Abstract
Much research in the construction industry is based on the concept of a unique project; hence, such concepts (or philosophy) present the construction project as a unit of analysis for the entire completion process that is usually delivered independently. Most decision support tools in construction have been designed at the project level rather than for construction institutions that often implement many projects simultaneously. Typically, these projects have common objectives that create dependencies among them. Then, the success of one project depends on other projects and the existing interrelationships among them. Thus, construction institutions still need to deal with their projects from a portfolio perspective,which requires strategic management at a portfolio level. This paper employs resource management techniques to allocate resources to manage construction portfolios. A case study targeted strategic decision making about financing projects that have stalled. The final recommendation of this paper is to use development and planning software to serve and support strategic decisions in institutions with concurrent stalled projects.
1 Introduction
Investment professionals have become specialised, and financial concepts have become more sophisticated, over the past 25 years, allowing higher quality client service and better investment performance.
When construction organisations invest in a variety of projects, these combinations of construction projects can be considered portfolios of construction projects. Concepts of intelligent portfolio management (IPM) can be applied to a portfolio of construction projects. A portfolio of diversified projects usually has less risk than individual projects. However, investment in construction projects differs from that in other sectors. These differences arise from the difficulty of applying the portfolio theory in the construction industry [1].
Although academic consideration of the construction industry has been based on the delivery of one project, management focus has recently shifted from a single project to managing a portfolio of projects to achieve strategic objectives.Aportfolio approach requires a holistic analysis of the projects undertaken simultaneously. The concept of portfolio management (PM) is based on the fact that a duration estimate and a financial budget are needed for every project in the construction industry, whether it is a new development or maintenance work for an existing facility [2].
A previous studies were used to develop mathematical models that will be applied to the construction projects. The outcomes display that the PSO technique is proper for evaluating project management problems and can be utilized as a useful tool to search the optimal solutions with differs parameters [3].
Currently, in all Iraqi buildings, it was adopting a corrective maintenance approach in maintaining building rather than proper maintenance management approaches (preventive, predictive), this affects negatively on the quality and cost of building maintenance. In addition, lack of proper and specific maintenance–related documentation methods. The study proposed approach to develop the building maintenance management by using deterioration models which consist of different routes [4].
Researchers develop a clear concept about the BIM adoption in Iraq through investigating potential benefits that can be obtained through its application in construction projects also build a measurement model for these benefits [5, 6].
Management of a project plays a critical role for investment professionals and investors and in success in the construction industry. As one of the most important methods of management, the principles of PM have been around for about 20 years [7]. Therefore, choosing a successful management technique plays a key role in completing projects [8]. The vital role of PM is to optimise resource allocation of projects within the portfolio to achieve the technology and financial objectives of the institution. The theory of PM is a normative theory that describes the standard or norm of behaviour that investors should pursue when developing a construction portfolio.
Though widely applicable, modern portfolio theory (MPT) has a stronger influence when practised in PM. In its simplest form,MPT provides a framework to predict the performance of select projects within portfolios and to determine the probability of investment risk. In the investment management field, MPT introduces new terminology. Portfolio management theory (PMT) provides a framework to specify and measure the investment risk of projects within a portfolio. In addition, PM develops relationships among expected asset returns and investment risks [9].
IPM aims to optimise the selection of investment projects by defining the strategic objectives of an institution. This selection achieves an ideal balance among projects. The dependencies in construction portfolio projects within an institution must be considered because they have a significant effect on portfolio success. Few studies in construction PM investigate how the dependencies between projects can be handled [10].
The researcher studied the stalled projects to assess poject’s completion acceleration before and after the crisis (scarcity of financial resources). Situations of governmental investment plan projects also was studied from 2015 to 2018. Then the researcher summarized the financial statements for a group of suspended projects, each according to its sector (which will represent the financial portfolios later) over four years.
After filed data was collected, analysis was done. Finally, results were discussed in light of Iraqi construction industry. as given the flow chart below. Figure 1 summarizes the steps followed in this research.

Flowchart of the research methodology.
2 Portfolio Management Definition
Portfolio management is a decision process to prepare lists of investment projects that need to be constantly revised, updated, evaluated, and prioritised. Generally, PM is an uncertain process with continuous changes in information. It is characterised by strategic considerations through multiple objectives and interdependencies among portfolio projects [11].
PM is a decision process comprising several decision-making processes within institutions through periodic reviews of all portfolio projects. Which projects require new institutional selection strategies and new resourceallocation decisions can be determined through the analysis of the set of projects compared against each other [11]. Moreover,PMis vital for successful project innovation. The PM process ranges from strategic choices for resources and technologies needed to execute construction portfolios to how institutions spend scarce engineering, financial and marketing resources to deliver results. PM deals with the balance between the adequate number of projects that should be done and the available resources or capabilities of institutions [12]. Thus, PM considers the manifestation of the institutional strategy to explain or dictate where and how institutions invest in the future. Construction PM treats investment projects as financial investments like a fund manager treats stocks [12].
In addition, PM deals with achieving the strategic investment of a portfolio aligned with the overall institutional strategy. This alignment can be accomplished by maximising the portfolio value and investment return and balancing priorities in the portfolios. The successful performance of institutions requires managing the execution priority of projects within the portfolio. This step is vital for the following reasons [13]:
Senior management can achieve strategic institutional objectives for various types of implemented projects using the PM methodology.
The type of construction projects selected and the execution technology determine the institution’s allocations for the next five years.
Construction PM is about the allocation of scarce engineering, financial, and operational resources.
PM addresses the critical issue of balancing the available or scarce resources.
For the construction industry in Iraq, doing many projects with limited available resources results in a longer execution cycle and poor quality or under-performing projects.
Construction institutions increasingly take on projects to achieve firm objectives more efficiently and to augment their number of projects. These additional projects create the need for the intelligent management of construction portfolios to plan for a multitude of synchronous projects in an institution. Therefore, PM is not uniform and must be adapted to the institutional situation and the responsibilities and roles of institutional managers [14].
Studies conducted by the Project Management Institute (PMI) have reviewed the practices for PM and investigated the results of multiple methods. The findings demonstrate that high-performance institutions usually apply PM methodologies. These PM methodologies may be applied to processes, tools, or manager responsibilities that arose to address the complex requirements of the construction environments. This situation is very different at low-performing institutions [15].
Project management should be a part of PM, especially when related to corporate governance. Therefore, PM should have approaches to settle contract requirements. According to the Project Management Association, PM is a framework or structure that should comprise the following [15]:
portfolio direction effectiveness,
project sponsorship efficiency,
project management performance, and
disclosure and reporting.
In addition, PM can be divided into two parallel perspectives. The first perspective concerns interrelationships among various similar projects. The requirements for project management require investigation to acquire the overall objectives of the institution. The second perspective is adopting the correlation of various project objectives to maximise the outcomes of combination projects, which led to developing the concept of the portfolio. The PMI defines ‘portfolio’ as a group of related programmes, processed in close coordination to achieve high control and more efficient performance, which may not occur when processing them individually [16]. The development of PM techniques defines the centralised management of one or more portfolios by identifying, prioritising, managing, and controlling the projects to achieve specific strategic institutional objectives. Indeed, the portfolio theory can be comprehended as the integration of similar projects grouped to facilitate effectively reaching the strategic objectives of an institution. Portfolio theory is not necessarily interdependent or directly related to the projects of a construction portfolio [16].
3 Necessity of New Philosophy for Management
Strategic management is considered a monopoly of top management, whereas the management of a project issue is the responsibility of project management. This perspective fails to perfect the interactive relationships between both fields, especially in project-based industries. Initially, functioning strategic management is considered a precondition for aligning the evaluated project with the portfolio. Thus, the PM process may be essential for executing the institution’s formulated objectives [17]. Some characteristics of the construction industry must be considered when using strategic management. More than other sectors, the construction industry has been slow to adopt new strategic management methods, and these adoptions require many considerations [18].
First, the base institutional model for construction portfolio projects is an obstacle when a temporary institution (individual projects) does not allow the implementation of complex strategies. Some studies have found that medium-sized construction institutions are less likely to implement strategic management practices. Such institutions are less concerned about strategic management and are more proactive towards one-unit production [19]. The educational backgrounds of managers of construction institutions have led them to be less aware of the role of strategic management because most construction enterprises require an engineering background. Many of these managers lack formal training about formulating and implementing strategic management methods [20].
