Abstract
In the construction industry, time overrun in construction projects has become a global phenomenon. In Iraq, this problem is very considerable where a high percentage of projects are completed behind schedule, causing a large negative impact on society on the one side and the economic impact on the other side of the country. This study aims to define the major factors that cause construction project’s time overrun by studying delay causes of projects and performing a number of interviews with a group of specialists in project construction. Next, a questionnaire is used to obtain responses from 115 participants in the city of Najaf. In addition, agreement analysis is performed to ensure that the arranged rankings by all involved respondents’ categories are not ordered by coincidence, and the Chi-squared test is put to use as well to mark the agreement or disagreement context among the respondent category rankings. The target respondents of the study included: clients, consultants, project managers, contractors, and engineers who have an experience in project management and construction. The findings of the study revealed that the top five most essential factors causing delay in public construction projects are global and local economic crises, bureaucracy and corruption, public holidays, delay in getting governmental permits, and issuing numerous change orders by owners. Moreover, eight components are extracted from the 45 questionnaire items put to use for factor analysis. Among the extracted factors are the inaccuracy of tendering process, technical performance management, and government interferences.
1 Introduction
Construction projects, delay has been defined in various ways by different authors. Barmble and Callahan [1] defined construction delay as the time period through which some construction project parts have not been performed or extended due to expected situations. Aibinu and Jagboro [2] defined the delay as a circumstance where the project client and contractor separately or jointly share the noncompletion state of the project within the agreed, stipulated, or original contract time period. Construction delay was defined by Assaf and Al-Hejji [3] as the construction time overrun either beyond the specified completion date or beyond the agreed date by the project parties for the project delivery. Bekr [4] defined construction delay as exceeding or extension of the time period that is already agreed upon between the project owner and contractor to complete and deliver the project. In other words, construction delay may be defined as a failure to deliver the project within the agreed deadline between the project client and contractor because of defined and undefined causes. Construction delay is one of the large events in the construction industry that could occur simultaneously with the other delays, influencing directly the completion time of projects. In fact, numerous construction projects experience delays exceeding the initial time estimates. These delays rise an adverse impact on the project’s success in terms of time, cost, and quality. Construction delays cause troublesome for all involved parties in project construction where they could result in all of the claims, desertion, construction sector with slow growth, disputes, availability reduction of economic resources, and competition decrease [5]. Thus, it became important to eliminate the time overrun phenomenon by obtaining a clear idea regarding factors that cause delay for construction projects and oppose project’s success to failure. Depending on that, this study is conducted to fill the gap by developing a framework for identifying, analyzing, and grouping the causes of time overruns in construction projects in Iraq after considering different points of view of clients, consultants, project managers, contractors, and engineers. Classification of time overrun factors is carried out by using factor analysis where a casually established structure is made by underlying delay factors. Hence, insight into the major delay causes of construction projects from all engaged parties in project management and construction is provided. Moreover, the existent statements and affirmations that indicate an adjustment or opinion relative to the concept of delay causes of projects are tested and validated. In addition, the main goal of this study is to identify the critical factors that impact the Ira construction project’s performance and cause delay, group the defined factors into a cluster by using factor analysis, and then test the degree of agreement of the project delay factor rankings.
2 Literature review
2.1 A brief overview of Iraq construction industry
In the last few decades, Iraq has exposed into nationwide wars, causing a complete destruction in its economy and infrastructure, motivating Iraq government to pay more attention to the construction industry. Since 2008, Iraq witnessed a considerable growth in infrastructure construction and reconstruction projects. Iraq’s economy continued to grow as a result of the occurring growth in the oil sector where oil revenue contributes to the largest portion of revenue for the Iraqi government, resulting in booming all of urbanization and infrastructure development [6]. Then, the Iraqi government kept financing infrastructure projects till 2014 when big parts of Iraq were invaded by Islamic state of Iraq and Syria (ISIS), causing chaos in both economical and political situations of the country. So, ISIS was the first reason for slowing Iraq’s infrastructure. The other reason for infrastructure construction and reconstruction deceleration is the Iraqi government’s dependence mainly upon oil revenue for the country’s economy, therefore construction industry does not impact impressively on its economy [7]. Hence, coronavirus disease (COVID-19) and ISIS caused a decrease in oil revenue; that is why the Iraq government revealed an austerity policy and transferred large amounts of money predestined to finance infrastructure projects to cover medical and war expenses. These exceptionally developed situations created highly negative influences on the Iraq construction industry where many construction projects were suspended due to the shortage of funds [8]. After defeating ISIS, the Iraq government started again funding a number of infrastructure projects. As a consequence, the necessity of this study comes here to overwhelm the main delay causes of Iraq’s public projects and to stop wasting more time.
2.2 Previous studies regarding delay factors of construction projects
Many studies have defined different causes for delay of construction projects, which is reviewed and outlined in this section to constitute a theoretical framework where questionnaire items can be established. Danso et al. [9] investigated the influencing factors on time overruns in telecom tower projects in Ghana. They found that the main impacting factors for delay in telecom tower projects are delay of issuing payment certificates by clients, unrealistic requirements of clients, shortage of tower materials in markets, delay in providing design information and modifications of contract, inferior workmanship, inferior site management, contractor’s unethical behavior for gaining high profit, inflexible attitudes among the involved parties, construction engineers with inadequate experience, main dispute on project site, changes in design scope, shortage of quality control, poor managerial skills, and inferior management for the contract by consultants. Doloi et al. [10] executed a study for defining the key causes influencing time overruns in Indian construction projects. The most crucial factors of the Indian construction industry were defined as follows: a shortage of commitment, poor management of the site, inferior project site conditions, inefficient planning, clarity shortage in project scope, inadequate communication, and below-standard contracts. Gündüz et al. [11] explored causes of delays in construction projects in Turkey. They investigated the impact of 83 various delay causes in their study. The highly most influencing factors for delays were found as follows: inadequate experience of contractors, ineffective planning and scheduling of construction projects, inferior management for site and supervision, design changes, material late delivery, undependable subcontractors, late inspection and testing performance, poor skill workers, change orders, late site delivery, late approval of design documents, late payments, late decision making, inferior coordination and communication among the parties of projects, and unforeseen of surface and subsurface soil conditions. Marzouk et al. [12] investigated delay causes in Egyptian Civil Engineering projects. The specified top ten delay causes of projects are: not efficient planning and scheduling, inferior management of site and supervision, change orders, problems in projects financing by contractors, project awarding to the lowest bidder, low productivity of labors, impacts of subsurface conditions, late work delivery by subcontractors, lack of materials, and less-qualified workers. Khoshgoftar et al. [13] searched for causes of delays in construction projects in Iran. The key causes for delays defined in their study included: difficulties in financing the completed work, poor planning, management of site, management of contract, and shortage of communication between the project parties. Lindhard et al. [14] explored the causes of delays in the construction industry. In their conducted study, they revealed the six often most happening reasons to delay, which are connecting work, variation in the work plans, manpower, external conditions, construction design, and materials. Enshassi et al. [15] explored the most impacting factors on delays in construction projects in Gaza Strip. The revealed highly critical factors of delay in construction projects are as follows: strikes, closures of borders, materials shortage in markets and on sites, late delivery of materials to the construction sites, problems of cash flow, and inferior site management. Bajjou et al. [16] executed a study to specify the crucial factors of project delays in Moroccan construction study. The determined top ten factors causing for delays are late progress payments, employees with inadequate training, waste management without a strategy, unrealistic project duration set by clients, rework construction due to errors, extreme subcontracting, slowness in getting permits from governmental institutes, poor planning and scheduling, a shortage of collective planning, and workforce with no skills. Mahdi and Soliman [17] investigated the most significant causes of delay in all Arabic Gulf countries. The carried out analysis by them showed that there are 14 causes of delay in the gulf area, and the majority of delay factors comprises lack of resources, poor team management, inferior site management, unavailability of workforce and construction materials, difficulties in getting approvals from government institutions, and financial problems. Rachid et al. [18] searched the time overrun causes of construction projects in Algeria. They defined 59 delay causes in their study. The most important five causes of delay are slowness of change orders, unrealistic duration of the contract, slow variation orders of the additional quantities, slow progress payments, and inferior planning and scheduling. Mohamad et al. [19] investigated the time extension of projects in Malaysia. In their study, 16 causes of delay were defined. The most impacting causes are unavailability of skilled workers, a shortage of resources and manpower, change orders, drawing amendments, and slowness in making decisions. Indhu and Yogeswari [20] carried out a study to specify the inappropriate delay factors of construction equipment and their influence on the progress of construction projects in India. The main key factors that are defined in their study comprised incorrect management of inventory, equipment non-replacement, and unsound selection of equipment. These factors caused the firm to loss its reputation. As it is obvious from the previous review that factors causing the delay in different types of construction projects in the worldwide are available and discussed in numerous studies. A high percentage of the published studies have adopted the approach of questionnaire to get data from respondents. Anyhow, the substantial factors are extensively perceived to be the causes of construction projects delay. In addition, what was more observed is that there is a less coverage regarding time overrun factors in Iraq construction projects. Therefore, this study is intended to participate in this consideration by identifying the noticed knowledge gap.
