Based on the Sino-foreign petroleum cooperation project, the benefit evaluation algorithm of real economy based on big data analysis is proposed. The investment payback period, net present value, internal rate of return, discounted profit after investment and option value are selected as the benefit evaluation indicators of the real economy. The benchmark yield, discount rate and oil option parameters are defined as the benefits evaluation parameters of the real economy. Through the Delphi method and the analytic hierarchy process, the weight of each factor is specified. The method of expert independent scoring is used to construct the judgment matrix, and the consistency check is performed on the sort. The feature quantity matrix of the evaluation indicator is established to perform dimensionless processing on the original data. The project’s economic benefit indicators are divided into positive indicators of “ideal economic benefits” and negative indicators of “negative economic benefits”, the grey correlations are calculated, and real economic benefits are assessed. The results of project example analysis show that the algorithm not only realizes the whole life cycle management of overseas oil and gas cooperation projects, but also conducts tracking and evaluation of project implementation and economic benefits during the implementation process, and conducts sensitivity analysis on key indicators, that provides effective decision support for managers.

1 Introduction

The real economy refers to the economy created by people on the earth through the use of tools. It includes economic activities such as the production and circulation of material and spiritual products. It includes the production and service sectors of agriculture, industry, transportation and communications, business services, construction and cultural industries, as well as the departments of spiritual products such as education, culture, knowledge, information, art and sports [1]. Economic efficiency refers to the value or product that the enterprise occupies as much resources and labor as possible in its production activities. There are two indicators here, namely input and output indicators, where resources are input-type indicators and products are output-type indicators [2]. When the output is greater than the input, the economic activity can be considered to be economically beneficial. At the same time, companies have social responsibilities and cannot pursue economic benefits unilaterally [3].

In summary, companies must consider three aspects in terms of economic benefits:

  1. first, the output is greater than the input, that is, the output is greater than the consumption;

  2. second, the output is greater than the input to match, taking into account the long-term interests of the enterprise;

  3. the third is to pursue economic benefits in the context of undertaking certain social responsibilities.

Only when the above conditions are met, the economic benefits of the enterprise can be characterized as good, which is the precondition for the evaluation of economic benefits. The comprehensive analysis of the selected indicators is the economic benefit evaluation. The evaluation results will guide the company’s next cost control, capital investment and development strategy, and can also serve as the basis for corporate performance evaluation [4]. After determining the indicator system and selecting the scientific method of evaluation, the steps of evaluating the economic benefit indicators will be considered.

The benefit evaluation algorithm of the real economy based on multi-level extension evaluation method is proposed by some scholars [5]. Some have proposed the entity economic benefit evaluation algorithm based on the comprehensive index method [6]. Some scholars propose the entity economic benefit evaluation algorithm based on the analytic hierarchy process and the coefficient of variation method [7]. In addition, some scholars propose the entity economic benefit evaluation algorithm based on the entropy weight method [8].

The above algorithms cannot realize the whole life cycle management of the real economy, and in the process of project implementation, the economic benefits of the project cannot be evaluated, and the sensitivity analysis of key indicators cannot be performed. It also does not provide effective support for managing business and investment decisions.

In response to these problems, the benefit evaluation algorithm of real economy based on big data analysis is researched and proposed, and its specific research framework is described as follows:

  1. selection of the benefit evaluation indicators of the real economy;

  2. determination of evaluation parameters;

  3. construction of the evaluation model;

  4. project case analysis, test of the effectiveness of the algorithm;

  5. summary and outlook.

2 Methods

2.1 Selection of indicators for benefit evaluation of real economy

2.1.1 Payback period

The payback period is the period required to recover all the investment from the start of the project. The payback period includes the duration of the exploration and development project and the term of the commercial development recovery fund [9]. The formula for expressing the payback period is:

(1)t=1Pt(CICO)t=0

where Pt is the payback period; CI and COrepresent cash inflows and cash outflows, respectively.