Research into strategic management methods for construction continues, despite the delayed acceptance of the portfolio theory in construction management. While the changing strategy formulation has received more attention, the mechanism for implementing the developed strategies in the construction industry is still poorly researched.
The rapid acceleration of urbanisation requires the construction industry to adopt a new management method. Traditional project management cannot handle the complexity of some construction projects. Thus, new management methods are needed to achieve several objectives [21]:
to integrate the activities of construction organisations during project realisation,
to achieve more added value in service markets in the construction industry,
to diversify financing sources in construction projects,
to achieve high-performance standards for under-performing projects,
to find raw materials and modern technologies in the construction industry,
to interact with authorities and suppliers throughout all construction phases of a project.
The reasons above are the result of the complexity of the organisational structure in the construction production process and its development as an independent economic entity. Modern computing techniques monitor construction activities to promote efficiency, and institutional departments coordinate employees and activities with other institutions. However, opportunities and the capacities of the construction industry are restrained because institutional construction managers lack construction PM skills owing to the following [22]:
Construction managers prefer to work in the traditional planning economy.
Construction institution owners must employ a construction project management specialist with a civil engineering degree.
The educational system must focus on preparing highly skilled narrow-specialisation engineers.
PMT addresses more extensive tasks, including integrating interactions between design teams and subcontractors involved in the same project and organising building operations owned by several stockholders. Figure 2 summarises the differences between the two strategic management methodologies.
![Figure 2 Differences between productive management methods in the construction industry [23] PPM: Project portfolio management; PM: project management](/document/doi/10.1515/eng-2020-0064/asset/graphic/j_eng-2020-0064_fig_002.jpg)
Differences between productive management methods in the construction industry [23] PPM: Project portfolio management; PM: project management
4 Portfolio Management Domain
The essential purposes of PMT are to achieve a relatively lofty investment return rate (R%) for the level of specified tasks or the lowest possible risk for a specified investment return rate. Risks may include the probability that the actual return (r%) is less than the expected return (R%), where the risk and return usually have a logical correlation (i.e. increasing investment returns result in greater risks [14]). The environment of PM must be combined with computer technology that makes financial information sources accessible throughout the institution. In addition, PM enables senior institutional managers to make more efficient decisions.
Construction PM is linked to the implementation of strategy in two ways. First, management strategies for implementing projects have been studied extensively. Second, PM practices are developed by modifying top management strategies. This concept can be applied for single and multiple management projects, specifically in project-based industries, such as the construction industry, where projects have paramount strategic relevance [22]. Intelligent construction PM (ICPM) is a method of selecting and managing institutional projects using risk factors and the return rate. While the techniques originated in the financial industry, they can be applied to the evaluation of a construction project portfolio. The MPT targets a broader set of activities (e.g. the selection of projects, controlling resources, continuous risk management, and reporting a wider range of factors). Construction portfolios are different from others in terms of the subprojects that have shared objectives but compete for allocated resources and strategic assets [24].
The essential tasks of PM include investigating the suitable available projects, selecting and prioritising projects based on the resources, and evaluating the running process concerning meeting portfolio requirements. Such activities typically involve an optimisation technique and algorithm management for specific project selection criteria.However, project selection criteria are the most important means of aligning PM strategies; thus, criteria deserve the attention of practitioners, researchers and scholars [25]. The prediction of progress for individual construction projects is a complex process because of the uncertain and unique nature of the construction industry. The selection of project packages in a portfolio must be rearranged when the risk profile of a project changes after its initiation. The initial risk evaluation and continued information updates in a portfolio lead to high-performance project progress. This improved outcome may be the main motivation for the development of strategic management, such as PM, in institutions [26].
5 Diversification in Project Funds
An intuitive premise in the construction industry is providing sufficient reasonable information from the viewpoint of the contractor before negotiating the decision about the execution of a project [10]. Given the difficulties of acquiring and evaluating information for similar projects in the construction and industrial world, investment institutions have adopted PM. Institutions use PM to monitor the portfolios under construction, instead of simply selecting projects for the portfolios [18].
Debt and equity are the two primary capital sources for funding a new product or project. Debt capital represents borrowing assets from outside the institution. Capital should be repaid at a pre-agreed interest rate on an agreed schedule. Debt funding may represent capital borrowed via mortgages, loans, or bonds, with a risk that the borrower cannot repay the borrowed funds. In such a case, the lender’s profits are shared using revenues. Outstanding debt is usually listed in the liabilities section on the balance sheet [26]. Equity capital is ‘corporate money comprised of funds of owners and retained earnings. Owners’ funds are further classified as common and preferred stock proceeds or owners’ capital for a private (non-stock-issuing) company. Retained earnings are funds previously retained in the corporation for capital investment’. Equity is usually listed in the section on the net worth on the balance sheet [26].
In IPM, construction institutions must control the product pack (projects) in a portfolio regularly in addition to allocating assets and resources. Allocation of resources can be determined using a priority system for implementing the projects within the portfolio to meet the expectations of the strategic asset allocation or the available resources. Controlling a product pack also requires a comprehensive monitoring process to provide detailed information for the financial situation of the organisation. Rearranging the asset allocation strategy is a consequence of monitoring and controlling processes, which might cause several changes at the resource-allocation level of the projects. Management of a portfolio is a comprehensive asset management process characterised by changes. Institutions regularly update their decisions as a response to the circumstances [6]. The application of PM in the construction industry requires a huge amount of information regarding the financial performance of institutions that top management must effectively understand to make wise decisions.
‘Do not put all of your eggs in one basket’ is conventional wisdom in the investment world. In technical terms, this aphorism addresses diversification benefits. Moreover, MPT quantifies the concept of diversification by introducing a statistical association for the covariance or dependence between combined units. It is important to prioritise the execution of projects in a construction institution that may become bankrupt, especially when organisational resources are limited [27]. The concept of diversification is intuitive and applies to many different fields within finance. Applying the concept of diversification and introducing a new method of obtaining improved estimates of variances and covariances allows for a more precise measure of diversification and a more careful measure of risk [27].
6 Field Analysis and Study
The construction industry in Iraq has undergone many changes, emergencies, and modifications over the past decade, and building remains remain largely dependent on state treasury funding. A high proportion of the Iraqi budget and gross domestic product (GDP) consists of oil revenue. The Global Financial Crisis affected many countries, especially oil-producing countries and their military circumstances. These factors led to the end of Iraqi infrastructure projects that provided necessities for society’s demands, needs, and advancement. The financial crisis prompted the investigation and employment of modern techniques to manage the financing of construction projects that stalled five years ago. First, the researcher studied the stalled projects to assess project completion acceleration before and after the crisis (scarcity of financial resources). Governmental investment plan projects were also studied from 2015 to 2018. Then the researcher summarized the financial statements for a group of suspended projects, each according to its sector (which will represent the financial portfolios later) over four years. Investment budget projects and their costs, adjusted allocations, and cumulative expenditure in the government sector from 2015 to 2018 are shown in the following tables. The data were extracted from unified annual reports on the follow-up of investment budget projects. According to the implementing agencies, ‘Amounts [are] in millions of dinars (M.ID), and [the] information represents [the] last update on (15/Mar./2020) [15 March 2020]. [The] Iraqi Ministry of Planning (MOP) [has] also launched a National Development Plan (NDP) for the next five years (2018-2022)’. Table 1A&1B summarises some financial data for the stalled projects.