3 Methodology
The used data for this study were gathered from various categories like contractors, project managers, engineers, consultants, and clients. Project managers (PMs), contractors, and engineers were chosen after checking their profiles and reviewing their experience in executing projects in Iraq by using LinkedIn and by going to the websites of the target audience. To assure that the obtained data are valid and reliable, only members of active companies were targeted. The targeted consultants for this study were selected from the engineering staff of the University of Kufa where they are members of the Engineering Consultant Bureau in the College of Engineering. Clients were chosen from ministries, agencies, and departments that are engaged in construction projects. The collection process of data was managed by adopting three phases sequential approach: literature review, interview, and questionnaire (Figure 1). A preliminary review was executed to define the delay causes of projects. This stage was followed by an interview with a number of clients, consultants, contractors, PMs, and engineers. The exact number of respondents needed for the interview was not specified at the start of the study, but then it was arrived when the obtained data have been optimized where no new information come out from participants [21]. The major purpose of conducting an interview was to recognize construction projects, delay causes within the Iraqi local context. This step was carried out depending on the reality that construction projects are unique [22], factors causing for delay of a project may differ from a project to another based on the settings of sociocultural [23], the geographical location of the project [24], the used criteria for assessing [22], and who is evaluating the construction project [25]. Therefore, it was assumed that factors that may cause delay to construction projects within the Iraq government construction projects may vary. The questionnaire included two main parts: the first part was formulated to obtain the personal characteristics of respondents like years of experience, academic qualification, and professional qualification. In the second part, the target respondents were asked to rate how the 45 variables have contributed in the past construction delays of projects in Iraq by using a five-point Likert scale, where 5 = strongly agree, 4 = agree, 3 = neutral, 2 = disagree, and 1 = strongly disagree. The collected data were analyzed by using conclusive and descriptive statistical tools. The conclusive tools included using statistical package for the social sciences (SPSS) to calculate the relative importance index (RII), to rank the 45 delay causes of projects, and to carry out a factor analysis on the 45 causes of delay by utilizing rotation method, varimax with Kaiser normalization. The used descriptive tools comprise tables, standard deviation, mean, and percentages. Two approaches were applied to calculate the needed sample size for this study. The first approach comprised carrying out Yamane’s formula to compute the required sample size of respondents [26]. By checking the number of active working and registered construction companies with the Companies’ Register Authority in Najaf city, the number of active companies was found to be 992 companies (
where
where

Methodology.
4 Results
4.1 Respondent demographic survey
The personal characteristics of 115 respondents who sent back valid questionnaires are included in Table 1.
Respondent demographic survey
Variable | Category | Frequency | Percentage |
---|---|---|---|
Category of respondents | Client | 8 | 6.96 |
Consultant | 18 | 15.65 | |
PM | 15 | 13 | |
Contractor | 19 | 16.52 | |
Engineer | 55 | 47.83 | |
Total | 115 | 100 | |
Highest level of education | Doctorate | 9 | 7.83 |
Master | 25 | 21.74 | |
Bachelor | 78 | 67.83 | |
No degree | 3 | 2.61 | |
Total | 115 | 100 | |
Years of experience | Less than 5 | 16 | 13.91 |
5–10 | 20 | 17.39 | |
10–20 | 41 | 35.65 | |
20–30 | 25 | 21.74 | |
30–40 | 8 | 6.96 | |
Above 40 | 5 | 4.35 | |
Total | 115 | 100 |
4.2 Preliminary examination
It is a necessity to check if the study construct provides the analysis required standards before proceeding with the other developed study calculations. Thus, three checks are carried out for the study, which are: reliability, validity, and normality. To investigate the reliability of the questionnaire items, Cronbach’s alpha
Cronbach’s alpha formula:
where
For the 45 items, Cronbach’s alpha was computed and found equals to 0.97, which is above the recommended threshold of 0.7 [29]. Also, acquiring Cronbach’s alpha of 0.97 means that excellent consistency is existing in the measurement. To make sure that the subject under examination is measured by the prepared questionnaire, a validity check is needed. This check is performed by conducting a review of the referring literature and through carrying out contents investigation by a number of clients, consultants, contractors, engineers, and project managers. The adjustments and comments of the target participants on the contents of the questionary survey assured the validity of the contents. The normality of the 45 items was investigated by performing Skewness and Kurtosis tests. Chan et al. [30] revealed that a distribution is normal when Skewness and Kurtosis values are zero; hence, the obtained Skewness and Kurtosis values are testified against the null hypothesis of zero. The values of
Analysis outputs of delay causes of construction projects
Variables | Mean | SD | Skewness | Kurtosis | ||
---|---|---|---|---|---|---|
Statistic Std. error | Statistic Std. error | |||||
DPPC | 3.23 | 1.39 |
|
0.226 |
|
0.447 |
DDCSC | 2.75 | 1.337 | 0.273 | 0.226 |
|
0.447 |
IMCOC | 3.43 | 0.965 |
|
0.226 |
|
0.447 |
PCCCOP | 2.95 | 1.375 | 0.013 | 0.226 |
|
0.447 |
SMD | 3.25 | 1.498 |
|
0.226 |
|
0.447 |
WSC | 3.05 | 1.123 |
|
0.226 |
|
0.447 |
TPBA | 3.38 | 1.387 |
|
0.226 |
|
0.447 |
PASD | 2.67 | 1.09 | 0.361 | 0.226 |
|
0.447 |
MIDD | 3.1 | 1.489 |
|
0.226 |
|
0.447 |
DIDD | 2.97 | 1.357 |
|
0.226 |
|
0.447 |
CSSPQ | 3.02 | 1.481 |
|
0.226 |
|
0.447 |
ITPC | 3.05 | 1.572 |
|
0.226 |
|
0.447 |
CPD | 3.3 | 1.044 |
|
0.226 |
|
0.447 |
DPFC | 3.28 | 1.478 |
|
0.226 |
|
0.447 |
REC | 3.43 | 1.093 |
|
0.226 |
|
0.447 |
ISMSC | 3 | 1.331 |
|
0.226 |
|
0.447 |
PPSPC | 3.14 | 1.344 |
|
0.226 |
|
0.447 |
ICM | 2.93 | 1.336 |
|
0.226 |
|
0.447 |
FCSIW | 3.34 | 1.22 |
|
0.226 |
|
0.447 |
CTSIQ | 2.94 | 1.434 |
|
0.226 |
|
0.447 |
DPFLTC | 2.59 | 1.206 | 0.438 | 0.226 |
|
0.447 |
MLSM | 2.5 | 1.18 | 0.625 | 0.226 |
|
0.447 |
LDM | 2.7 | 1.251 | 0.242 | 0.226 |
|
0.447 |
CTSMC | 2.93 | 1.153 |
|
0.226 |
|
0.447 |
SFMSANTM | 2.79 | 0.996 | 0.161 | 0.226 |
|
0.447 |
CMP | 3.2 | 1.179 |
|
0.226 |
|
0.447 |
DL | 2.53 | 1.126 | 0.56 | 0.226 |
|
0.447 |
UW | 2.93 | 1.381 |
|
0.226 |
|
0.447 |
LPL | 3.09 | 1.341 |
|
0.226 |
|
0.447 |
CLP | 2.61 | 1.282 | 0.364 | 0.226 |
|
0.447 |
DWWSSC | 3.22 | 1.066 |
|
0.226 |
|
0.447 |
EB | 2.57 | 1.068 | 0.397 | 0.226 |
|
0.447 |
EOPS | 2.32 | 1.031 | 0.638 | 0.226 |
|
0.447 |
IEPE | 2.47 | 1.02 | 0.26 | 0.226 |
|
0.447 |
SE | 2.54 | 1.062 | 0.209 | 0.226 |
|
0.447 |
ISC | 2.96 | 1.046 |
|
0.226 |
|
0.447 |
IWC | 2.97 | 0.912 |
|
0.226 |
|
0.447 |
DGPM | 3.5 | 1.334 |
|
0.226 |
|
0.447 |
TCRJS | 2.98 | 1.108 | 0.114 | 0.226 |
|
0.447 |
AC | 2.82 | 1.048 | 0.095 | 0.226 |
|
0.447 |
CGRL | 3.18 | 1.189 |