The biggest advantage of the investment payback period indicator is that it is intuitive and simple, can measure the investment risk, and reflects the advantages and disadvantages of the investment benefit to a certain extent, so it has been widely used.

However, there are certain shortcomings and limitations in the investment recovery period. (1) The investment recovery period cannot reflect the benefits of the project after the investment is recovered. (2) The investment recovery period is greatly affected by the cash inflow, which will not be conducive to the comparison between the schemes (3) The calculation of the payback period is generally carried out in the static manner without considering the time value of the funds.

Although the payback period does not fully measure the economic profit of the project, it has the effect of measuring the investment risk. In overseas exploration investment projects with high political and economic risk, the recovery of investment must be guaranteed before it can rise to the evaluation of the project’s income. Therefore, the payback period should be used as the important indicator to measure overseas exploration investment projects.

2.1.2 Net present value

The net present value is the cumulative value of the discounted face value of the net cash flow, and its calculation formula is:

(2)NPV=t=0T(CItCOt)×(1+R)t

where CIt and COt represent the cash inflow and the cash outflow of the tth year, respectively; R is the discount rate; T means the life cycle of the item.

The net present value not only considers the cash flow that occurs during the whole process of the project, but also considers the time value of the funds, which can dynamically reflect the profitability of the project during the economic life. It is the common indicator for evaluating the economic effects of projects and one of the mandatory indicators for international oil companies in evaluating exploration investment projects [10].

2.1.3 Internal rate of return

The internal rate of return refers to the discount rate when the project’s current value of net cash flow is equal to zero over the life of the project. This indicator is used to evaluate the project’s profitability and is an indicator of the efficiency of capital utilization. The calculation of the internal rate of return implies a basic assumption that all the economic benefits obtained during the life of the project can be used for reinvestment, and the reinvested rate of return is equal to the internal rate of return. Its calculation formula is as follows:

(3)t=1T(CItCOt)(1+i)t=0

where i represents the internal rate of return of the real economy.

Among all economic evaluation indicators, internal rate of return is another important indicator, which is an important evaluation basis for the financial profitability of investment projects [11].

2.1.4 Discounted after-tax investment profit rate

The profit margin is still not perfect by measuring the payback period, net present value and internal rate of return. The profitability of unit investment needs to be considered. Offshore oil exploration projects are risky and long-term, and the time value of funds must be considered. Therefore, the discounted after-tax investment profit rate is selected. The specific calculation formula is:

(4)DPR=t=1TPtt=1TIt

where DPR represents the project’s discounted after-tax investment profit rate; It is the investment amount in the t-th year.

At present, many international oil companies regard the discounted after-tax investment profit rate as an important indicator of investment decisions.

2.1.5 Option value

In actual work, the investment depends not only on the value added by the project, but also on the strategic value of it. Therefore, projects with the net present value less than zero are not eager to be abandoned. Sometimes the temporarily lossy project may bring greater benefits to the future of the enterprise. In the benefits evaluation of the real economy, the option value of the project must be considered. Through the Black-Scholes model, the option value of the real economy is calculated and its formula is as follows:

(5)C=AN(d1)XerτN(d2)
(6)d1=ln(A/X)+τ(rδ+σ2/2)στ
(7)d2=d1στ

where τis the expiration date of the selected oil option; A represents the present value of the income after the τ time; Xmeans the expected investment in the next stage; r represents the risk-free rate, generally taking the interest rate of the national debt; δ is the annual loss rate of cash flow, which is generally considered to be equal to r; σ represents the volatility of the value of developed petroleum resources; N(x) is the cumulative probability distribution function of the standard normal distribution (i.e., the probability that the random variable is less than x).

2.2 Determination of evaluation parameters

2.2.1 Benchmark rate of return

Benchmark rate of return should be determined based on the project’s risk level, inflation factors, interest rates, tax policies, reinvestment opportunities and expected goals. International oil companies generally set specific standards for the company, and the benchmark yields are generally used as trade secrets and are not leaked [12].