Situations of Investment Plan Projects for 2015 to 2018*
| Sector Name | 2015 | 2016 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| No. of projects | Total project cost (M.ID) | Annual allocation fund (M.ID) | Cumulative payments (M.ID) | Develop. gap (M.ID) | No. of projects | Total cost of projects (M.ID) | Annual allocation fund (M.ID) | Cumulative payments (M.ID) | Develop. gap (M.ID) | |
| Industry Sector | 395 | 112,138,047.7 | 17,270,175.7 | 41,865,925.8 | 70,272,121.9 | 247 | 109,613,353.6 | 15,955,998.9 | 51,147,791.8 | 58,465,561.7 |
| Agriculture Sector | 195 | 23,921,995.8 | 477,181.0 | 6,488,768.60 | 17,433,227.2 | 129 | 22,680,212.9 | 174,832.24 | 4,757,680.4 | 17,922,532.5 |
| Buildings & Services | 1,744 | 86,028,583.6 | 11,686,909.6 | 23,888,791.0 | 62,139,792.6 | 1,225 | 59,040,816.1 | 3,421,176.7 | 21,632,512.4 | 37,408,303.8 |
| Transportation Communication | 371 | 27,579,131.9 | 1,447,967.9 | 5,525,323.3 | 22,053,808.6 | 241 | 21,799,679.2 | 370,479.8 | 4,931,919.4 | 16,867,759.7 |
| Programme Province Investment | 3,830 | 37,652,679.8 | 4,338,654.8 | - | - | 3,170 | 33,479,428 | 1,818,274 | - | - |
| Total | 6,535 | 287,320,439.0 | 30,220,889.0 | 77,768,808.7 | 171,898,951 | 1,842 | 213,134,062 | 19,922,487 | 82,469,904 | 130,664,158 |
Situations of Investment Plan Projects for (2015–2018)*
| Sector Name | 2015 | 2016 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| No. of projects | Total project cost (M.ID) | Annual allocation fund (M.ID) | Cumulative payments (M.ID) | Develop. gap (M.ID) | No. of projects | Total cost of projects (M.ID) | Annual allocation fund (M.ID) | Cumulative payments (M.ID) | Develop. gap (M.ID) | |
| Industry Sector | 256 | 114,774,070.4 | 17,997,140.6 | 42,010,073.3 | 72,763,997.2 | 232 | 112,047,708.7 | 17,318,102.4 | - | - |
| Agriculture Sector | 105 | 12,635,586.92 | 520,835.92 | 4,930,214.13 | 7,705,372.79 | 108 | 12,724,845.95 | 4,460,371.2 | - | - |
| Buildings & Services | 1,086 | 60,548,886.80 | 4,791,785.09 | 23,363,911.5 | 37,184,975.3 | 1,009 | 52,001,945.81 | - | - | - |
| Transportation Communication | 237 | 16,488,318.16 | 488,069.00 | 4,709,600.56 | 11,778,717.2 | 231 | 16,384,551.76 | - | - | - |
| Programme Province Investment | 3,039 | 27,868,265.1 | - | - | - | 2,743 | 25,711,664.3 | - | - | - |
| Total | 4,723 | 232,315,127.0 | 23,797,830.6 | 75,013,799.5 | 129,433,063 | 4,323 | 218,870,716.5 | 21,778,473.6 | - | - |
*Source: Ministry of Planning, Department of Sector Planning, General Director Office
In another endeavour, the researcher investigated the financial inputs’ expectations of the federal budget, based on estimates of some federal financial authorities, such as the IMF, the Ministry of Oil and the Budget Strategy Committee. Tables 2 to 4 illustrate expectations of financial inputs from oil production, oil export, and non-oil proceeds for the next five years.
Expected Iraqi Oil Production and Revenues
| Year | Oil production million (bbl./d) | Oil export million (bbl./d) | Expected oil revenues per IMF (B.ID) | Expected oil revenues per Ministry of Oil (B.ID) | Expected oil revenues per Budget Strategy Committee (B.ID) |
|---|---|---|---|---|---|
| 2018 | 4.7 | 3.9 | 75045 | 75715.9 | 74033.4 |
| 2019 | 4.7 | 3.9 | 74537 | 75715.9 | 74033.4 |
| 2020 | 4.7 | 3.9 | 76055 | 75715.9 | 74033.4 |
| 2021 | 4.9 | 4.0 | 77232 | 94914.9 | 74033.4 |
| 2022 | 4.9 | 4.0 | 79076 | 103543.2 | 74033.4 |
| Total | 23.9 | 19.7 | 381940 | 425605.5 | 370167 |
*Source: Ministry of Planning – National Development Plan (2018-2022) IMF: International Monetary Fund
Expected Miscellaneous Income*
| Year | Direct taxes | Indirect taxes | Other | Total |
|---|---|---|---|---|
| 2018 | 4996.6 | 2213.7 | 5799.8 | 14923.9 |
| 2019 | 5146.1 | 2313.1 | 6038.4 | 14430.4 |
| 2020 | 5303.4 | 2390.7 | 6262.4 | 13956.5 |
| 2021 | 5466.5 | 2471.6 | 6492.3 | 13497.6 |
| 2022 | 5639.8 | 2555.8 | 6728.3 | 13009.7 |
*Source: Ministry of Planning – National Development Plan (2018-2022)
Overall Expected Income
| Year | Expecte oil revenues (BID) | Miscellaneous income (BID) | ||||
|---|---|---|---|---|---|---|
| International Monetary Fund | Ministry of Oil | Strategic Budget Committee | Direct taxes | Indirect taxes | Other | |
| 2018 | 75045 | 75715.9 | 74033.4 | 4996.6 | 2213.7 | 5799.8 |
| 2019 | 74537 | 75715.9 | 74033.4 | 5146.1 | 2313.1 | 6038.4 |
| 2020 | 76050 | 75715.9 | 74033.4 | 5303.4 | 2390.7 | 6262.4 |
| 2021 | 77232 | 94914.6 | 74033.4 | 5466.5 | 2471.6 | 6492.3 |
| 2022 | 79076 | 103543.2 | 74033.4 | 5639.8 | 2555.8 | 6728.3 |
| Summary | 370.2 (B.ID) 84.1% | 69.8 (B.ID) 15.9% | ||||
| Total | 440,000 (B.ID) 100% | |||||
Source: Ministry of Planning – National Development Plan (2018-2022)
Target growth rates of investments in the national economy for each sector as envisaged by successive governments are shown in Tables 5 to 7. National development plans established the targeted growth rates for each sector in line with the expectation of financial inputs over the next five years. Based on the above, the total amounts that can be spent on each sector are shown below. The researcher summarized the targeted growth rates for each sector in Tables 5 to 7.