|
0.226 |
|
0.447 |
PH | 3.57 | 1.14 |
|
0.226 |
|
0.447 |
BC | 3.68 | 1.536 |
|
0.226 |
|
0.447 |
GLED | 3.7 | 1.061 |
|
0.226 |
|
0.447 |
DILTR | 2.9 | 1.235 |
|
0.226 |
|
0.447 |
Abbreviations list
Abbreviation | Variables |
---|---|
DPPC | Delay in progress payments by clients |
DDCSC | Delay in delivering the construction sites to contractors |
IMCOC | Issuing many change orders by clients |
PCCCOP | Poor communication and coordination between clients and other parties |
SMD | Slowness in making decisions |
WSC | Work suspension by clients |
TPBA | Type of project bidding and award |
PASD | Project award with short duration |
MIDD | Mistakes and inconsistencies in the design documents |
DIDD | Delays in issuing design documents |
CSSPQ | Clients’ supervision staff with poor qualification |
ITPC | Inaccuracy in tender preparation by clients |
CPD | Changing in the project design |
DPFC | Difficulties in projects financing by contractors |
REC | Rework due to error during construction |
ISMSC | Inferior site management and supervision by contractors |
PPSPC | Poor planning and scheduling of projects by contractors |
ICM | Inappropriate construction methods |
FCSIW | Frequent changes for subcontractors due to their incompetent work |
CTSIQ | Contractors technical staff with inferior qualification |
DPFLTC | Delay in performing field and laboratory tests by contractors |
MLSM | Materials lack on site or market |
LDM | Late delivery of materials |
CTSMC | Changes in the types and specifications of materials during construction |
SFMSANTM | Slowness in finishing materials selection due to the availability of numerous types in markets |
CMP | Changes in the materials prices |
DL | Deficiency of labors |
UW | Unqualified workforce |
LPL | Low productivity of labor |
CLP | Conflicts among labor personnel |
DWWSSC | Difficulties of workforce to work in some sites due to security conditions |
EB | Equipment breakdown |
EOPS | Equipment operators with poor skills |
IEPE | Inferior efficiency and productivity of equipment |
SE | Shortage of equipment |
ISC | Impacts of subsurface conditions |
IWC | Influences of weather conditions |
DGPM | Delays in getting permits from municipality |
TCRJS | Traffic control and restriction at job site |
AC | Accidents during construction |
CGRL | Changes in governmental regulations and laws |
PH | Public holidays |
BC | Bureaucracy and Corruption |
GLED | Global and local economic disaster |
DILTR | Delay in Issuing laboratorial test results |
4.3 Ranking of public project delay causes
The provided respondents’ rankings on the delay causes of Iraq public construction projects are assessed in this section. The participants ranked the 45 delay causes of the questionnaire of construction projects by using a five-point Likert Scale. The utilized process is aimed at specifying the relative importance of various factors identified as being the major reasons for the delay in construction projects. The RII is computed by applying formula (4) [31,32]:
where RII is the relative importance index,
RII and ranks of delay causes of construction projects
Variables | Client | Consultant | PM | Contractor | Engineer | OverallRank | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
RII | Rank | RII | Rank | RII | Rank | RII | Rank | RII | Rank | RII | Rank | |
DPPC | 0.775 | 4 | 0.733 | 5 | 0.64 | 15 | 0.747 | 5 | 0.564 | 17 | 0.645 | 12 |
DDCSC | 0.575 | 11 | 0.589 | 15 | 0.627 | 16 | 0.568 | 18 | 0.505 | 28 | 0.55 | 35 |
IMCOC | 0.725 | 6 | 0.689 | 9 | 0.72 | 9 | 0.768 | 4 | 0.644 | 5 | 0.687 | 5 |
PCCCOP | 0.8 | 3 | 0.633 | 11 | 0.667 | 13 | 0.621 | 13 | 0.513 | 27 | 0.59 | 27 |
SMD | 0.825 | 2 | 0.767 | 3 | 0.76 | 6 | 0.684 | 8 | 0.545 | 22 | 0.65 | 11 |
WSC | 0.575 | 11 | 0.622 | 12 | 0.707 | 10 | 0.663 | 10 | 0.567 | 16 | 0.61 | 19 |
TPBA | 0.625 | 9 | 0.844 | 1 | 0.773 | 5 | 0.632 | 12 | 0.618 | 8 | 0.677 | 7 |
PASD | 0.525 | 13 | 0.556 | 18 | 0.613 | 17 | 0.589 | 16 | 0.487 | 31 | 0.534 | 37 |
MIDD | 0.825 | 2 | 0.722 | 6 | 0.68 | 12 | 0.684 | 8 | 0.52 | 25 | 0.621 | 17 |
DIDD | 0.775 | 4 | 0.567 | 17 | 0.707 | 10 | 0.674 | 9 | 0.516 | 26 | 0.593 | 25 |
CSSPQ | 0.775 | 4 | 0.711 | 7 | 0.72 | 9 | 0.6 | 15 | 0.513 | 27 | 0.603 | 21 |
ITPC | 0.775 | 4 | 0.689 | 9 | 0.68 | 12 | 0.684 | 8 | 0.516 | 26 | 0.61 | 19 |
CPD | 0.7 | 7 | 0.7 | 8 | 0.72 | 9 | 0.705 | 6 | 0.611 | 9 | 0.661 | 9 |
DPFC | 0.7 | 7 | 0.8 | 2 | 0.813 | 3 | 0.663 | 10 | 0.556 | 19 | 0.656 | 10 |
REC | 0.55 | 12 | 0.722 | 6 | 0.773 | 5 | 0.621 | 13 | 0.691 | 2 | 0.685 | 6 |
ISMSC | 0.6 | 10 | 0.711 | 7 | 0.76 | 6 | 0.537 | 20 | 0.545 | 22 | 0.6 | 22 |
PPSPC | 0.625 | 9 | 0.756 | 4 | 0.747 | 7 | 0.611 | 14 | 0.56 | 18 | 0.628 | 16 |
ICM | 0.6 | 10 | 0.7 | 8 | 0.733 | 8 | 0.526 | 21 | 0.527 | 23 | 0.586 | 29 |
FCSIW | 0.725 | 6 | 0.8 | 2 | 0.813 | 3 | 0.589 | 16 | 0.604 | 10 | 0.668 | 8 |
CTSIQ | 0.6 | 10 | 0.733 | 5 | 0.76 | 6 | 0.558 | 19 | 0.502 | 29 | 0.588 | 28 |
DPFLTC | 0.475 | 15 | 0.611 | 13 | 0.6 | 18 | 0.505 | 22 | 0.476 | 33 | 0.518 | 39 |
MLSM | 0.525 | 13 | 0.456 | 24 | 0.72 | 9 | 0.474 | 23 | 0.462 | 35 | 0.501 | 43 |
LDM | 0.55 | 12 | 0.533 | 19 | 0.693 | 11 | 0.526 | 21 | 0.502 | 29 | 0.539 | 36 |
CTSMC | 0.575 | 11 | 0.611 | 13 | 0.693 | 11 | 0.579 | 17 | 0.553 | 20 | 0.586 | 29 |
SFMSANTM | 0.55 | 12 | 0.533 | 19 | 0.613 | 17 | 0.568 | 18 | 0.549 | 21 | 0.558 | 34 |
CMP | 0.75 | 5 | 0.611 | 13 | 0.787 | 4 | 0.663 | 10 | 0.585 | 12 | 0.64 | 14 |
DL | 0.675 | 8 | 0.478 | 22 | 0.587 | 19 | 0.558 | 19 | 0.451 | 36 | 0.506 | 42 |
UW | 0.675 | 8 | 0.611 | 13 | 0.733 | 8 | 0.589 | 16 | 0.524 | 24 | 0.586 | 29 |
LPL | 0.625 | 9 | 0.7 | 8 | 0.72 | 9 | 0.653 | 11 | 0.549 | 21 | 0.617 | 18 |
CLP | 0.575 | 11 | 0.578 | 16 | 0.693 | 11 | 0.432 | 26 | 0.48 | 32 | 0.522 | 38 |
DWWSSC | 0.6 | 10 | 0.644 | 10 | 0.76 | 6 | 0.558 | 19 | 0.647 | 4 | 0.643 | 13 |
EB | 0.5 | 14 | 0.478 | 22 | 0.653 | 14 | 0.505 | 22 | 0.495 | 30 | 0.515 | 40 |
EOPS | 0.525 | 13 | 0.467 | 23 | 0.6 | 18 | 0.442 | 25 | 0.425 | 37 | 0.464 | 45 |
IEPE | 0.525 | 13 | 0.478 | 22 | 0.627 | 16 | 0.453 | 24 | 0.473 | 34 | 0.494 | 44 |
SE | 0.525 | 13 | 0.522 | 20 | 0.64 | 15 | 0.474 | 23 | 0.476 | 33 | 0.508 | 41 |
ISC | 0.6 | 10 | 0.644 | 10 | 0.613 | 17 | 0.568 | 18 | 0.575 | 15 | 0.591 | 26 |
IWC | 0.625 | 9 | 0.567 | 17 | 0.613 | 17 | 0.579 | 17 | 0.6 | 11 | 0.595 | 24 |
DGPM | 0.8 | 3 | 0.733 | 5 | 0.787 | 4 | 0.747 | 5 | 0.636 | 6 | 0.701 | 4 |
TCRJS | 0.625 | 9 | 0.567 | 17 | 0.64 | 15 | 0.632 | 12 | 0.578 | 14 | 0.597 | 23 |
AC | 0.525 | 13 | 0.511 | 21 | 0.573 | 20 | 0.568 | 18 | 0.582 | 13 | 0.563 | 33 |
CGRL | 0.725 | 6 | 0.622 | 12 | 0.653 | 14 | 0.695 | 7 | 0.604 | 10 | 0.637 | 15 |
PH | 0.775 | 4 | 0.689 | 9 | 0.84 | 2 | 0.779 | 3 | 0.658 | 3 | 0.715 | 3 |
BC | 0.875 | 1 | 0.767 | 3 | 0.853 | 1 | 0.853 | 1 | 0.633 | 7 | 0.736 | 2 |
GLED | 0.75 | 5 | 0.722 | 6 | 0.853 | 1 | 0.789 | 2 | 0.695 | 1 | 0.739 | 1 |
DILTR | 0.625 | 9 | 0.6 | 14 | 0.6 | 18 | 0.611 | 14 | 0.553 | 20 | 0.581 | 32 |
As it is clear from Tables 2 and 4, the target participants ranked “global and local economic crisis” with a mean value of 3.70 as the most critical cause for delay in construction projects in Iraq. This is followed by “Bureaucracy and Corruption” with a mean value of 3.68 as the second highly severe delay cause, while “public holidays” with a mean of 3.57 was ranked third. The top ten rankings for time overrun causes according to the order of importance are as follows.