2.2.2 Discount rate

There are currently three different methods for calculating the international discount rate:

  1. the end-year method:

    Calculate the present value by the face value of the net cash flow at the end of the year. The calculation formula of the discount rate is (1 + j)n;

  2. the mid-year method:

    Converting the present value by the face value of the net cash flow in the middle of the year, the calculation formula of the discount rate is (1 + j)0.5−n;

  3. Continuous compounding method:

    The internationally used continuous compounding method based on the calculation formula of the continuous equal annual cash flow discount rate is ej1jeniwhere, j is the nominal annual discount rate; n is the number of years of equal annual cash flow; e is the bottom of the natural logarithm.

    The value of the discount rate in each oil company has its own measurement standards, but in general, time, risk, inflation and other factors are generally necessary to be considered, usually taking the expected rate of return or weighted capital cost of similar or similar projects. In the current economic evaluation method in China, the first method is used for calculation.

2.2.3 Oil option parameters

The calculation of the value of the oil option involves six parameters, which are as following:

  1. The present value of the petroleum resources to be developed A refers to the present value of the income of the petroleum resources to be developed after τtime, which can be obtained by the net present value method based on the predicted cash flow;

  2. Expenses X for the development of petroleum resources, including block acquisition costs, exploration investment;

  3. Risk-free interest rate r, r takes the interest rate of US short-term government bonds;

  4. 4 Annual cash flow loss rate δ , generally similar to r;

  5. The volatility δof the value of petroleum resources, in view of the value of petroleum resources mainly affected by fluctuations in oil prices, so the value of it is similar to the volatility of oil prices;

  6. The term of the oil option is τ,where the exploration period of the contract is used as the value of τ.

2.3 Benefit evaluation of the real economy

2.3.1 Determination of the weight of the benefit evaluation index of the real economy

The status of each indicator is different in the system. The differences are mainly reflected in the following two aspects: First, the evaluator is in the different environment; second, the indicator plays a different role in the evaluation process. In the evaluation model, the indicators are recognized by the importance and degree of influence. On the other hand, the relative size of the indicator weight directly affects the outcome of the benefit evaluation. Reasonable determination of the weight coefficient, objectively reflecting its importance, will directly improve the accuracy of the final evaluation.

The Delphi method is combined with the analytic hierarchy process to weight the distribution factors. The experts’ opinions are collected as the basis for determining the weight [13]. The working steps are as follows:

Consultation questionnaire

The specific weight values are not required to be directly determined, and the relative importance between the indicators needs to be given. The relative importance is represented by the natural numbers 1, 2, 3... 9 and their reciprocals 1/2, 1/3... 1/9; the meanings are shown in Table 1.

Table 1

Calibration method for judging the importance of two indicators

Scale valuemeaning
1they are of equal importance;
3the C1 is slightly more important than the C2;
5the C1 is more important than the C2;
7the C1 is obviously more important than the C2;
9the C1 is extremely more important than the C2;
2, 4, 6, 8Between the two adjacent levels;
1/2, 1/3,..., 1/9The result is the opposite of the above result

2.3.2 Calculation of weight vector and consistency test

After the establishment of the indicator system, the affiliation between the upper and lower levels will be fixed. For the same level of indicators, the two-two comparison method can be used to determine the relative weight relationship. The specific operations are as follows:

Construct the pairwise comparison matrix

Constructing the judgment matrix is the key to analytic analysis, which is directly related to the accuracy of the benefit assessment. The method of independent scoring by experts in this paper is used to construct the judgment matrix and perform consistency check on the sort. The same level indicators are compared in pairs, and the results are represented by the T.L. ratio scale, as shown in Table 1.

Assume that element B of the primary indicator is related to the element B1B2, · · · , Bm in the next level indicator (m is the number of indicators). By constructing the judgment matrix B as shown in Table 2, the importance of each element in the secondary index with respect to B is analyzed.