Target Growth Rates of Investments in National Economic Sectors from 2018 to 2022*
| Sector | 2015 base | Target | Planned | of | Distribution of planned investments over five years (B.ID) | ||||
|---|---|---|---|---|---|---|---|---|---|
| year (B.ID) | growth next five years | investment amount (B.ID) | investment | 2018 | 2019 | 2020 | 2021 | 2022 | |
| Agricultural | 3707.5 | 8.4% | 7574.2 | 3.4% | 1280.2 | 1388.4 | 1505.0 | 1631.5 | 1768.5 |
| Oil | 100929.2 | 7.5% | 84683.7 | 38.4% | 14579.5 | 15673 | 16848 | 18112 | 19470.5 |
| Mining | 330.0 | 1.0% | 5677.2 | 1.0% | 1077.9 | 1105.9 | 1134.7 | 1164.2 | 1194.5 |
| Transformative | 1535.1 | 10.5% | 4854.3 | 2.2% | 787.2 | 689.9 | 961.2 | 1062.2 | 1173.7 |
| industries | |||||||||
| Energy | 2130.7 | 6.0% | 20243.3 | 9.2% | 3591.1 | 3806.5 | 4034.9 | 4277.0 | 4533.7 |
| Infrastructure | 13768.4 | 6.8% | 12233.6 | 5.5% | 2135.8 | 2281.1 | 2436.2 | 2601.8 | 2778.8 |
| Transport and communications | 14313.9 | 7.0% | 39582.1 | 17.9% | 6883.0 | 7362.8 | 7880.3 | 8431.9 | 9022.1 |
| Trade | 14872.9 | 8.3% | 8545.1 | 3.9% | 14479.9 | 1568.0 | 1698.2 | 1839.1 | 1991.8 |
| Insurance | 11815.1 | 2.6% | 1077.9 | 2.6% | 1077.9 | 1105.9 | 1134.7 | 1164.2 | 1194.5 |
| Services sector | 19777.8 | 4.5% | 37219 | 16.9% | 6803.3 | 7109.5 | 7429.4 | 7763.7 | 8113.1 |
| Non-oilactivities | 81402.0 | 6.1% | NA | NA | 98201.8 | 104255.3 | 110721.6 | 117631.5 | 125017.3 |
| Total (B.ID) | 182331200 | 7.0% | 220640.0 | 100% | 38592.2 | 41172.8 | 43934.2 | 46889.4 | 50052.5 |
| Total (B.$) | 154090400 | 7.0% | 186465 | 100% | 32600 | 34800 | 37200 | 39700 | 42300 |
*Data from Ministry of Planning – National Development Plan (2018-2022) NA: not available
Target Growth Rates of the Gross Domestic Product (GDP) for (2018-2022)*
| Sector | 2015 base year | Target growth next | Distribution of planned development – gross domestic product(B.ID) | ||||
|---|---|---|---|---|---|---|---|
| (B.ID) | five years | 2018 | 2019 | 2020 | 2021 | 2022 | |
| Agricultural | 3707.5 | 8.4% | 4722.5 | 5119.2 | 5549.2 | 6015.3 | 6520.6 |
| Oil | 100929.2 | 7.5% | 125384.0 | 134787.5 | 144896.9 | 155764.2 | 167446.5 |
| Mining | 330.0 | 1.0% | 340.0 | 343.4 | 346.8 | 350.3 | 353.8 |
| Transformative industries | 1535.1 | 10.5% | 2071.2 | 2288.7 | 2529.0 | 2794.5 | 3088.0 |
| Energy | 2130.7 | 6.0% | 2537.7 | 2690.0 | 2851.4 | 3022.4 | 3203.8 |
| Infrastructure | 13768.4 | 6.8% | 16772.5 | 17913.0 | 19131.1 | 20432.0 | 21821.4 |
| Transport and communication | 14313.9 | 7.0% | 17535.1 | 18762.6 | 20076.0 | 21481.3 | 22985.0 |
| Trade | 14872.9 | 8.3% | 18892.1 | 20460.2 | 22158.4 | 23997.5 | 25989.3 |
| Insurance | 11815.1 | 2.6% | 12760.8 | 13092.6 | 13433.0 | 13782.3 | 14140.6 |
| Services sector | 19777.8 | 4.5% | 22569.8 | 23585.4 | 24646.7 | 25755.8 | 26914.9 |
| Non-oil activities | 81402.0 | 6.1% | 98201.8 | 104255.3 | 110721.6 | 117631.5 | 125017.3 |
| Total (B.ID) | 182331200.0 | 7.0% | 223585.8 | 239042.8 | 255618.5 | 273395.7 | 292463.8 |
| Total (B.$) | 154090400 | 7.0% | 189.2 | 202.2 | 216.3 | 231.3 | 247.4 |
*Data from Ministry of Planning – National Development Plan for (2018-2022)
Expected income [31]
| Year | Expected oil revenues (BID) | Miscellaneous income (BID) | ||||
|---|---|---|---|---|---|---|
| International Monetary Fund | Ministry of Oil | Strategic Budget Committee | Direct taxes | Indirect taxes | Other | |
| 2018 | 75045 | 75715.9 | 74033.4 | 4996.6 | 2213.7 | 5799.8 |
| 2019 | 74537 | 75715.9 | 74033.4 | 5146.1 | 2313.1 | 6038.4 |
| 2020 | 76050 | 75715.9 | 74033.4 | 5303.4 | 2390.7 | 6262.4 |
| 2021 | 77232 | 94914.6 | 74033.4 | 5466.5 | 2471.6 | 6492.3 |
| 2022 | 79076 | 103543.2 | 74033.4 | 5639.8 | 2555.8 | 6728.3 |
The portfolios of the stalled construction projects were named according to the state sectors: agricultural, energy, service, infrastructure, and other project portfolios. The portfolio in this study is a set of stalled projects that were suspended due to a lack of funding. Usually, projects in
Target growth rates for portfolios [32]
| Portfolio* | Target growth | Investment | Investment % | Distribution of planned investments over five years (BID) | ||||
|---|---|---|---|---|---|---|---|---|
| next 5 years | planned (bID) | 2018 | 2019 | 2020 | 2021 | 2022 | ||
| P1 | 8.4% | 7574.2 | 3.4% | 1280.2 | 1388.4 | 1505.0 | 1631.5 | 1768.5 |
| P2 | 7.5% | 84683.7 | 38.4% | 14579.5 | 15673 | 16848 | 18112 | 19470.5 |
| P3 | 1.0% | 5677.2 | 2.6% | 1077.9 | 1105.9 | 1134.7 | 1164.2 | 1194.5 |
| P4 | 10.5% | 4854.3 | 2.2% | 787.2 | 689.9 | 961.2 | 1062.2 | 1173.7 |
| P5 | 6.0% | 20243.3 | 9.2% | 3591.1 | 3806.5 | 4034.9 | 4277.0 | 4533.7 |
| P6 | 6.8% | 12233.6 | 5.5% | 2135.8 | 2281.1 | 2436.2 | 2601.8 | 2778.8 |
| P7 | 7.0% | 39582.1 | 17.9% | 6883.0 | 7362.8 | 7880.3 | 8431.9 | 9022.1 |
| P8 | 8.3% | 8545.1 | 3.9% | 14479.9 | 1568.0 | 1698.2 | 1839.1 | 1991.8 |
| P9 | 4.5% | 37219 | 16.9% | 6803.3 | 7109.5 | 7429.4 | 7763.7 | 8113.1 |
*Portfolios and assessments are coded for data organization
the construction portfolios have many common characteristics to address many strategic objectives of the government sector. For each construction portfolio, the projects are in the same class; therefore, a project in the portfolio is submitted to the same valuation factors for the priority matrix. The data and results obtained from the field survey are summarised in tables to track the analysis of the study [28, 32].
The Iraqi government’s financial budgets for the past ten years have been studied and analysed. Then, the researcher employed the theories of IPM with the support of administrative and financial cadres in the MOP. The study aimed to determine how to achieve optimal financial decisions that ensure project continuity. In addition to completing the stalled projects, this will help open it to the public as soon as possible.
The researcher classified the projects according to the sector as a portfolio with separate functional characteristics and independent requirements. Therefore, the strategic projects have two categories according to the funding resources:
Allocated budget projects have a predefined schedule (start and end information). The relationships between the activities are examined. For these portfolios, the researcher applied the concepts of resource levelling and smoothing, as shown in Eq. (1) [33]:
where F.F. is the free-float activity within the project in the portfolio, E.F. is the early finish of non-critical path activities, and E.S. is defined as ‘the minimum early start of sequential activities’.
Within a portfolio, free-float activities are applied to the momentum equation (Eq. (2)) [33]. Thus, the effectiveness of the activity is moved to the right position. The sub-sequent tables depict a summary of the results:
where I.F. is the moment factor of the shifted activity within a project of the portfolio, r.r. is the resource rate of activity, and m is the minimum number of moved cells.
Projects planned without a named budget show a community need. However, no financial capacity exists to establish these projects. Therefore, these projects are constructed depending on the revenues or internal operating amounts obtained by sponsoring institutions. An annual investment budget is usually used to complete these types of projects. Therefore, these projects have a known start time but no known end.
For this type of project, the researcher and competent cadres of MOP designed a methodology to assess the priorities of implementing the suspended projects called the priority matrix. The priority matrix prioritises each project package within the same portfolio. This methodology arranges the projects within a specific portfolio from the highest importance to the least importance. Within the portfolio, many projects await funding. The researcher developed priorities to allocate spending on the most important projects, to the least, according to evaluation axes related to the added value resulting from accelerating the implementation of each suspended project. Evaluation axes consist of 14 axes (strategic alignment, achieving portfolio requirements, aligned with the portfolio plan, spatial development, precedence of the portfolio, social feasibility, economic feasibility, percentage completion, financial percentage completion, payable financial dues, possibility of cost reducing, possibility of converting to an investment, possibility of transfer to operational budget, problems of project) whose total specific weight equals 100 per cent. Table 9 summarises the assessment using the priority matrix for each portfolio. Table 10 summarises the results.