Global and local economic crises, Bureaucracy and corruption, public holidays, delays in getting permits from municipality, issuing many change orders by clients, rework due to errors during construction, type of project biding and award (the lowest bidder), frequent changes for subcontractors due to their incompetent work, changing in the project design, and difficulties in projects financing by contractors.
Moreover, the computed indexes are ranked for all target respondent categories. The main purpose of investigating all respondent rankings is to identify the highly crucial delay causes from various perspectives according to the respondent categories. Thus, as it is included in Table 4, clients ranked “bureaucracy and corruption” as the most severe time overrun cause, followed by “slowness in making decisions” (ranked second), while “poor communication and coordination between clients and other parties” and “delays in getting permits from municipality” are ranked third. Consultants ranked “type of project bidding and award (the lowest bidder)” as the highest delay cause, succeeded by “difficulties in projects financing by contractors” and “Frequent changes for subcontractors due to their incompetent work” ranked second, while “slowness in making decisions” and “bureaucracy and corruption” were ranked third. PMs ranked first all of “global and local economic disaster” and “bureaucracy and corruption,” ranked second “public holidays,” and ranked third all of “difficulties in projects financing by contractors” and “frequent changes for subcontractors due to their incompetent work.” Contractors ranked “bureaucracy and corruption” as the most critical delay cause, ranked “global and local economic disaster” as the top second crucial delay cause, and “public holidays” was ranked third. Engineers ranked “global and local economic disaster” as the most severe delay cause, followed by “rework due to errors during construction” (ranked to No. 2), while “public holidays” was ranked third.
4.4 Agreement analysis
To confirm that the provided rankings by all involved respondents’ categories: clients, consultants, project managers, contractors, and engineers are not ordered by coincidence or partiality, but these rankings represent the real and true causes of delay in construction projects in Iraq. For that purpose, two methods are carried out: Spearman rank correlation coefficient and Kendall’s coefficient of concordance.
Spearman rank correlation coefficient can be computed by applying the following equation [33]:
where
Spearman rank correlation coefficients of overall categories of respondents
Respondent category | Values of Spearman rank correlation coefficient |
---|---|
Client-Consultant | 0.891 |
Client-PM | 0.918 |
Client-Contractor | 0.849 |
Client-Engineer | 0.359 |
Consultant-PM | 0.932 |
Consultant-Contractor | 0.882 |
Consultant-Engineer | 0.593 |
PM-Contractor | 0.849 |
PM-Engineer | 0.527 |
Contractor-Engineer | 0.739 |
From the contents of Table 5, it is obvious that the calculated coefficients are strong and positive, which show a high harmonization between all respondent categories’ ranks. The highest harmonization pairs are “consultant-PM,” “client-PM,” and “client-consultant.” In case there is a necessity to constitute a level of agreement between the categories of respondents by adopting a single coefficient, then the significance of the second check of Kendall’s coefficient of concordance (W) comes out. Legendre [34] stated that Kendall’s coefficient is directly related to the Spearman rank correlation coefficient. Kendall’s coefficient can be calculated by computing the mean of Spearman correlations pairwise by carrying out the following equation [35]:
where
The computation of Kendall’s coefficient is 0.803; that means there is a harmonization in a high degree among the categories of all respondents on the time overruns causes of construction projects in Iraq.
4.5 Significance test
The Chi-squared test is put to use to mark the agreement or disagreement context among the respondent categories rankings is considerable statistically. Two hypotheses are put for the
where
The calculation output of Chi-squared test is 176.66. Then, by using the critical table for
4.6 Classification of delay factors
Factor analysis has been put to use to examine the relations among the 45 delay factors used for this study. The used extraction method for this analysis is principal component analysis to group causes of delay in Iraq construction projects into less number of groups. Before conducting factor analysis, a preparative check was performed by utilizing Kaiser–Meyer–Olkin (KMO) and Bartlett’s tests to investigate the suitability of the gathered data for factor analysis. The main advantage of using Bartlett’s test is to ensure the correlation matrix identity while the KMO test measures the sample adequacy where the data significance value should not be less than 0.5 to be satisfactory for factor analysis [37]. The findings of Bartlett and KMO tests are comprised in Table 6. The outputs of the performed tests included in Table 6 show that the adequacy of KMO measure of sampling is 0.917, which is above 0.5, assuring the appropriateness of data for factor analysis. Moreover, a significance value of 0.000, which is below 0.5 where it indicates the excellence of the measure and confirms the identity of the correlation matrix [38]. An eight-component model was extracted from 45 items of time overruns in construction projects in Iraq for a sample of 115 respondents. The extracted components comprise 73.647% of the responses’ variance. Results of the total variance for the delay factors of construction projects are included in Table 7. The component transformation matrix for the eight extracted components is comprised in Table 8. As it is obvious from Table 8 that most of the correlation coefficients are above the recommended level of 0.3 [39]. Furthermore, a rotated component matrix is included in Table 9 where all contained loading factors are more than 0.4.