Table 2

Judgment matrix structure

BBB...B
B1b11b12...b1m
B2b21b22...b2m
...............
Bmbm1bm2...bmm

The judgment matrix has the following properties:

(8)bij>0
(9)bij=1bji
(10)bij=1

Calculation of index weights

The geometric mean method is used to calculate the weight of the indicators.

The product of each row element in the judgment matrix is calculated as follows.

(11)Mi=i=1mbij(i=1,2,,m)

By calculating the N root of M i , Wi¯can be written as

(12)Wi¯=NMi

where Wi¯is normalized to obtain the weight vector Wi of the evaluation indicator:

(13)Wi=Wi¯i=1mWi¯

Consistency test

The maximum eigenvalue of the judgment matrix is calculated

(14)λmax=1m×i=1m(Bi×Wi)Wi

The consistency index CI of judgment matrix is calculated,

(15)CI=(λmaxm)/(m1)

The formula for calculating the random consistency ratio CR is as follows:

(16)CR=CI/RI

where RI represents the average random consistency index of the judgment matrix of the real economic benefit evaluation index.

According to the above formula (16), the consistency check is performed on the constructed judgment matrix. It is generally considered that the judgment matrix has acceptable consistency, and CR < 0.1. Otherwise, the judgment matrix needs to be corrected. The values of the random consistency coefficient are shown in Table 3.

Table 3

Value of random consistency coefficient

Order of the matrix12345678910
RI value0.00.00.580.901.121.241.321.411.451.63

2.3.3 Establishment of indicator feature quantity matrix

Assume that there are n mines to be evaluated, and each mine has m evaluation indicators. By arranging the indicators in order, the index feature matrix of n order can be obtained [14]:

(17)X=x11x12x1nx21x22x2nMMMMxm1xm2xmn

where xij is the feature quantity of the i(i = 1, 2, · · · , m) evaluation indicator of the j(j = 1, 2, · · · , n) mine.

Usually, it has two types of benefits: the bigger of the benefit the better and the smaller of the cost the better.

The so-called mean value, that is, the average value of the same index of the evaluated mine is used to remove each item, and the formula is

(18)xij=xiji=1mxij

2.3.4 “Positive economic benefits” and “Negative economic benefits”

Let I+ is the set of profitable economic indicators; I is the cost-based economic indicators.

The two types of indicators can be regarded as one collection, and the “positive economic benefits” can be combined into one collection:

(19)x+={maxjxijiI+,maxjxijiI+j=1,2,,n}=x1+,x2+,x3+,,xm+
(20)x={maxjxijiI,maxjxijiIj=1,2,,n}=x1,x2,x3,,xm

The approximate degree of the ith indicator of the positive ideal economic benefit and jth mine is represented by the grey correlation coefficient ξ(xij,x+):

(21)ξ(xij,x+)=minjminixijx++ρmaxjmaxixijx+xijx++ρmaxjmaxixijx+

where minjminixijx+ and maxjmaxixijx+ are the minimum and maximum differences of the two levels, respectively. ρ is the resolution coefficient, which ranges from 0 < ρ < 1.

The approximate degree of the ith indicator of the negative ideal economic benefit and jth mine is represented by the grey correlation coefficient ξ(xij,x).

(22)ξ(xij,x)=minjminixijx+ρmaxjmaxixijxxijx+ρmaxjmaxixijx

where minjminixijxand maxjmaxixijx are the minimum and maximum differences of the two levels, respectively.

Assume that the indicator weight is ωi (i = 1, 2, · · · , m), The grey correlations of the “ideal economic benefits” and “negative economic benefits” of the jth mines are

(23)γ(xj,x+)=i=1mωiξ(xij,x+)
(24)γ(xj,x)=i=1mωiξ(xij,x)

2.3.5 Construction of the benefit evaluation model of the real economy

The sum of the squares of the weights of all schemes is the largest objective function [15, 16, 17, 18, 19, 20, 21]

(25)maxF(uj)=j=1n(1uj)γ(xj,x+)2+ujγ(xj,x)2

Let the first derivative of the above formula (25) be zero, that is dF(uj)duj=0,the benefit evaluation model of the real economy is

(26)uj=γ(xj,x+)2γ(xj,x+)2+γ(xj,x)2=11+γ(xj,x)γ(xj,x+)2

The large uj value means that the project’s economic benefits are very good. Through this model, the economic benefits of post-assessment and pre-assessment of the same mine can be compared, and the economic benefits between mines of different years or different scales can also be compared.