Priority Matrix Assessment for Portfolios
| Assessment Axes of Priority Matrix* | Portfolios* | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| P1 | P2 | P3 | P4 | P5 | P6 | P7 | P8 | P9 | |
| Strategic Alignment | 8% | 9% | 4% | 12% | 11% | 8% | 10% | 10% | 10% |
| Achieving Portfolio Requirements | 8% | 9% | 8% | 8% | 2% | 10% | 5% | 5% | 2% |
| Aligned with the Portfolio Plan | 3% | 5% | 10% | 10% | 1% | 5% | 7% | 4% | 5% |
| Spatial Development | 3% | 5% | 3% | 4% | 8% | 8% | 6% | 5% | 3% |
| Precedence of the Portfolio | 6% | 8% | 7% | 6% | 7% | 10% | 9% | 8% | 6% |
| Social Feasibility | 8% | 10% | 2% | 8% | 9% | 6% | 10% | 8% | 10% |
| Economic Feasibility | 9% | 10% | 10% | 5% | 4% | 7% | 2% | 10% | 8% |
| Percentage Completion | 5% | 8% | 10% | 7% | 7% | 6% | 10% | 5% | 7% |
| Financial Percentage Completion | 7% | 5% | 8% | 6% | 3% | 5% | 2% | 4% | 5% |
| Payable Financial Dues | 4% | 4% | 5% | 5% | 9% | 10% | 8% | 8% | 10% |
| Possibility of Cost Reducing | 10% | 8% | 7% | 4% | 5% | 7% | 6% | 10% | 4% |
| Possibility of Converting to an Invest. | 4% | 5% | 9% | 8% | 6% | 7% | 10% | 4% | 10% |
| Possibility of Tran. to the Oper. Budg. | 15% | 10% | 7% | 5% | 8% | 4% | 10% | 6% | 10% |
| Problems of Project | 10% | 4% | 6% | 7% | 7% | 10% | 5% | 8% | 10% |
| Total | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% |
*Portfolios are coded for data organisation.
Results of the Studied projects
| Portfolio | Projects | Cost (MID) | Payment (%) | Complete (%) | Assess. of PM | Decision (no. 347) of 2015 |
|---|---|---|---|---|---|---|
| Lining the irrigation canals | 122904 | 4% | 18% | 52 | NE | |
| Regulation of the river | 115750 | 68% | 68% | 60 | NE | |
| Agricultural project portfolio | Jay barrage | 100000 | 32% | 99.5% | 55 | NE |
| Closed irrigation project | 25424 | 93.27% | 99.7% | 74 | NE | |
| Irrigation project | 23138 | 34% | 73% | 60 | NE | |
| Expansion of the rivers | 100000 | 10% | 11% | 54 | NE | |
| Construct modern villages | 359000 | 55.2% | 40% | 65 | NE | |
| Increase operational storage capacity for liquid gas/16 | 183910 | 91% | 86.2% | 84 | Continuous | |
| ball tank | ||||||
| Water supply to the refinery | 104575 | 87.26% | 96.22% | 40 | Continuous | |
| Oil project portfolio | Development of the oil field 14 in. pipe with pumping stations | 533110 225000 | 67.8% 80.2% | 72.48% 70.7% | 84 78 | Continuous Continuous |
| Rehabilitation of gas pressing stations | 118000 | 39.79% | 61.01% | 71 | Continuous | |
| Rehabilitation of K3 station | 96900 | 88.59% | 79% | 84 | Continuous | |
| Development of oil field | 14163.3 | 0% | 0% | 69 | Continuous | |
| Project sealed lead-acid battery MF and solar batteries | 25000 | 3% | 77% | 55 | Continuous | |
| Rehabilitate the company for petrochemical industries | 1200000 | 99% | 90% | 61 | Continuous | |
| Rehabilitate the fertiliser plant No. 3 with an electricity | 105075 | 90% | 98% | 68 | Continuous | |
| Transformative Industry portfolio | conversion station Rehabilitate the southern fertiliser plant IQ-P6 | 303790918 | 69% | 57% | 63 | Continuous |
| Geological survey, investigation and evaluation | 62500 | 69% | 56% | 32 | Continuous | |
| Rehabilitate the electric stations in the northern region | 25231.917 | 0% | 0% | 83 | Continuous | |
| Rehabilitate gaseous electric stations | 1237099.82 | 7% | 20% | 80 | Continuous | |
| Rehabilitate the thermal electric station | 462554.429 | 22% | 50% | 80 | Continuous | |
| Rehabilitate the hydropower electric stations | 72416.9028 | 32% | 74% | 80 | Continuous | |
| Energy project portfolio | Develop electrical networks at central regions | 1147636 | 11% | 5% | 67 | Continuous |
| Build electricity control centres in northern governorates | 63000 | 30% | 40% | 73 | Continuous | |
| Develop electrical networks for city centres | 128 | 60% | 65% | 73 | Continuous | |
| Residential complex | 70000 | 92% | 95% | 68 | Continuous | |
| Residential complex | 55186 | 95% | 97% | 69 | Continuous | |
| Infrastructure project portfolio Residential complex | Infrastructure for developing scientific capacity | 138300 | 0.07% | 0.07% | 45 | NJ |
| Rehabilitate the infrastructure | 13000 | 0.96% | 0.95% | 82 | NJ | |
| Rehabilitate the complex of the ministry | 43875 | 15% | 28% | 48 | Stalled | |
| Establish a general hospital | 147500 | 61% | 83% | 69 | Continuous | |
| Low income housing project | 74078.864 | 10% | 12% | 57 | Continuous | |
| Develop telecommunication networks for the main cities | 155222 | 0.19% | 1% | 49 | Continuous | |
| Optical cable network project (access network) | 216000 | 0.99% | 0.57% | 62 | Continuous | |
| Develop satellite channel | 28098 | 0.03% | 0.6% | 0.23 | Continuous | |
| Transport and Communications portfolio | West breakwater project of port | 951000 | 52% | 56% | 69 | Continuous |
| Railway | 57000 | 0.476% | 0.94% | 46 | Stalled | |
| Rehabilitate airport | 23016.4 | 0.385% | 0.92% | 66 | Stalled | |
| Rehabilitate airport | 59000 | 0.808% | 0.9% | 57 | Stalled | |
| Install electromechanical equipment for silo | 23000 | 0% | 0.25% | 70 | Continuous | |
| Rehabilitate horizontal high-capacity silos | 20000 | 0.27% | 0.58% | 71 | Continuous | |
| Trade project portfolio | Rehabilitate electromechanical/control the two groups (D&E) | 26250 | 0.22% | 0.27% | 75 | Continuous |
| Construct a metal silo | 12000 | 0.46% | 0.6% | 67 | Continuous | |
| Construct a metal silo | 12000 | 0.48% | 0.57% | 67 | Continuous | |
| Maintain and operate sewage water treatment projects | 34014 | 99.9% | 85% | 82 | NE | |
| Water purification plants/greater project | 847017 | 50.39% | 35.3% | 76 | NE | |
| Service project portfolio | Water purification project | 50000 | 58% | 77.6% | 66 | NE |
| Water purification project | 15000 | 87% | 69% | 80 | NE | |
| Water purification project | 73000 | 34% | 71.3% | 66 | NE | |
| Land acquisition for water projects in governorates | 30000 | 26% | 26% | 75 | NE | |
*Projects are coded for data organisation. NE: not evaluated; NJ: not yet judged
The researcher applied the concept of resource levelling where determinants of resources are directly related to the costs following the budget. The researcher relied on amounts allocated by the country’s annual budget, the ‘investment budget’. The investment budget is usually spent on stalled projects suspended during the year (i.e. it is distributed to projects in need according to priority). Within a portfolio, the budget should determine what is required for specified resources for each time unit. The national economy is weak but not because of production, which covers not only domestic consumption but also diversification of exports, which is almost zero. Generally, financial elements of the public state budget depend on oil sector production. This is not surprising because the country contains the world’s second-largest oil reserves. As a result, the revenues of oil account for about two-thirds of the country’s GDP for all exports and fiscal revenue. The petroleum industry represents a pivotal element of the national economy, contributing to the country’s GDP and growth and constituting 90% of the state revenue and almost all exports. Thus, the country’s GDP comprises the production volume fluctuation and oil prices.