KMO and Bartlett’s tests for the study delay factors
Kaiser-Meyer-Olkin measure of sampling adequacy | 0.917 | |
---|---|---|
Bartlett’s test of sphericity | Approx. Chi-square | 4743.502 |
df | 990 | |
Sig. | 0 |
Findings of overall variance illustrated for factors of project delay
Component | Initial eigenvalues | Rotation sums of square loadings | ||||
---|---|---|---|---|---|---|
Total | % of variance | Cumulative | Total | % of variance | Cumulative | |
1 | 20.011 | 44.469 | 44.469 | 12.789 | 28.421 | 28.421 |
2 | 4.499 | 9.998 | 54.467 | 7.687 | 17.083 | 45.504 |
3 | 2.251 | 5.002 | 59.469 | 4.009 | 8.909 | 54.413 |
4 | 1.548 | 3.439 | 62.909 | 1.983 | 4.407 | 58.82 |
5 | 1.329 | 2.953 | 65.862 | 1.944 | 4.319 | 63.139 |
6 | 1.248 | 2.774 | 68.636 | 1.894 | 4.209 | 67.348 |
7 | 1.172 | 2.604 | 71.24 | 1.446 | 3.214 | 70.562 |
8 | 1.083 | 2.407 | 73.647 | 1.388 | 3.085 | 73.647 |
Component transformation matrix for the eight excerpted components
Component | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
---|---|---|---|---|---|---|---|---|
1 | 0.737 | 0.533 | 0.309 | 0.129 | 0.159 | 0.175 | 0.052 | 0.033 |
2 |
|
0.523 | 0.36 | 0.34 | 0.145 | 0.091 |
|
0.163 |
3 | 0.032 |
|
0.737 | 0.27 |
|
0.002 | 0.25 |
|
4 |
|
|
|
|
0.453 | 0.629 | 0.449 |
|
5 | 0.075 |
|
|
0.448 | 0.33 |
|
0.415 | 0.632 |
6 | 0.021 |
|
0.371 |
|
0.705 |
|
|
0.07 |
7 | 0.131 |
|
|
0.629 | 0.11 | 0.232 |
|
|
8 |
|
0.169 |
|
0.283 | 0.202 |
|
0.251 |
|
Factor analysis outputs of the factor loadings
Variables | Component | |||||||
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
ITPC | 0.887 | |||||||
CSSPQ | 0.846 | |||||||
MIDD | 0.834 | |||||||
SMD | 0.833 | |||||||
DPFC | 0.797 | |||||||
DPPC | 0.793 | |||||||
PPSPC | 0.759 | |||||||
DIDD | 0.732 | |||||||
PCCCOP | 0.725 | |||||||
DDCSC | 0.72 | |||||||
BC | 0.713 | |||||||
ISMSC | 0.701 | |||||||
ICM | 0.685 | |||||||
DGPM | 0.67 | |||||||
TPBA | 0.667 | |||||||
CTSIQ | 0.66 | |||||||
WSC | 0.646 | |||||||
LPL | 0.636 | |||||||
CPD | 0.591 | |||||||
UW | 0.51 | |||||||
IEPE | 0.879 | |||||||
EOPS | 0.827 | |||||||
SE | 0.821 | |||||||
EB | 0.751 | |||||||
CLP | 0.654 | |||||||
DPFLTC | 0.654 | |||||||
LDM | 0.641 | |||||||
MLSM | 0.636 | |||||||
DILTR | 0.511 | |||||||
CGRL | 0.717 | |||||||
GLED | 0.658 | |||||||
AC | 0.623 | |||||||
CMP | 0.614 | |||||||
TCRJS | 0.6 | |||||||
PH | 0.555 | |||||||
IWC | 0.818 | |||||||
ISC | 0.711 | |||||||
REC | 0.814 | |||||||
CTSMC | 0.524 | |||||||
FCSIW | 0.5 | |||||||
SFMSANTM | 0.668 | |||||||
DL | 0.622 | |||||||
PASD | 0.665 | |||||||
DWWSSC | 0.639 | |||||||
IMCOC |
The extracted time overrun factors are illustrated as follows: Factor 1: Inaccuracy of tendering process: This factor comprises failures occurring because of client’s team deficiency in preparing an accurate tender estimation due to unskilled estimation team, not detailed project’s drawings and specifications, unavailability of historical cost data, imports, etc. Factor 2: Technical performance management: This factor includes failures happening because of contractor deficiency the management of technical performance where he is not able to provide construction fleet of equipment on time with the needed number, horsepower, and productivity. Factor 3: Government interferences: It is composed of three sequent items, which are: government changes, political interferences, and changes in the regulations and laws as a result. In other words, government changes lead to political interferences in the projects and to changes in government policies. Factor 4: Weather conditions: This factor comprises all risk consequences from severe weather conditions that occur at projects’ sites. Since, construction relies on weather conditions, planning and designing projects in Iraq are highly specified by the geography, landscape, and local weather conditions. Besides, building materials and strategies are changeable to fit a particular climate. Factor 5: Rework construction practices: It includes changes, errors, and/or omissions happening during construction stage and resulting in time overruns. The most encountered rework causes in Iraq projects are construction method changes, errors, and omissions that occurred during the construction stage. Factor 6: Material delays: This factor is composed of two items: numerous type availability of materials in markets and difficulty of getting governmental approvals. The Iraqi market comprises various types of materials from different sources, and getting an approval about usage of a specific material is very hard because of the outdated traditional governmental policies. Factor 7: Estimation challenges: It concludes the issues of risk management that could be ignored in the Iraq public project management. Risk challenges include poor processes of estimation due to unskilled estimators and incomplete drawings provided by clients. Factor 8: Exceptional challenges: Due to terrorist threats in Iraq, there are restrictions on delivering materials, equipment, and workers into some governmental sites where projects are constructed. Therefore, governmental permits are needed to deliver contractor supplies, but obtaining permits is complicated because of the impractical governmental regulations.
5 Output discussion
The top five highly ranked causes of time overruns of construction projects in Iraq are global and local economic disaster (mean = 3.7, RII = 0.739), bureaucracy and corruption (mean = 3.68, RII = 0.736), public holidays (mean = 3.57, RII = 0.715), delays in getting permits from the municipality (mean = 3.5, RII = 0.701), and issuing many change orders by clients (mean = 3.43, RII = 0.687). Global and local economic crisis is ranked as the highest impacting factor for delays in Iraq construction industry. The principal revenue of the Iraqi government is from export of oil products; therefore, the happening reduction in the world demand for oil because of ISIS and COVID-19 resulted in suspension of the construction activities in Iraq, causing delay in projects where no finance ability existed anymore. Bureaucracy and corruption are the second-ranked cause for delay of public projects. Corruption is penetrating almost all levels of the Iraqi government. In 2018, Iraq was ranked on average as 162 out of 180 by corruption perceptions index. Corruption and bureaucracy that are occurring as a result of corruption impacted directly the development of infrastructure in Iraq. Public holiday is the third delay cause of public projects. Iraq has numerous national and religious holidays; the matter that causes work suspension for many days where contractors cannot perform construction activities on holidays where the resident project representative office members are not present to supervise the contractor works at sites. Besides, contractors usually miscalculate the needed days of work to accomplish projects where they do not take into account of the number of holidays in Iraq. Delay in getting permits from municipality is the fourth-ranked cause of delay. Corruption, bureaucracy, and outdated governmental laws are the main cause of delay. Corrupt employees put a lot of obstacles in front of contractors to give such permits taking advantage of the elderly set laws where they claim that this is the best way to prevent frauds. Issuing many change orders by clients is the fifth highly causing factor for delay. Inaccuracy in tender preparation by clients, Iraqi governmental institutes, and projects awarding with incomplete drawings and specifications are the main problems, leading to work errors, work reconstruction, and project delay as a result.
6 Conclusion
A literature review, interview, and questionnaire are utilized in a consecutive research approach to build a framework for identifying and classifying delay factors of construction projects in Iraq. The study’s participants comprised 115 respondents who have sufficient experience in the construction industry. Descriptive and conclusive statistical tools were used to analyze the collected data. The Spearman rank correlation coefficient was calculated to assure that supplied rankings by all respondent categories are not provided by chance, but instead they represent the actual delay causes. This study has defined 45 delay factors of projects that were observed to be the highly crucial factors for dissecting the public projects delay in Iraq. The highest top five ranked factors by the overall respondents are: global and local economic disaster, bureaucracy and corruption, public holidays, delays in getting permits from municipality, and issuing many change orders by clients. These findings are obtained by using a five-point Likert scale to satisfy the study objective and provide stakeholders of projects with a decision-making support by distinguishing what constitutes the major delay factors. Depending on factor analysis approach, the 45 delay factors were furthermore grouped into eight groups: inaccuracy of tendering process, technical performance management, government interferences, weather conditions, rework construction practices, material delays, estimation challenges, and exceptional challenges. The conducted agreement test illustrated that the calculated coefficients are strong and positive, exhibiting a high harmonization between the rankings of all respondent categories. The highest agreement pairs are “consultant-PM,” “client-PM,” and “client-consultant.” Significance test was performed as well by utilizing the Chi-squared test to determine the disagreement or agreement context among the respondent categories rankings. The results showed that the null hypothesis is not accepted, and there is an agreement with a high degree among the five categories on the 45 delay causes. The gathered information from this study will serve in both practical and academic fields. Practically, the achieved information will help in the selection of public projects leaders and team members, in defining the possible points of delay where the standard measures will be taken in consideration, and in predicting the demands of the prophesied performance levels even before the commencement of projects. Academically, this study has provided some insights and concepts related to project management, particularly concepts of projects delay.
7 Recommendations
Based on the monitored causes of projects time overruns, future research will comprise investigating and framing the suitable plans to handle those causes. For example, wording an economic plan and program with a strategic dimension to be applied without any politic interferences, provide other funding sources for construction projects in Iraq by validating the other economic sectors, such as tourism, industry, and cultivation, eliminating the administrative and financial corruption by establishing supervisory programs, and issuing new rules and regulations to reduce the number of the public holidays.
-
Conflict of interest: Authors state no conflict of interest.