3 Results

3.1 Basic information of the project

The project began with the signing of the contract between the Chinese and foreign contractors in 2007, the transfer of

production rights to the project in January 2017, and commercial production began in March 2017. The project operation benefit is the analysis of the historical data from 2007 to 2017.

3.2 Project operation benefit evaluation

3.2.1 Production, investment and cost

Before the contract is signed in 2007, China has built a production capacity of 300 million cubic meters of natural gas in the block. From 2007 to 2015, the Chinese self-operated gas production is 2.5 billion square meters. In January 2015, the project’s production operation rights are transferred to foreign contractors. In December 2015, the annual processing capacity of 3 billion cubic meters of natural gas processing plant is officially completed. From 2015 to 2017, the company has cumulatively produced 7.6 billion cubic meters of natural gas. The benefit evaluation algorithm of real economic based on big data analysis is used to evaluate the operational efficiency of the project. The comprehensive production and output value of the block from 2007 to 2017 can be obtained as shown in Table 4 and Figure 1.

Figure 1 Project output and output value
Figure 1

Project output and output value

Table 4

Summary of project output and output value

20072008200920102011201220132014201520162017
output / billion square0.282.983.393.222.683.614.224.6713.8330.4232.21
Production value / million1791982262151872.2311419129312346
US dollars

From 2007 to 2017, the project has invested a total of 938.23 million US dollars, including exploration investment of 285.88 million US dollars and development investment of 65.135 million US dollars. The total investment of the Chinese side is 231.32 million US dollars, and the total investment of contractors is 709.91 million US dollars. The specifics of investment costs from 2007 to 2017 are shown in Table 5 and Figure 2.

Figure 2 Project investment and cos
Figure 2

Project investment and cos

Table 5

Project investment and cost

20072008200920102011201220132014201520162017
Exploration investment / 10, 000 US dollars19961208523402591121103789---
Development investment / 10, 000 US dollars4680---49-813410105137161548212961
Operating cost / million dollars132867787662551716729689469536515894
Gas price / (Yuan / thousand square)556.5556.5556.5556.5582.8582.8613.4716.3716.3716.3736.3

3.2.2 Evaluation indicators of the project

The evaluation indicators of economic benefit include internal rate of return, net present value, accumulated cash contribution, investment recovery period, cash investment return rate and return on investment capital. The evaluation indicators of the project from 2007 to 2017 are shown in Table 6.

Table 6

Status of various evaluation indicators for the project from 2007 to 2017

evaluation indicators2007 year – 2017 year
Gas price / (Yuan / thousand square)628.38
Production / billion square102.41
Total investment / 10, 000 US dollars93824.15
Total cost / million dollars19362.89
Total unit cost / 10, 000 USD191.92
projectCNForeign
Pre-taxPost-taxPre-taxPost-taxPre-taxPost-tax
Internal Rate of Return%−12.1-36.2-34.4-
Net present value / 10, 000 USD−25.48−29.198.627.24−17.67−19.97
Cumulative cash contribution / 10, 000 USD−24.17−35.7526.7122.48−32.48−39.85
Payback period / month1212551213
Cash return on investment%−26.3−38.2----
Return on investment capital%16.14.2----

4 Discussion

After the contract is signed in 2007, after the evaluation period and development period, 2017 officially enters the commercial production period, and the commercial period is 20 years, to 2037. In the economic benefit evaluation analysis of the whole life cycle of the project, the data historical data from 2007 to 2017 and the data from 2017 to 2037 are adjusted based on the overall development plan data. The following analysis results are based on the natural gas price of 900 Yuan / thousand in the future.

