigeria. Mediterr J Soc Sci. 2012;3(1):313–22.Search in Google Scholar

[27] Fagbenle OI, Oluwunmi AO. Building failure and collapse in Nigeria: the influence of the informal sector. J Sustain Dev. 2010;3(4):268–76.10.5539/jsd.v3n4p268Search in Google Scholar

[28] Oyediran IA, Julius OF. Geotechnical basis for building instability and failure: case study from lagos, Nigeria. Eng Geol Soc Territory. 2015;5:365–70.10.1007/978-3-319-09048-1_70Search in Google Scholar

[29] Faturechi R, Levenberg E, Miller-Hooks E. Evaluating and optimizing resilience of airport pavement networks. Comput Oper Res. 2014;43:335–48. 10.1016/j.cor.2013.10.009. Search in Google Scholar

[30] Chen Y, Corr JD, Durango-Cohen P. Analysis of common-cause and special-cause variation in the deterioration of transportation infrastructure: a field application of statistical process control for structural health monitoring. Transp Res Part B Methodol. 2014;59:96–116. 10.1016/j.trb.2013.11.002. Search in Google Scholar

[31] Bardel T. Stabilization of landslides – optimization of solutions or maximization of costs – case study. Sci Technol Innov. 2018;3:2.10.5604/01.3001.0012.7714Search in Google Scholar

[32] Kłosiński B. Site investigation for the design of bridge foundations – part I and II. Mosty; 2018.Search in Google Scholar

[33] Kołodziejczyk U, Kostecki J, Gontaszewska-Piekarz A, Wysokowski A. The problem of stabilization of landslides in glaciotectonically disturbed areas. Case study: road engineering structure. E3S Web Conf. 2018;45:00032.10.1051/e3sconf/20184500032Search in Google Scholar

Received: 2020-03-27
Revised: 2021-03-15
Accepted: 2021-04-06
Published Online: 2021-06-01

© 2021 Marzena Lendo-Siwicka et al., published by De Gruyter

This work is licensed under the Creative Commons Attribution 4.0 International License.