References
[1] Bramble BB, Callahan MT. Construction delay claims. USA: John Wiley and Sons, Inc.; 1987. Search in Google Scholar
[2] Aibinu AA, Jagboro GO. The effects of construction delays in Nigerian construction industry. Int J Project Manag. 2002;20(8):593–9. 10.1016/S0263-7863(02)00028-5Search in Google Scholar
[3] Assaf SA, Al-Hejji S. Causes of delay in large construction projects. Int J Project Management. 2006;24(4):349–57. 10.1016/j.ijproman.2005.11.010Search in Google Scholar
[4] Bekr GA. Causes of delay in PCPs in Iraq. Jordan J Civil Eng. 2015;9(2):149–62. Search in Google Scholar
[5] Singh R. Delays and cost overruns in infrastructure project: extent causes and remedies. Econ Political Weekly. 2010;XLV(21):43–54. Search in Google Scholar
[6] Jahanger QK. Important causes of delay in construction projects in Baghdad city. Australian J Basic Appl Sci. 2013;7(4):14–23. Search in Google Scholar
[7] CBI. Iraq economic annual report. Baghdad: Bank of Iraq; 2012. Search in Google Scholar
[8] Abdulhussein H, Shibaani A. Risk management in construction projects in Iraq: contractors’ perspective. Int J Eng Res. 2016;4(3):114–29. Search in Google Scholar
[9] Danso H, Antwi JK. Evaluation of the factors influencing time and cost overruns in telecom tower construction in Ghana. Civil Environ Res. 2012;2(6):15–24. Search in Google Scholar
[10] Doloi H, Sawhney A, Iyer K, Rentala S. Analyzing factors affecting delays in Indian construction projects. Int J Project Management. 2012;30(4):479–89. 10.1016/j.ijproman.2011.10.004Search in Google Scholar
[11] Gündüz M, Nielsen Y, Ozdemir M. Quantification of delay factors using the relative importance index method for construction projects in Turkey. J Manag Eng. 2012;29(2):133–9. 10.1061/(ASCE)ME.1943-5479.0000129Search in Google Scholar
[12] Marzouk MM, El-Rasas TI. Analyzing delay causes in Egyptian construction projects. J Adv Res. 2014;5(1):49–55. 10.1016/j.jare.2012.11.005Search in Google Scholar PubMed PubMed Central
[13] Khoshgoftar M, AbuBakar AH, Osman O. Causes of delays in Iranian construction projects. Int J Constr Manag. 2014;10(2):53–69. 10.1080/15623599.2010.10773144Search in Google Scholar
[14] Lindhard S, Wandahl S. Exploration of the reasons for delays in construction. Int J Constr Manag. 2014;14(1):36–44. 10.1080/15623599.2013.875267Search in Google Scholar
[15] Enshassi A, Kumaraswamy M, Al-Najjar J. Significant factors causing time and cost overruns in construction projects in the Gaza strip: contractors’ perspective. Int J Constr Manag. 2014;10(1):35–60. 10.1080/15623599.2010.10773137Search in Google Scholar
[16] Bajjou MS, Chafi A. Empirical study of schedule delay in Moroccan construction projects. Int J Constr Manag. 2018;20(7):783–800. 10.1080/15623599.2018.1484859Search in Google Scholar
[17] Mahdi I, Soliman E. Significant and top ranked delay factors in Arabic Gulf countries. Int J Constr Manag. 2018;21(2):167–80. 10.1080/15623599.2018.1512029Search in Google Scholar
[18] Rachid Z, Toufik B, Mohammed B. Causes of schedule delays in construction projects in Algeria. Int J Constr Manag. 2018;19(5):371–81. 10.1080/15623599.2018.1435234Search in Google Scholar
[19] Mohamad HM, Mohamad MI, Saad I, Bolong N, Mustazama J, Razali SNM. A case study of S-curve analysis: causes, effects, tracing and monitoring project extension of time. Civil Eng J. 2021;7(4):649–61. 10.28991/cej-2021-03091679Search in Google Scholar
[20] Indhu B, Yogeswari K. Structural equation modelling (SEM) approach on inappropriate construction equipment delay factors. Civil Eng J. 2021;7(7):1156–68. 10.28991/cej-2021-03091717Search in Google Scholar
[21] Silverman D. Doing qualitative research. 4th ed. London: Sage Publication; 2013. Search in Google Scholar
[22] Mir FA, Pinnington AH. Exploring the value of project management: linking project management performance and project success. Int J Project Management. 2014;32(2):202–17. 10.1016/j.ijproman.2013.05.012Search in Google Scholar
[23] Maumbe BM, Owei V, Alexander A. Questioning the pace and pathway of the government development in Africa: a case study of South Africa’s Cape Gateway project. Government Inform Quarter. 2008;25(4):757–77. 10.1016/j.giq.2007.08.007Search in Google Scholar
[24] Ahsan K, Gunawan I. Analysis of cost and schedule performance of international developmental projects. Int J Project Manag. 2010;28(1):68–78. 10.1016/j.ijproman.2009.03.005Search in Google Scholar
[25] Carvalho MM. An investigation of the role of communication in IT projects. Int J Operat Production Manag. 2014;34(1):36–64. 10.1108/IJOPM-11-2011-0439Search in Google Scholar
[26] Israel GD. Determining sample size. University of Florida Cooperative Extension Service, Institute of Food and Agriculture Sciences. Florida: EDIS; 1992. Search in Google Scholar
[27] Damoah IS, Kumi DK. Causes of government construction projects failure in an emerging economy Evidence from Ghana, Int J Managing Projects Business. 2018;11(3):558–82. 10.1108/IJMPB-04-2017-0042Search in Google Scholar
[28] Yin R. Case study research: design and methods. 4th ed. Thousand Oaks, California: Sage; 2009. Search in Google Scholar
[29] Pallant J. SPSS survival manual: a step by step guide to data analysis using SPSS. Crows Nest, NSW: Allen and Unwin; 2004. Search in Google Scholar
[30] Chan APC, Ho DCK, Tam CM. Design and build success factors: a multivariate analysis. J Constr Eng Manag. 2001;127(2):93–100. 10.1061/(ASCE)0733-9364(2001)127:2(93)Search in Google Scholar
[31] Ehshassi A, Mhamed S, Abushaban S. Factors affecting the performance of construction projects in the Gaza strip. J Civil Eng Manag. 2009;15(3):269–80. 10.3846/1392-3730.2009.15.269-280Search in Google Scholar
[32] Fagbenle OI, Adeyemi AY, Adesanya DA. The impact of non-financial incentives on bricklayers’ productivity in Nigeria. Constr Manag Econom. 2004;22(9):899–911. 10.1080/0144619042000241262Search in Google Scholar
[33] Fugar FDK, Agyakwah-Baah AB. Delays in building construction projects in Ghana. Australasian J Constr Econom Building. 2010;10(1–2):103–16. 10.5130/ajceb.v10i1/2.1592Search in Google Scholar
[34] Legendre P. Species associations: the Kendall coefficient of concordance revisited, American statistical association and the international biometric society. J Agric Biol Environ Stat. 2005;10(2):226–45. 10.1198/108571105X46642Search in Google Scholar
[35] Zar JH. Biostatistical analysis. 4th ed. Upper Saddle River, NJ: Prentice Hall; 1999. Search in Google Scholar
[36] Frimpong Y, Oluwoye J, Crawford L. Causes of delay and cost overruns in construction of groundwater projects in developing countries: Ghana as a case study. Int J Project Management. 2003;21(5):321–6. 10.1016/S0263-7863(02)00055-8Search in Google Scholar
[37] Ferguson E, Cox T. Exploratory factor analysis: A user’s guide. Int J Selection Assessment. 1993;1(2):84–94. 10.1111/j.1468-2389.1993.tb00092.xSearch in Google Scholar
[38] Ikediashi DI, Ogunlana SO, Alotaibi A. Analysis of project failure factors for infrastructure projects in Saudi Arabia: a multivariate approach. J Constr Developing Countries. 2014;19(1):35–52. Search in Google Scholar
[39] Yang J, Shen GQ, Ho M, Drew DS, Chan APC. Exploring critical success factors for stakeholder management in construction projects. J Civil Eng Manag. 2009;15(4):337–48. 10.3846/1392-3730.2009.15.337-348Search in Google Scholar
© 2022 the author(s), published by De Gruyter
This work is licensed under the Creative Commons Attribution 4.0 International License.