4.1 Evaluation indicators of the project in the whole life cycle

From 2017 to 2037, the project produced a total of 65.66 billion square meters of natural gas. Among them, the stable production period from 2017 to 2027 is expected to be stable for 10 years, and the annual production of stable production will be 3.6 billion cubic meters of natural gas. The period from 2027 to 2037 is the period of reduced production, and the rate of decline in production during the period of production reduction is 6% per year, as shown in Table 7.

Table 7

Production estimate in life cycle

20172018201920202021202220232024202520262027
Production value / million US dollars1432355353535353535353
Production / billion square1313.73130.33432.15235.95235.95235.95235.95235.95235.95235.95235.9
2028202920302031203220332034203520362037
Production value / million US dollars53535047444239373533
Production / billion square5235.95235.94933.74631.74329.84128.03826.33624.73423.23221.8

From 2007 to 2037, with an estimated natural gas price of 900 Yuan / thousand square meters, the project is expected to accumulate a total investment of 149.953 million US dollars, including exploration investment of 286.88 million US dollars (Chinese 184 million US dollars), development investment 12 (2.65 million US dollars, The Chinese side is $47.32 million).

When the natural gas price is expected to be 900 Yuan/1000 in the future, the evaluation indicators of the whole life cycle of the project (2007 to 2037) are shown in Table 8.

Table 8

Financial benefit indicators for the project from 2007 to 2037

evaluation indicators2007 year – 2037 year
Gas price / (Yuan / thousand square)858.77
Production / billion square682.63
Total investment / 10, 000 US dollars144084.16
Total cost / million dollars31534.62
Total unit cost / 10, 000 USD45.29
projectCNForeign
Pre-taxPost-taxPre-tax Pre-taxPost-taxPre-tax
Internal Rate of Return%20.617.942.7 40.0321.217.9
Net present value / 10, 000 USD57.934.950.7 37.523.613.7
Cumulative cash contribution / 10, 000 USD687.6507.3430.9 318.2274.3207.5
Payback period / month12125 51213
Cash return on investment%477352- ---
Return on investment capital%477352- ---

4.2 Sensitivity analysis

In the sensitivity analysis of the project, the data for the project from 2007 to 2017 is historical data, and the data for 2017 to 2037 is the adjusted development plan data. The following analysis results are based on the following variables: The natural gas price is expected to be 900 Yuan / thousand squares in the future.

4.2.1 Analysis of the impact of natural gas price changes on economic benefit evaluation

Take the sensitivity analysis of “expected natural gas prices” as an example. In the analysis, based on 1000 Yuan / thousand squares, the change values are 1400, 1200, 1000, 800 and 600 US dollars / thousand squares, if only natural gas prices fluctuate. The results of the benefit indicators

for the period from 2007 to 2037 are shown in Table 9 (the results are all pre-tax values).

Table 9

Sensitivity analysis of natural gas prices from 2007 to 2037

evaluation indicators140012001000800600
projectInternal Rate of Return%23.722.220.518.515.9
Net present value / 10, 000 USD9596176918578763883319790
Cumulative cash contribution / 10, 000 USD936986782333627681473029318376
Payback period / month1112121213
Cash return on investment%650.3542.9435.7328.3220.9
Return on investment capital%650.4543.1435.7328.4221.1
CNInternal Rate of Return%45.244.142.741.139.5
Net present value / 10, 000 USD7407262719506803872727508
Cumulative cash contribution / 10, 000 USD632352533496430797327532224268
Payback period / month55555
Cash return on investment%-----
Return on investment capital%-----
foreignInternal Rate of Return%23.421.419.216.612.9
Net present value / 10, 000 USD31409237191671596261802
Cumulative cash contribution / 10, 000 USD323033267236215283163895112507
Payback period / month1212121314
Cash return on investment%-----
Return on investment capital%-----

As can be seen from Figures 3 and 4, during the period from 2007 to 2037, the natural gas price is 1400, 1200, 1000, 800 and 600 USD/1000, respectively, and the change in the pre-tax internal rate of return and the net present value of the project.