7 Conclusions
In the present study, a numerical analysis has been carried out to verify and evaluate the applicability of intelligent portfolio management theory in the Iraqi construction industry. The field study conducted by the researcher indicated that strategic departments of national construction industry in Iraq need modern and effective administrative systems, national bodies need to improve the reality of its’ infrastructure by multi mid-term and long-term programmatic agenda strategies as five-year plans. Lack of professionalism in most of strategic management departments in Iraqi bodies, particularly with regard to financial allocation for service sectors as well as spread of corruption, nepotism and absence of transparency and justice. Priorities of financial resource allocation for infrastructure financing usually subject to several social and political considerations and personal convictions sometimes by the senior administrations in national construction industry. So, adopting intelligent portfolio management concepts’ in national institutions of the construction industry to solve state budget shortage, enhance enterprises’ efficiency for resource consumption. Also, this will support, financial decisions taken by senior management departments. The current study focused on settlement strategies regarding the risks of the national construction industry as effective solutions to the existing stalled construction projects. The increased use of portfolios is a means to share construction risks among construction projects. Construction institutions have adopted the use of portfolios for relatively low cost initial capital construction projects. The portfolio concept for such projects is oriented differently, where project importance and priority lead to new considerations when adopting the portfolio management theory in national construction industry.
References
[1] Kangari R, Riggs LS. Portfolio management in construction. Construct Manag Econ. 1988 Jun;6(2):161–9.10.1080/01446198800000014Search in Google Scholar
[2] Gann DM, Salter AJ. Innovation in project-based, service-enhanced firms: the construction of complex products and systems. Res Policy. 2000 Aug;29(7–8):955–72.10.1016/S0048-7333(00)00114-1Search in Google Scholar
[3] Khalaf, T. Z., Çağlar, H., Çağlar, A., & Hanoon, A. N. (2020). Particle Swarm Optimization Based Approach for Estimation of Costs and Duration of Construction Projects. Civil Engineering Journal, 6(2), 384-401. https://doi.org/10.28991/cej-2020-0309147810.28991/cej-2020-03091478Search in Google Scholar
[4] Omar, N. S., Hatem, W. A., & Najy, H. I. (2019). Predictive Modeling for Developing Maintenance Management in Construction Projects. Civil Engineering Journal, 5(4), 892-900. https://doi.org/10.28991/cej-2019-0309129710.28991/cej-2019-03091297Search in Google Scholar
[5] Hatem, W. A., Abd, A. M., & Abbas, N. N. (2017). Testing a Measurement Model of BIM Potential Benefits in Iraqi Construction Projects. Civil Engineering Journal, 3(12). https://doi.org/10.28991/cej-03096310.28991/cej-030963Search in Google Scholar
[6] Abed, H. R., Hatem, W. A., & Jasim, N. A. (2019). Adopting BIM Technology in Fall Prevention Plans. Civil Engineering Journal, 5(10), 2270-2281. https://doi.org/10.28991/cej-2019-0309141010.28991/cej-2019-03091410Search in Google Scholar
[7] Toor SR, Ogunlana SO. Critical COMs of success in large-scale construction projects: evidence from Thailand construction industry. Int J Proj Manag. 2008 May;26(4):420–30.10.1016/j.ijproman.2007.08.003Search in Google Scholar
[8] Dashti MA, Farjami Y, Vedadi A, Anisseh M. ‘Implementation of particle swarm optimization in construction of optimal risky portfolios’, 2007 IEEE International Conference on Industrial Engineering and Engineering Management, Dec. 2007. https://doi.org/10.1109/IEEM.2007.441930310.1109/IEEM.2007.4419303Search in Google Scholar
[9] Fabozzi FJ, Gupta F,Markowitz HM. The legacy of modern portfolio theory. J Invest. 2002 Aug;11(3):7–22.10.3905/joi.2002.319510Search in Google Scholar
[10] Rajegopal S. What is the role of leadership in successful delivery execution. Portfolio Management; 2013. pp. 170–7.10.1057/9781137023346_12Search in Google Scholar
[11] Cooper RG, Edgett SJ, Kleinschmidt EJ. New product portfolio management: practices and performance. J Prod Innov Manage. 1992 Jul;16(4):333–51.10.1111/1540-5885.1640333Search in Google Scholar
[12] Guo N, Yu SW. The necessity of project portfolio management in the construction industry of China mainland. Appl Mech Mater. 2013 Aug;357–360:2238–41.10.4028/www.scientific.net/AMM.357-360.2238Search in Google Scholar
[13] Meskendahl S. The influence of business strategy on project portfolio management and its success— A conceptual framework. Int J Proj Manag. 2010 Dec;28(8):807–17.10.1016/j.ijproman.2010.06.007Search in Google Scholar
[14] Blomquist T, Müller R. Practices, roles, and responsibilities of middle managers in program and portfolio management. Proj Manage J. 2006 Mar;37(1):52–66.10.1177/875697280603700105Search in Google Scholar
[15] Thiry M. ‘For DAD’: A programme management life-cycle process. Int J Proj Manag. 2004 Apr;22(3):245–52.10.1016/S0263-7863(03)00064-4Search in Google Scholar
[16] ‘IEEE Guide – Adoption of the Project Management Institute (PMI(R)) standard. A guide to the Project Management Body of Knowledge (PMBOK(R) Guide)fourth edition’.Search in Google Scholar
[17] Meskendahl S. The influence of business strategy on project portfolio management and its success— A conceptual framework. Int J Proj Manag. 2010 Dec;28(8):807–17.10.1016/j.ijproman.2010.06.007Search in Google Scholar
[18] Junnonen JM. Junnonen, ‘Strategy formation in construction firms’. Eng Construct Architect Manag. 1998 Jun;5(2):107–14.10.1108/eb021065Search in Google Scholar
[19] Chinowsky PS, Meredith JE. Strategic management in construction. J Constr Eng Manage. 2000 Jan;126(1):1–9.10.1061/(ASCE)0733-9364(2000)126:1(1)Search in Google Scholar
[20] Pries F, Janszen F. Innovation in the construction industry: the dominant role of the environment. Construct Manag Econ. 1995 Jan;13(1):43–51.10.1080/01446199500000006Search in Google Scholar
[21] Construction project leadership. Management of Construction Projects. 2017;(Mar):274–86.10.4324/9781315529097-19Search in Google Scholar
[22] K. A. Artto and P. H. Dietrich, ‘Strategic business management through multiple projects’, The Wiley Guide to Managing Projects, Nov. 2007, ch.7, pp. 144–176.10.1002/9780470172391.ch7Search in Google Scholar
[23] Subramaniam A. (2009), Holistic approach to manage strategic initiatives, [Project Portfolio Management] Available: https://www.slideshare.net/anandsubramaniam/project-portfolio-management(Accessed July 12, 2019)Search in Google Scholar
[24] Kaiser MG, El Arbi F, Ahlemann F. Successful project portfolio management beyond project selection techniques: understanding the role of structural alignment. Int J Proj Manag. 2015 Jan;33(1):126–39.10.1016/j.ijproman.2014.03.002Search in Google Scholar
[25] L. Romano, ‘Adaptive portfolio management’, Advances in IT Personnel and Project Management, pp. 153–177. https://doi.org/10.4018/978-1-5225-2151-8.ch00610.4018/978-1-5225-2151-8.ch006Search in Google Scholar
[26] The portfolio management PMO and metrics. Project Management Metrics, KPIs, and Dashboards. 2017;(Sep):413–23.10.1002/9781119427599.ch8Search in Google Scholar
[27] Newnan DG. ‘A review of: ’Engineeringeconomy: A behavioralapproach by Anthony Tarquin and Leland Blank’. Eng Econ. 1979 Jan;25(1):75–7.10.1080/00137917908956220Search in Google Scholar
[28] Fabozzi FJ, Gupta F,Markowitz HM. The legacy of modern portfolio theory. J Invest. 2002 Aug;11(3):7–22.10.3905/joi.2002.319510Search in Google Scholar
[29] Report of Iraqi Ministry of Planning, Central Statistical Organization, Directorate of Standard Numbers and Department of Sectors Planning.Search in Google Scholar
[30] Presidency of Council of Ministers, National Investment Commission, Major strategic projects available for investment according to sector.Search in Google Scholar
[31] Ministry of Finance, Department of Budget.Search in Google Scholar
[32] Economic visions of the National Investment Commission and the report of economic reform policy for the next five years.Search in Google Scholar
[33] Pilcher R. Principles of construction management. McGraw-Hill College; 1992.[Google Scholar].Search in Google Scholar
© 2020 K. R. Erzaij et al., published by De Gruyter
This work is licensed under the Creative Commons Attribution 4.0 International License.