Articles in the same Issue
- Regular Articles
- Performance of a horizontal well in a bounded anisotropic reservoir: Part I: Mathematical analysis
- Key competences for Transport 4.0 – Educators’ and Practitioners’ opinions
- COVID-19 lockdown impact on CERN seismic station ambient noise levels
- Constraint evaluation and effects on selected fracture parameters for single-edge notched beam under four-point bending
- Minimizing form errors in additive manufacturing with part build orientation: An optimization method for continuous solution spaces
- The method of selecting adaptive devices for the needs of drivers with disabilities
- Control logic algorithm to create gaps for mixed traffic: A comprehensive evaluation
- Numerical prediction of cavitation phenomena on marine vessel: Effect of the water environment profile on the propulsion performance
- Boundary element analysis of rotating functionally graded anisotropic fiber-reinforced magneto-thermoelastic composites
- Effect of heat-treatment processes and high temperature variation of acid-chloride media on the corrosion resistance of B265 (Ti–6Al–4V) titanium alloy in acid-chloride solution
- Influence of selected physical parameters on vibroinsulation of base-exited vibratory conveyors
- System and eco-material design based on slow-release ferrate(vi) combined with ultrasound for ballast water treatment
- Experimental investigations on transmission of whole body vibration to the wheelchair user's body
- Determination of accident scenarios via freely available accident databases
- Elastic–plastic analysis of the plane strain under combined thermal and pressure loads with a new technique in the finite element method
- Design and development of the application monitoring the use of server resources for server maintenance
- The LBC-3 lightweight encryption algorithm
- Impact of the COVID-19 pandemic on road traffic accident forecasting in Poland and Slovakia
- Development and implementation of disaster recovery plan in stock exchange industry in Indonesia
- Pre-determination of prediction of yield-line pattern of slabs using Voronoi diagrams
- Urban air mobility and flying cars: Overview, examples, prospects, drawbacks, and solutions
- Stadiums based on curvilinear geometry: Approximation of the ellipsoid offset surface
- Driftwood blocking sensitivity on sluice gate flow
- Solar PV power forecasting at Yarmouk University using machine learning techniques
- 3D FE modeling of cable-stayed bridge according to ICE code
- Review Articles
- Partial discharge calibrator of a cavity inside high-voltage insulator
- Health issues using 5G frequencies from an engineering perspective: Current review
- Modern structures of military logistic bridges
- Retraction
- Retraction note: COVID-19 lockdown impact on CERN seismic station ambient noise levels
- Special Issue: Trends in Logistics and Production for the 21st Century - Part II
- Solving transportation externalities, economic approaches, and their risks
- Demand forecast for parking spaces and parking areas in Olomouc
- Rescue of persons in traffic accidents on roads
- Special Issue: ICRTEEC - 2021 - Part II
- Switching transient analysis for low voltage distribution cable
- Frequency amelioration of an interconnected microgrid system
- Wireless power transfer topology analysis for inkjet-printed coil
- Analysis and control strategy of standalone PV system with various reference frames
- Special Issue: AESMT
- Study of emitted gases from incinerator of Al-Sadr hospital in Najaf city
- Experimentally investigating comparison between the behavior of fibrous concrete slabs with steel stiffeners and reinforced concrete slabs under dynamic–static loads
- ANN-based model to predict groundwater salinity: A case study of West Najaf–Kerbala region
- Future short-term estimation of flowrate of the Euphrates river catchment located in Al-Najaf Governorate, Iraq through using weather data and statistical downscaling model
- Utilization of ANN technique to estimate the discharge coefficient for trapezoidal weir-gate
- Experimental study to enhance the productivity of single-slope single-basin solar still
- An empirical formula development to predict suspended sediment load for Khour Al-Zubair port, South of Iraq
- A model for variation with time of flexiblepavement temperature
- Analytical and numerical investigation of free vibration for stepped beam with different materials
- Identifying the reasons for the prolongation of school construction projects in Najaf
- Spatial mixture modeling for analyzing a rainfall pattern: A case study in Ireland
- Flow parameters effect on water hammer stability in hydraulic system by using state-space method
- Experimental study of the behaviour and failure modes of tapered castellated steel beams
- Water hammer phenomenon in pumping stations: A stability investigation based on root locus
- Mechanical properties and freeze-thaw resistance of lightweight aggregate concrete using artificial clay aggregate
- Compatibility between delay functions and highway capacity manual on Iraqi highways
- The effect of expanded polystyrene beads (EPS) on the physical and mechanical properties of aerated concrete
- The effect of cutoff angle on the head pressure underneath dams constructed on soils having rectangular void
- An experimental study on vibration isolation by open and in-filled trenches
- Designing a 3D virtual test platform for evaluating prosthetic knee joint performance during the walking cycle
- Special Issue: AESMT-2 - Part I
- Optimization process of resistance spot welding for high-strength low-alloy steel using Taguchi method
- Cyclic performance of moment connections with reduced beam sections using different cut-flange profiles
- Time overruns in the construction projects in Iraq: Case study on investigating and analyzing the root causes
- Contribution of lift-to-drag ratio on power coefficient of HAWT blade for different cross-sections
- Geotechnical correlations of soil properties in Hilla City – Iraq
- Improve the performance of solar thermal collectors by varying the concentration and nanoparticles diameter of silicon dioxide
- Enhancement of evaporative cooling system in a green-house by geothermal energy
- Destructive and nondestructive tests formulation for concrete containing polyolefin fibers
- Quantify distribution of topsoil erodibility factor for watersheds that feed the Al-Shewicha trough – Iraq using GIS
- Seamless geospatial data methodology for topographic map: A case study on Baghdad
- Mechanical properties investigation of composite FGM fabricated from Al/Zn
- Causes of change orders in the cycle of construction project: A case study in Al-Najaf province
- Optimum hydraulic investigation of pipe aqueduct by MATLAB software and Newton–Raphson method
- Numerical analysis of high-strength reinforcing steel with conventional strength in reinforced concrete beams under monotonic loading
- Deriving rainfall intensity–duration–frequency (IDF) curves and testing the best distribution using EasyFit software 5.5 for Kut city, Iraq
- Designing of a dual-functional XOR block in QCA technology
- Producing low-cost self-consolidation concrete using sustainable material
- Performance of the anaerobic baffled reactor for primary treatment of rural domestic wastewater in Iraq
- Enhancement isolation antenna to multi-port for wireless communication
- A comparative study of different coagulants used in treatment of turbid water
- Field tests of grouted ground anchors in the sandy soil of Najaf, Iraq
- New methodology to reduce power by using smart street lighting system
- Optimization of the synergistic effect of micro silica and fly ash on the behavior of concrete using response surface method
- Ergodic capacity of correlated multiple-input–multiple-output channel with impact of transmitter impairments
- Numerical studies of the simultaneous development of forced convective laminar flow with heat transfer inside a microtube at a uniform temperature
- Enhancement of heat transfer from solar thermal collector using nanofluid
- Improvement of permeable asphalt pavement by adding crumb rubber waste
- Study the effect of adding zirconia particles to nickel–phosphorus electroless coatings as product innovation on stainless steel substrate
- Waste aggregate concrete properties using waste tiles as coarse aggregate and modified with PC superplasticizer
- CuO–Cu/water hybrid nonofluid potentials in impingement jet
- Satellite vibration effects on communication quality of OISN system
- Special Issue: Annual Engineering and Vocational Education Conference - Part III
- Mechanical and thermal properties of recycled high-density polyethylene/bamboo with different fiber loadings
- Special Issue: Advanced Energy Storage
- Cu-foil modification for anode-free lithium-ion battery from electronic cable waste
- Review of various sulfide electrolyte types for solid-state lithium-ion batteries
- Optimization type of filler on electrochemical and thermal properties of gel polymer electrolytes membranes for safety lithium-ion batteries
- Pr-doped BiFeO3 thin films growth on quartz using chemical solution deposition
- An environmentally friendly hydrometallurgy process for the recovery and reuse of metals from spent lithium-ion batteries, using organic acid
- Production of nickel-rich LiNi0.89Co0.08Al0.03O2 cathode material for high capacity NCA/graphite secondary battery fabrication
- Special Issue: Sustainable Materials Production and Processes
- Corrosion polarization and passivation behavior of selected stainless steel alloys and Ti6Al4V titanium in elevated temperature acid-chloride electrolytes
- Special Issue: Modern Scientific Problems in Civil Engineering - Part II
- The modelling of railway subgrade strengthening foundation on weak soils
- Special Issue: Automation in Finland 2021 - Part II
- Manufacturing operations as services by robots with skills
- Foundations and case studies on the scalable intelligence in AIoT domains
- Safety risk sources of autonomous mobile machines
- Special Issue: 49th KKBN - Part I
- Residual magnetic field as a source of information about steel wire rope technical condition
- Monitoring the boundary of an adhesive coating to a steel substrate with an ultrasonic Rayleigh wave
- Detection of early stage of ductile and fatigue damage presented in Inconel 718 alloy using instrumented indentation technique
- Identification and characterization of the grinding burns by eddy current method
- Special Issue: ICIMECE 2020 - Part II
- Selection of MR damper model suitable for SMC applied to semi-active suspension system by using similarity measures