Articles in the same Issue

  1. Regular Articles
  2. Electrochemical studies of the synergistic combination effect of thymus mastichina and illicium verum essential oil extracts on the corrosion inhibition of low carbon steel in dilute acid solution
  3. Adoption of Business Intelligence to Support Cost Accounting Based Financial Systems — Case Study of XYZ Company
  4. Techno-Economic Feasibility Analysis of a Hybrid Renewable Energy Supply Options for University Buildings in Saudi Arabia
  5. Optimized design of a semimetal gasket operating in flange-bolted joints
  6. Behavior of non-reinforced and reinforced green mortar with fibers
  7. Field measurement of contact forces on rollers for a large diameter pipe conveyor
  8. Development of Smartphone-Controlled Hand and Arm Exoskeleton for Persons with Disability
  9. Investigation of saturation flow rate using video camera at signalized intersections in Jordan
  10. The features of Ni2MnIn polycrystalline Heusler alloy thin films formation by pulsed laser deposition
  11. Selection of a workpiece clamping system for computer-aided subtractive manufacturing of geometrically complex medical models
  12. Development of Solar-Powered Water Pump with 3D Printed Impeller
  13. Identifying Innovative Reliable Criteria Governing the Selection of Infrastructures Construction Project Delivery Systems
  14. Kinetics of Carbothermal Reduction Process of Different Size Phosphate Rocks
  15. Plastic forming processes of transverse non-homogeneous composite metallic sheets
  16. Accelerated aging of WPCs Based on Polypropylene and Birch plywood Sanding Dust
  17. Effect of water flow and depth on fatigue crack growth rate of underwater wet welded low carbon steel SS400
  18. Non-invasive attempts to extinguish flames with the use of high-power acoustic extinguisher
  19. Filament wound composite fatigue mechanisms investigated with full field DIC strain monitoring
  20. Structural Timber In Compartment Fires – The Timber Charring and Heat Storage Model
  21. Technical and economic aspects of starting a selected power unit at low ambient temperatures
  22. Car braking effectiveness after adaptation for drivers with motor dysfunctions
  23. Adaptation to driver-assistance systems depending on experience
  24. A SIMULINK implementation of a vector shift relay with distributed synchronous generator for engineering classes
  25. Evaluation of measurement uncertainty in a static tensile test
  26. Errors in documenting the subsoil and their impact on the investment implementation: Case study
  27. Comparison between two calculation methods for designing a stand-alone PV system according to Mosul city basemap
  28. Reduction of transport-related air pollution. A case study based on the impact of the COVID-19 pandemic on the level of NOx emissions in the city of Krakow
  29. Driver intervention performance assessment as a key aspect of L3–L4 automated vehicles deployment
  30. A new method for solving quadratic fractional programming problem in neutrosophic environment
  31. Effect of fish scales on fabrication of polyester composite material reinforcements
  32. Impact of the operation of LNG trucks on the environment
  33. The effectiveness of the AEB system in the context of the safety of vulnerable road users
  34. Errors in controlling cars cause tragic accidents involving motorcyclists
  35. Deformation of designed steel plates: An optimisation of the side hull structure using the finite element approach
  36. Thermal-strength analysis of a cross-flow heat exchanger and its design improvement
  37. Effect of thermal collector configuration on the photovoltaic heat transfer performance with 3D CFD modeling
  38. Experimental identification of the subjective reception of external stimuli during wheelchair driving
  39. Failure analysis of motorcycle shock breakers
  40. Experimental analysis of nonlinear characteristics of absorbers with wire rope isolators
  41. Experimental tests of the antiresonance vibratory mill of a sectional movement trajectory
  42. Experimental and theoretical investigation of CVT rubber belt vibrations
  43. Is the cubic parabola really the best railway transition curve?
  44. Transport properties of the new vibratory conveyor at operations in the resonance zone
  45. Assessment of resistance to permanent deformations of asphalt mixes of low air void content
  46. COVID-19 lockdown impact on CERN seismic station ambient noise levels
  47. Review Articles
  48. FMEA method in operational reliability of forest harvesters
  49. Examination of preferences in the field of mobility of the city of Pila in terms of services provided by the Municipal Transport Company in Pila
  50. Enhancement stability and color fastness of natural dye: A review
  51. Special Issue: ICE-SEAM 2019 - Part II
  52. Lane Departure Warning Estimation Using Yaw Acceleration
  53. Analysis of EMG Signals during Stance and Swing Phases for Controlling Magnetorheological Brake applications
  54. Sensor Number Optimization Using Neural Network for Ankle Foot Orthosis Equipped with Magnetorheological Brake
  55. Special Issue: Recent Advances in Civil Engineering - Part II
  56. Comparison of STM’s reliability system on the example of selected element
  57. Technical analysis of the renovation works of the wooden palace floors
  58. Special Issue: TRANSPORT 2020
  59. Simulation assessment of the half-power bandwidth method in testing shock absorbers
  60. Predictive analysis of the impact of the time of day on road accidents in Poland
  61. User’s determination of a proper method for quantifying fuel consumption of a passenger car with compression ignition engine in specific operation conditions
  62. Analysis and assessment of defectiveness of regulations for the yellow signal at the intersection
  63. Streamlining possibility of transport-supply logistics when using chosen Operations Research techniques
  64. Permissible distance – safety system of vehicles in use
  65. Study of the population in terms of knowledge about the distance between vehicles in motion
  66. UAVs in rail damage image diagnostics supported by deep-learning networks
  67. Exhaust emissions of buses LNG and Diesel in RDE tests
  68. Measurements of urban traffic parameters before and after road reconstruction
  69. The use of deep recurrent neural networks to predict performance of photovoltaic system for charging electric vehicles