Articles in the same Issue
- Regular Articles
- Fabrication of aluminium covetic casts under different voltages and amperages of direct current
- Inhibition effect of the synergistic properties of 4-methyl-norvalin and 2-methoxy-4-formylphenol on the electrochemical deterioration of P4 low carbon mold steel
- Logistic regression in modeling and assessment of transport services
- Design and development of ultra-light front and rear axle of experimental vehicle
- Enhancement of cured cement using environmental waste: particleboards incorporating nano slag
- Evaluating ERP System Merging Success In Chemical Companies: System Quality, Information Quality, And Service Quality
- Accuracy of boundary layer treatments at different Reynolds scales
- Evaluation of stabiliser material using a waste additive mixture
- Optimisation of stress distribution in a highly loaded radial-axial gas microturbine using FEM
- Analysis of modern approaches for the prediction of electric energy consumption
- Surface Hardening of Aluminium Alloy with Addition of Zinc Particles by Friction Stir Processing
- Development and refinement of the Variational Method based on Polynomial Solutions of Schrödinger Equation
- Comparison of two methods for determining Q95 reference flow in the mouth of the surface catchment basin of the Meia Ponte river, state of Goiás, Brazil
- Applying Intelligent Portfolio Management to the Evaluation of Stalled Construction Projects
- Disjoint Sum of Products by Orthogonalizing Difference-Building ⴱ
- The Development of Information System with Strategic Planning for Integrated System in the Indonesian Pharmaceutical Company
- Simulation for Design and Material Selection of a Deep Placement Fertilizer Applicator for Soybean Cultivation
- Modeling transportation routes of the pick-up system using location problem: a case study
- Pinless friction stir spot welding of aluminium alloy with copper interlayer
- Roof Geometry in Building Design
- Review Articles
- Silicon-Germanium Dioxide and Aluminum Indium Gallium Arsenide-Based Acoustic Optic Modulators
- RZ Line Coding Scheme With Direct Laser Modulation for Upgrading Optical Transmission Systems
- LOGI Conference 2019
- Autonomous vans - the planning process of transport tasks
- Drivers ’reaction time research in the conditions in the real traffic
- Design and evaluation of a new intersection model to minimize congestions using VISSIM software
- Mathematical approaches for improving the efficiency of railway transport
- An experimental analysis of the driver’s attention during train driving
- Risks associated with Logistics 4.0 and their minimization using Blockchain
- Service quality of the urban public transport companies and sustainable city logistics
- Charging electric cars as a way to increase the use of energy produced from RES
- The impact of the truck loads on the braking efficiency assessment
- Application of virtual and augmented reality in automotive
- Dispatching policy evaluation for transport of ready mixed concrete
- Use of mathematical models and computer software for analysis of traffic noise
- New developments on EDR (Event Data Recorder) for automated vehicles
- General Application of Multiple Criteria Decision Making Methods for Finding the Optimal Solution in City Logistics
- The influence of the cargo weight and its position on the braking characteristics of light commercial vehicles
- Modeling the Delivery Routes Carried out by Automated Guided Vehicles when Using the Specific Mathematical Optimization Method
- Modelling of the system “driver - automation - autonomous vehicle - road”
- Limitations of the effectiveness of Weigh in Motion systems
- Long-term urban traffic monitoring based on wireless multi-sensor network
- The issue of addressing the lack of parking spaces for road freight transport in cities - a case study
- Simulation of the Use of the Material Handling Equipment in the Operation Process
- The use of simulation modelling for determining the capacity of railway lines in the Czech conditions
- Proposals for Using the NFC Technology in Regional Passenger Transport in the Slovak Republic
- Optimisation of Transport Capacity of a Railway Siding Through Construction-Reconstruction Measures
- Proposal of Methodology to Calculate Necessary Number of Autonomous Trucks for Trolleys and Efficiency Evaluation
- Special Issue: Automation in Finland
- 5G Based Machine Remote Operation Development Utilizing Digital Twin
- On-line moisture content estimation of saw dust via machine vision
- Data analysis of a paste thickener
- Programming and control for skill-based robots
- Using Digital Twin Technology in Engineering Education – Course Concept to Explore Benefits and Barriers
- Intelligent methods for root cause analysis behind the center line deviation of the steel strip
- Engaging Building Automation Data Visualisation Using Building Information Modelling and Progressive Web Application
- Real-time measurement system for determining metal concentrations in water-intensive processes
- A tool for finding inclusion clusters in steel SEM specimens
- An overview of current safety requirements for autonomous machines – review of standards
- Expertise and Uncertainty Processing with Nonlinear Scaling and Fuzzy Systems for Automation
- Towards online adaptation of digital twins
- Special Issue: ICE-SEAM 2019
- Fatigue Strength Analysis of S34MnV Steel by Accelerated Staircase Test
- The Effect of Discharge Current and Pulse-On Time on Biocompatible Zr-based BMG Sinking-EDM
- Dynamic characteristic of partially debonded sandwich of ferry ro-ro’s car deck: a numerical modeling
- Vibration-based damage identification for ship sandwich plate using finite element method
- Investigation of post-weld heat treatment (T6) and welding orientation on the strength of TIG-welded AL6061
- The effect of nozzle hole diameter of 3D printing on porosity and tensile strength parts using polylactic acid material
- Investigation of Meshing Strategy on Mechanical Behaviour of Hip Stem Implant Design Using FEA
- The effect of multi-stage modification on the performance of Savonius water turbines under the horizontal axis condition
- Special Issue: Recent Advances in Civil Engineering
- The effects of various parameters on the strengths of adhesives layer in a lightweight floor system
- Analysis of reliability of compressed masonry structures
- Estimation of Sport Facilities by Means of Technical-Economic Indicator
- Integral bridge and culvert design, Designer’s experience
- A FEM analysis of the settlement of a tall building situated on loess subsoil
- Behaviour of steel sheeting connections with self-drilling screws under variable loading
- Resistance of plug & play N type RHS truss connections
- Comparison of strength and stiffness parameters of purlins with different cross-sections of profiles
- Bearing capacity of floating geosynthetic encased columns (GEC) determined on the basis of CPTU penetration tests
- The effect of the stress distribution of anchorage and stress in the textured layer on the durability of new anchorages
- Analysis of tender procedure phases parameters for railroad construction works
- Special Issue: Terotechnology 2019
- The Use of Statistical Functions for the Selection of Laser Texturing Parameters
- Properties of Laser Additive Deposited Metallic Powder of Inconel 625
- Numerical Simulation of Laser Welding Dissimilar Low Carbon and Austenitic Steel Joint
- Assessment of Mechanical and Tribological Properties of Diamond-Like Carbon Coatings on the Ti13Nb13Zr Alloy
- Characteristics of selected measures of stress triaxiality near the crack tip for 145Cr6 steel - 3D issues for stationary cracks
- Assessment of technical risk in maintenance and improvement of a manufacturing process
- Experimental studies on the possibility of using a pulsed laser for spot welding of thin metallic foils
- Angular position control system of pneumatic artificial muscles
- The properties of lubricated friction pairs with diamond-like carbon coatings
- Effect of laser beam trajectory on pocket geometry in laser micromachining
- Special Issue: Annual Engineering and Vocational Education Conference
- The Employability Skills Needed To Face the Demands of Work in the Future: Systematic Literature Reviews
- Enhancing Higher-Order Thinking Skills in Vocational Education through Scaffolding-Problem Based Learning
- Technology-Integrated Project-Based Learning for Pre-Service Teacher Education: A Systematic Literature Review
- A Study on Water Absorption and Mechanical Properties in Epoxy-Bamboo Laminate Composite with Varying Immersion Temperatures
- Enhancing Students’ Ability in Learning Process of Programming Language using Adaptive Learning Systems: A Literature Review
- Topical Issue on Mathematical Modelling in Applied Sciences, III
- An innovative learning approach for solar power forecasting using genetic algorithm and artificial neural network
- Hands-on Learning In STEM: Revisiting Educational Robotics as a Learning Style Precursor