Figure 3 Internal rate of return of the project from 2007 to 2037 with changes in natural gas prices
Figure 3

Internal rate of return of the project from 2007 to 2037 with changes in natural gas prices

Figure 4 The net present value of the project from 2007 to 2037 with the price of natural gas
Figure 4

The net present value of the project from 2007 to 2037 with the price of natural gas

4.2.2 Comparison of the impact of multi-factor changes on benefit evaluation

The impact of changes in multiple factors (oil price, declining production, declining investment, and declining cost) on the same indicator (project internal rate of return or project net present value) is concentrated in the same scatter plot to facilitate comparison of factor sensitivity.

Through the sensitivity analysis of various factors, the analysis results are obtained. As shown in Figure 5, the “expected crude oil price” has the greatest impact on the internal rate of return of the evaluation indicators from 2007 to 2037.

Figure 5 Sensitivity analysis of pre-tax internal rate of return from 2007 to 2037
Figure 5

Sensitivity analysis of pre-tax internal rate of return from 2007 to 2037

As can be seen from Figure 6, during the period from 2007 to 2037, expected crude oil price, expected development investment and production decline rate have greater impact on the net present value of the project.

Figure 6 Sensitivity analysis of project net present value from 2007 to 2037
Figure 6

Sensitivity analysis of project net present value from 2007 to 2037

5 Conclusions

Based on the Sino-foreign petroleum cooperation projects, the evaluation and analysis theory of project economic benefits have been deeply studied. Through the discussion of the economic evaluation indicators of overseas petroleum projects, the evaluation model of economic benefits is established. According to the model, the benefit evaluation information system is developed and utilized. The system not only realizes the whole life cycle management of overseas oil and gas cooperation projects, but also conducts tracking and evaluation of project implementation and economic benefits during the implementation process, and conducts sensitivity analysis on key indicators. It provides effective decision support for managers.

The evaluation and analysis of the economic benefits of overseas oil and gas cooperation projects need to be further studied and discussed in depth and breadth:

  1. the characteristics of production management of overseas oil and gas cooperation projects need to be further studied to improve the methods and theories of economic benefit evaluation and risk analysis;

  2. in the evaluation of the economic benefits of the whole life cycle of overseas oil and gas projects, changes in inflation and exchange rates should be considered. Regression models and BP neural network models are used to predict the eligible indicators, such as oil price, investment and operating costs. This will make the assessment and analysis of the economic benefits of the project whole life cycle more accurate and scientific.

  3. The economic benefit evaluation information system still has room for improvement. Establishing a project-centered evaluation and analysis system not only makes the construction of the evaluation model more flexible, but also makes project management more convenient.

References

[1] Mayama S., Development of economic and benefit evaluation method for multi terminal hvdc, J. Instit. Electr. Eng. Jap., 2017, 137(11), 749-752.10.1541/ieejjournal.137.749Search in Google Scholar

[2] Zhang X.S., Su X., Wang Y.M., Study on evaluation method for military information systems interoperability, J. China Acad. Electr. Inform. Technol., 2016, 11(6), 649-654.Search in Google Scholar

[3] Asimakopoulou G.E., Hatziargyriou N.D., Evaluation of economic benefits of DER aggregation, IEEE Trans. Sustain. Ener., 2017, (99), 1-1.10.1109/TSTE.2017.2743349Search in Google Scholar

[4] Li J., Deng C., Li Y., et al., Comprehensive benefit evaluation system for Low-Impact development of urban storm water management measures, Water Res. Manag., 2017, 31(15), 4745-4758.10.1007/s11269-017-1776-5Search in Google Scholar

[5] Papadaskalopoulos D., Moreira R., Strbac G., et al., Quantifying the potential economic benefits of flexible industrial demand in the european power system, IEEE Trans. Industr. Inform., 2018, (99), 1-1.10.1109/TII.2018.2811734Search in Google Scholar