  70. Analysis of dangers in the operation of city buses at the intersections
  71. Psychological factors of the transfer of control in an automated vehicle
  72. Testing and evaluation of cold-start emissions from a gasoline engine in RDE test at two different ambient temperatures
  73. Age and experience in driving a vehicle and psychomotor skills in the context of automation
  74. Consumption of gasoline in vehicles equipped with an LPG retrofit system in real driving conditions
  75. Laboratory studies of the influence of the working position of the passenger vehicle air suspension on the vibration comfort of children transported in the child restraint system
  76. Route optimization for city cleaning vehicle
  77. Efficiency of electric vehicle interior heating systems at low ambient temperatures
  78. Model-based imputation of sound level data at thoroughfare using computational intelligence
  79. Research on the combustion process in the Fiat 1.3 Multijet engine fueled with rapeseed methyl esters
  80. Overview of the method and state of hydrogenization of road transport in the world and the resulting development prospects in Poland
  81. Tribological characteristics of polymer materials used for slide bearings
  82. Car reliability analysis based on periodic technical tests
  83. Special Issue: Terotechnology 2019 - Part II
  84. DOE Application for Analysis of Tribological Properties of the Al2O3/IF-WS2 Surface Layers
  85. The effect of the impurities spaces on the quality of structural steel working at variable loads
  86. Prediction of the parameters and the hot open die elongation forging process on an 80 MN hydraulic press
  87. Special Issue: AEVEC 2020
  88. Vocational Student's Attitude and Response Towards Experiential Learning in Mechanical Engineering
  89. Virtual Laboratory to Support a Practical Learning of Micro Power Generation in Indonesian Vocational High Schools
  90. The impacts of mediating the work environment on the mode choice in work trips
  91. Utilization of K-nearest neighbor algorithm for classification of white blood cells in AML M4, M5, and M7
  92. Car braking effectiveness after adaptation for drivers with motor dysfunctions
  93. Case study: Vocational student’s knowledge and awareness level toward renewable energy in Indonesia
  94. Contribution of collaborative skill toward construction drawing skill for developing vocational course
  95. Special Issue: Annual Engineering and Vocational Education Conference - Part II
  96. Vocational teachers’ perspective toward Technological Pedagogical Vocational Knowledge
  97. Special Issue: ICIMECE 2020 - Part I
  98. Profile of system and product certification as quality infrastructure in Indonesia
  99. Prediction Model of Magnetorheological (MR) Fluid Damper Hysteresis Loop using Extreme Learning Machine Algorithm
  100. A review on the fused deposition modeling (FDM) 3D printing: Filament processing, materials, and printing parameters
  101. Facile rheological route method for LiFePO4/C cathode material production
  102. Mosque design strategy for energy and water saving
  103. Epoxy resins thermosetting for mechanical engineering
  104. Estimating the potential of wind energy resources using Weibull parameters: A case study of the coastline region of Dar es Salaam, Tanzania
  105. Special Issue: CIRMARE 2020
  106. New trends in visual inspection of buildings and structures: Study for the use of drones
  107. Special Issue: ISERT 2021
  108. Alleviate the contending issues in network operating system courses: Psychomotor and troubleshooting skill development with Raspberry Pi
  109. Special Issue: Actual Trends in Logistics and Industrial Engineering - Part II
  110. The Physical Internet: A means towards achieving global logistics sustainability
  111. Special Issue: Modern Scientific Problems in Civil Engineering - Part I
  112. Construction work cost and duration analysis with the use of agent-based modelling and simulation
  113. Corrosion rate measurement for steel sheets of a fuel tank shell being in service
  114. The influence of external environment on workers on scaffolding illustrated by UTCI
  115. Allocation of risk factors for geodetic tasks in construction schedules
  116. Pedestrian fatality risk as a function of tram impact speed
  117. Technological and organizational problems in the construction of the radiation shielding concrete and suggestions to solve: A case study
  118. Finite element analysis of train speed effect on dynamic response of steel bridge
  119. New approach to analysis of railway track dynamics – Rail head vibrations
  120. Special Issue: Trends in Logistics and Production for the 21st Century - Part I
  121. Design of production lines and logistic flows in production
  122. The planning process of transport tasks for autonomous vans
  123. Modeling of the two shuttle box system within the internal logistics system using simulation software
  124. Implementation of the logistics train in the intralogistics system: A case study
  125. Assessment of investment in electric buses: A case study of a public transport company
  126. Assessment of a robot base production using CAM programming for the FANUC control system
  127. Proposal for the flow of material and adjustments to the storage system of an external service provider
  128. The use of numerical analysis of the injection process to select the material for the injection molding
  129. Economic aspect of combined transport
  130. Solution of a production process with the application of simulation: A case study
  131. Speedometer reliability in regard to road traffic sustainability
  132. Design and construction of a scanning stand for the PU mini-acoustic sensor
  133. Utilization of intelligent vehicle units for train set dispatching
  134. Special Issue: ICRTEEC - 2021 - Part I
  135. LVRT enhancement of DFIG-driven wind system using feed-forward neuro-sliding mode control
  136. Special Issue: Automation in Finland 2021 - Part I
  137. Prediction of future paths of mobile objects using path library
  138. Model predictive control for a multiple injection combustion model
  139. Model-based on-board post-injection control development for marine diesel engine
  140. Intelligent temporal analysis of coronavirus statistical data
Downloaded on 8.9.2025 from https://www.degruyterbrill.com/document/doi/10.1515/eng-2021-0074/html
Scroll to top button