Articles in the same Issue
- Regular Articles
- Performance of a horizontal well in a bounded anisotropic reservoir: Part I: Mathematical analysis
- Key competences for Transport 4.0 – Educators’ and Practitioners’ opinions
- COVID-19 lockdown impact on CERN seismic station ambient noise levels
- Constraint evaluation and effects on selected fracture parameters for single-edge notched beam under four-point bending
- Minimizing form errors in additive manufacturing with part build orientation: An optimization method for continuous solution spaces
- The method of selecting adaptive devices for the needs of drivers with disabilities
- Control logic algorithm to create gaps for mixed traffic: A comprehensive evaluation
- Numerical prediction of cavitation phenomena on marine vessel: Effect of the water environment profile on the propulsion performance
- Boundary element analysis of rotating functionally graded anisotropic fiber-reinforced magneto-thermoelastic composites
- Effect of heat-treatment processes and high temperature variation of acid-chloride media on the corrosion resistance of B265 (Ti–6Al–4V) titanium alloy in acid-chloride solution
- Influence of selected physical parameters on vibroinsulation of base-exited vibratory conveyors
- System and eco-material design based on slow-release ferrate(vi) combined with ultrasound for ballast water treatment
- Experimental investigations on transmission of whole body vibration to the wheelchair user's body
- Determination of accident scenarios via freely available accident databases
- Elastic–plastic analysis of the plane strain under combined thermal and pressure loads with a new technique in the finite element method
- Design and development of the application monitoring the use of server resources for server maintenance
- The LBC-3 lightweight encryption algorithm
- Impact of the COVID-19 pandemic on road traffic accident forecasting in Poland and Slovakia
- Development and implementation of disaster recovery plan in stock exchange industry in Indonesia
- Pre-determination of prediction of yield-line pattern of slabs using Voronoi diagrams
- Urban air mobility and flying cars: Overview, examples, prospects, drawbacks, and solutions
- Stadiums based on curvilinear geometry: Approximation of the ellipsoid offset surface
- Driftwood blocking sensitivity on sluice gate flow
- Solar PV power forecasting at Yarmouk University using machine learning techniques
- 3D FE modeling of cable-stayed bridge according to ICE code
- Review Articles
- Partial discharge calibrator of a cavity inside high-voltage insulator
- Health issues using 5G frequencies from an engineering perspective: Current review
- Modern structures of military logistic bridges
- Retraction
- Retraction note: COVID-19 lockdown impact on CERN seismic station ambient noise levels
- Special Issue: Trends in Logistics and Production for the 21st Century - Part II
- Solving transportation externalities, economic approaches, and their risks
- Demand forecast for parking spaces and parking areas in Olomouc
- Rescue of persons in traffic accidents on roads
- Special Issue: ICRTEEC - 2021 - Part II
- Switching transient analysis for low voltage distribution cable
- Frequency amelioration of an interconnected microgrid system
- Wireless power transfer topology analysis for inkjet-printed coil
- Analysis and control strategy of standalone PV system with various reference frames
- Special Issue: AESMT
- Study of emitted gases from incinerator of Al-Sadr hospital in Najaf city
- Experimentally investigating comparison between the behavior of fibrous concrete slabs with steel stiffeners and reinforced concrete slabs under dynamic–static loads
- ANN-based model to predict groundwater salinity: A case study of West Najaf–Kerbala region
- Future short-term estimation of flowrate of the Euphrates river catchment located in Al-Najaf Governorate, Iraq through using weather data and statistical downscaling model
- Utilization of ANN technique to estimate the discharge coefficient for trapezoidal weir-gate
- Experimental study to enhance the productivity of single-slope single-basin solar still
- An empirical formula development to predict suspended sediment load for Khour Al-Zubair port, South of Iraq
- A model for variation with time of flexiblepavement temperature
- Analytical and numerical investigation of free vibration for stepped beam with different materials
- Identifying the reasons for the prolongation of school construction projects in Najaf
- Spatial mixture modeling for analyzing a rainfall pattern: A case study in Ireland
- Flow parameters effect on water hammer stability in hydraulic system by using state-space method
- Experimental study of the behaviour and failure modes of tapered castellated steel beams
- Water hammer phenomenon in pumping stations: A stability investigation based on root locus
- Mechanical properties and freeze-thaw resistance of lightweight aggregate concrete using artificial clay aggregate
- Compatibility between delay functions and highway capacity manual on Iraqi highways
- The effect of expanded polystyrene beads (EPS) on the physical and mechanical properties of aerated concrete
- The effect of cutoff angle on the head pressure underneath dams constructed on soils having rectangular void
- An experimental study on vibration isolation by open and in-filled trenches
- Designing a 3D virtual test platform for evaluating prosthetic knee joint performance during the walking cycle
- Special Issue: AESMT-2 - Part I
- Optimization process of resistance spot welding for high-strength low-alloy steel using Taguchi method
- Cyclic performance of moment connections with reduced beam sections using different cut-flange profiles
- Time overruns in the construction projects in Iraq: Case study on investigating and analyzing the root causes
- Contribution of lift-to-drag ratio on power coefficient of HAWT blade for different cross-sections
- Geotechnical correlations of soil properties in Hilla City – Iraq
- Improve the performance of solar thermal collectors by varying the concentration and nanoparticles diameter of silicon dioxide
- Enhancement of evaporative cooling system in a green-house by geothermal energy
- Destructive and nondestructive tests formulation for concrete containing polyolefin fibers
- Quantify distribution of topsoil erodibility factor for watersheds that feed the Al-Shewicha trough – Iraq using GIS
- Seamless geospatial data methodology for topographic map: A case study on Baghdad
- Mechanical properties investigation of composite FGM fabricated from Al/Zn
- Causes of change orders in the cycle of construction project: A case study in Al-Najaf province
- Optimum hydraulic investigation of pipe aqueduct by MATLAB software and Newton–Raphson method
- Numerical analysis of high-strength reinforcing steel with conventional strength in reinforced concrete beams under monotonic loading
- Deriving rainfall intensity–duration–frequency (IDF) curves and testing the best distribution using EasyFit software 5.5 for Kut city, Iraq
- Designing of a dual-functional XOR block in QCA technology
- Producing low-cost self-consolidation concrete using sustainable material
- Performance of the anaerobic baffled reactor for primary treatment of rural domestic wastewater in Iraq
- Enhancement isolation antenna to multi-port for wireless communication
- A comparative study of different coagulants used in treatment of turbid water
- Field tests of grouted ground anchors in the sandy soil of Najaf, Iraq
- New methodology to reduce power by using smart street lighting system
- Optimization of the synergistic effect of micro silica and fly ash on the behavior of concrete using response surface method
- Ergodic capacity of correlated multiple-input–multiple-output channel with impact of transmitter impairments
- Numerical studies of the simultaneous development of forced convective laminar flow with heat transfer inside a microtube at a uniform temperature
- Enhancement of heat transfer from solar thermal collector using nanofluid
- Improvement of permeable asphalt pavement by adding crumb rubber waste
- Study the effect of adding zirconia particles to nickel–phosphorus electroless coatings as product innovation on stainless steel substrate
- Waste aggregate concrete properties using waste tiles as coarse aggregate and modified with PC superplasticizer
- CuO–Cu/water hybrid nonofluid potentials in impingement jet
- Satellite vibration effects on communication quality of OISN system
- Special Issue: Annual Engineering and Vocational Education Conference - Part III
- Mechanical and thermal properties of recycled high-density polyethylene/bamboo with different fiber loadings
- Special Issue: Advanced Energy Storage
- Cu-foil modification for anode-free lithium-ion battery from electronic cable waste
- Review of various sulfide electrolyte types for solid-state lithium-ion batteries
- Optimization type of filler on electrochemical and thermal properties of gel polymer electrolytes membranes for safety lithium-ion batteries
- Pr-doped BiFeO3 thin films growth on quartz using chemical solution deposition
- An environmentally friendly hydrometallurgy process for the recovery and reuse of metals from spent lithium-ion batteries, using organic acid
- Production of nickel-rich LiNi0.89Co0.08Al0.03O2 cathode material for high capacity NCA/graphite secondary battery fabrication
- Special Issue: Sustainable Materials Production and Processes
- Corrosion polarization and passivation behavior of selected stainless steel alloys and Ti6Al4V titanium in elevated temperature acid-chloride electrolytes
- Special Issue: Modern Scientific Problems in Civil Engineering - Part II
- The modelling of railway subgrade strengthening foundation on weak soils
- Special Issue: Automation in Finland 2021 - Part II
- Manufacturing operations as services by robots with skills
- Foundations and case studies on the scalable intelligence in AIoT domains
- Safety risk sources of autonomous mobile machines
- Special Issue: 49th KKBN - Part I
- Residual magnetic field as a source of information about steel wire rope technical condition
- Monitoring the boundary of an adhesive coating to a steel substrate with an ultrasonic Rayleigh wave
- Detection of early stage of ductile and fatigue damage presented in Inconel 718 alloy using instrumented indentation technique
- Identification and characterization of the grinding burns by eddy current method
- Special Issue: ICIMECE 2020 - Part II
- Selection of MR damper model suitable for SMC applied to semi-active suspension system by using similarity measures