Articles in the same Issue
- Regular Articles
- Fabrication of aluminium covetic casts under different voltages and amperages of direct current
- Inhibition effect of the synergistic properties of 4-methyl-norvalin and 2-methoxy-4-formylphenol on the electrochemical deterioration of P4 low carbon mold steel
- Logistic regression in modeling and assessment of transport services
- Design and development of ultra-light front and rear axle of experimental vehicle
- Enhancement of cured cement using environmental waste: particleboards incorporating nano slag
- Evaluating ERP System Merging Success In Chemical Companies: System Quality, Information Quality, And Service Quality
- Accuracy of boundary layer treatments at different Reynolds scales
- Evaluation of stabiliser material using a waste additive mixture
- Optimisation of stress distribution in a highly loaded radial-axial gas microturbine using FEM
- Analysis of modern approaches for the prediction of electric energy consumption
- Surface Hardening of Aluminium Alloy with Addition of Zinc Particles by Friction Stir Processing
- Development and refinement of the Variational Method based on Polynomial Solutions of Schrödinger Equation
- Comparison of two methods for determining Q95 reference flow in the mouth of the surface catchment basin of the Meia Ponte river, state of Goiás, Brazil
- Applying Intelligent Portfolio Management to the Evaluation of Stalled Construction Projects
- Disjoint Sum of Products by Orthogonalizing Difference-Building ⴱ
- The Development of Information System with Strategic Planning for Integrated System in the Indonesian Pharmaceutical Company
- Simulation for Design and Material Selection of a Deep Placement Fertilizer Applicator for Soybean Cultivation
- Modeling transportation routes of the pick-up system using location problem: a case study
- Pinless friction stir spot welding of aluminium alloy with copper interlayer
- Roof Geometry in Building Design
- Review Articles
- Silicon-Germanium Dioxide and Aluminum Indium Gallium Arsenide-Based Acoustic Optic Modulators
- RZ Line Coding Scheme With Direct Laser Modulation for Upgrading Optical Transmission Systems
- LOGI Conference 2019
- Autonomous vans - the planning process of transport tasks
- Drivers ’reaction time research in the conditions in the real traffic
- Design and evaluation of a new intersection model to minimize congestions using VISSIM software
- Mathematical approaches for improving the efficiency of railway transport
- An experimental analysis of the driver’s attention during train driving
- Risks associated with Logistics 4.0 and their minimization using Blockchain
- Service quality of the urban public transport companies and sustainable city logistics
- Charging electric cars as a way to increase the use of energy produced from RES
- The impact of the truck loads on the braking efficiency assessment
- Application of virtual and augmented reality in automotive
- Dispatching policy evaluation for transport of ready mixed concrete
- Use of mathematical models and computer software for analysis of traffic noise
- New developments on EDR (Event Data Recorder) for automated vehicles
- General Application of Multiple Criteria Decision Making Methods for Finding the Optimal Solution in City Logistics
- The influence of the cargo weight and its position on the braking characteristics of light commercial vehicles
- Modeling the Delivery Routes Carried out by Automated Guided Vehicles when Using the Specific Mathematical Optimization Method
- Modelling of the system “driver - automation - autonomous vehicle - road”
- Limitations of the effectiveness of Weigh in Motion systems
- Long-term urban traffic monitoring based on wireless multi-sensor network
- The issue of addressing the lack of parking spaces for road freight transport in cities - a case study
- Simulation of the Use of the Material Handling Equipment in the Operation Process
- The use of simulation modelling for determining the capacity of railway lines in the Czech conditions
- Proposals for Using the NFC Technology in Regional Passenger Transport in the Slovak Republic
- Optimisation of Transport Capacity of a Railway Siding Through Construction-Reconstruction Measures
- Proposal of Methodology to Calculate Necessary Number of Autonomous Trucks for Trolleys and Efficiency Evaluation
- Special Issue: Automation in Finland
- 5G Based Machine Remote Operation Development Utilizing Digital Twin
- On-line moisture content estimation of saw dust via machine vision
- Data analysis of a paste thickener
- Programming and control for skill-based robots
- Using Digital Twin Technology in Engineering Education – Course Concept to Explore Benefits and Barriers
- Intelligent methods for root cause analysis behind the center line deviation of the steel strip
- Engaging Building Automation Data Visualisation Using Building Information Modelling and Progressive Web Application
- Real-time measurement system for determining metal concentrations in water-intensive processes
- A tool for finding inclusion clusters in steel SEM specimens
- An overview of current safety requirements for autonomous machines – review of standards
- Expertise and Uncertainty Processing with Nonlinear Scaling and Fuzzy Systems for Automation
- Towards online adaptation of digital twins
- Special Issue: ICE-SEAM 2019
- Fatigue Strength Analysis of S34MnV Steel by Accelerated Staircase Test
- The Effect of Discharge Current and Pulse-On Time on Biocompatible Zr-based BMG Sinking-EDM
- Dynamic characteristic of partially debonded sandwich of ferry ro-ro’s car deck: a numerical modeling
- Vibration-based damage identification for ship sandwich plate using finite element method
- Investigation of post-weld heat treatment (T6) and welding orientation on the strength of TIG-welded AL6061
- The effect of nozzle hole diameter of 3D printing on porosity and tensile strength parts using polylactic acid material
- Investigation of Meshing Strategy on Mechanical Behaviour of Hip Stem Implant Design Using FEA
- The effect of multi-stage modification on the performance of Savonius water turbines under the horizontal axis condition
- Special Issue: Recent Advances in Civil Engineering
- The effects of various parameters on the strengths of adhesives layer in a lightweight floor system
- Analysis of reliability of compressed masonry structures
- Estimation of Sport Facilities by Means of Technical-Economic Indicator
- Integral bridge and culvert design, Designer’s experience
- A FEM analysis of the settlement of a tall building situated on loess subsoil
- Behaviour of steel sheeting connections with self-drilling screws under variable loading
- Resistance of plug & play N type RHS truss connections
- Comparison of strength and stiffness parameters of purlins with different cross-sections of profiles
- Bearing capacity of floating geosynthetic encased columns (GEC) determined on the basis of CPTU penetration tests
- The effect of the stress distribution of anchorage and stress in the textured layer on the durability of new anchorages
- Analysis of tender procedure phases parameters for railroad construction works
- Special Issue: Terotechnology 2019
- The Use of Statistical Functions for the Selection of Laser Texturing Parameters
- Properties of Laser Additive Deposited Metallic Powder of Inconel 625
- Numerical Simulation of Laser Welding Dissimilar Low Carbon and Austenitic Steel Joint
- Assessment of Mechanical and Tribological Properties of Diamond-Like Carbon Coatings on the Ti13Nb13Zr Alloy
- Characteristics of selected measures of stress triaxiality near the crack tip for 145Cr6 steel - 3D issues for stationary cracks
- Assessment of technical risk in maintenance and improvement of a manufacturing process
- Experimental studies on the possibility of using a pulsed laser for spot welding of thin metallic foils
- Angular position control system of pneumatic artificial muscles
- The properties of lubricated friction pairs with diamond-like carbon coatings
- Effect of laser beam trajectory on pocket geometry in laser micromachining
- Special Issue: Annual Engineering and Vocational Education Conference
- The Employability Skills Needed To Face the Demands of Work in the Future: Systematic Literature Reviews
- Enhancing Higher-Order Thinking Skills in Vocational Education through Scaffolding-Problem Based Learning
- Technology-Integrated Project-Based Learning for Pre-Service Teacher Education: A Systematic Literature Review
- A Study on Water Absorption and Mechanical Properties in Epoxy-Bamboo Laminate Composite with Varying Immersion Temperatures
- Enhancing Students’ Ability in Learning Process of Programming Language using Adaptive Learning Systems: A Literature Review
- Topical Issue on Mathematical Modelling in Applied Sciences, III
- An innovative learning approach for solar power forecasting using genetic algorithm and artificial neural network
- Hands-on Learning In STEM: Revisiting Educational Robotics as a Learning Style Precursor