[6] Chen Y.,Wang L., Huang Y.Z., et al., Economic benefit evaluation model of distribution network planning based on multi-level extension evaluation method, Electr. Pow., 2016, 49(10), 159-164.Search in Google Scholar

[7] Yang B.J., Huang G.Q., Chen, H.J., et al., Comprehensive evaluation of eco-economic benefits of multi-crop rotation in paddy field systems, Chinese J. Eco-Agricult., 2016, 24(1), 112-120.Search in Google Scholar

[8] Yang W.J., Chen L.P., Research on economic benefit evaluation index system of agricultural sustainable development–taking Chongqing city as an example, Chinese J. Agricult. Res. Reg. Plan., 2016, 37(5), 1-7.Search in Google Scholar

[9] Yu T., Ding Y., Lin G.L., Economic benefit evaluation of LNG Ship through the northeast passage based on entropy weight method, J. Dalian Maritime Univ., 2017, 43(3), 50-57.Search in Google Scholar

[10] Li J., Gao J., Qiao Y., Economic benefit model of reducing valve by minimum night flow, Harbin Gongye Daxue Xuebao / J. Harbin Instit. Technol. 2017, 49(8), 55-59.Search in Google Scholar

[11] Deeba S.R., Sharma R., Saha T.K., et al., Evaluation of techni- cal and financial benefits of battery-based energy storage systems in distribution networks, LET Renew. Pow. Gener., 2016, 10(8), 1149-1160.10.1049/iet-rpg.2015.0440Search in Google Scholar

[12] Kreimeier M., Stumpf E., Benefit evaluation of hybrid electric propulsion concepts for cs-23 aircraft, Ceas Aeronautic. J., 2017, 8(4), 691-704.10.1007/s13272-017-0269-9Search in Google Scholar

[13] Zhao X., Nie T., He S.W., et al., Safety evaluation of rear oil depot based on analytic hierarchy process, Automat. Instrument., 2016, (3), 161-163.Search in Google Scholar

[14] Mayama S., Development of economic and benefit evaluation method for multi terminal hvdc, J. Instit. Electr. Eng. Japan, 2017, 137(11), 749-752.10.1541/ieejjournal.137.749Search in Google Scholar

[15] Kalkhambkar V., Kumar R., Bhakar R., Joint optimal allocation methodology for renewable distributed generation and energy storage for economic benefits, LET Renew. Pow. Gener., 2016, 10(9), 1422-1429.10.1049/iet-rpg.2016.0014Search in Google Scholar

[16] Waqas M., Nizami A.S., Aburiazaiza A.S., Barakat M.A., Rashid M.I., Ismail I.M.I., Optimizing the process of food waste compost and valorizing its applications: A case study of Saudi Arabia, J. Clean. Prod., 2018, 176, 426-438.10.1016/j.jclepro.2017.12.165Search in Google Scholar

[17] Balakrishnaraja R., Balasubramanian S., Aravindan P., Arulraj A., Selvapriya K., Geethadevi S. et al., Optimization of ethanol production using pretreated corn cob and sugarcane bagasse hydrolysate by candida parapsilosis strain Bkr1, J. Envir. Biol., 2017, 38(6), 1357-1363.10.22438/jeb/38/6/MRN-360Search in Google Scholar

[18] Maldonado M., Prada J., Senosiain M.J., On linear operators and bases on Köthe spaces, Appl.Math. Nonlin. Sci., 2016, 1(2), 617-624.10.21042/AMNS.2016.2.00047Search in Google Scholar

[19] Peng W., Lin Z., Wang L., Chang J., Gu F., Zhu X., Molecular characteristics of illicium verum extractives to activate acquired immune response, Saudi J. Biol. Sci., 2016, 23(3), 348-352.10.1016/j.sjbs.2015.10.027Search in Google Scholar PubMed PubMed Central

[20] Ahmad Y., Ali U., Bilal M., Zafar S., Zahid Z., Some new standard graphs labeled by 3-total edge product cordial labeling, Appl. Math. Nonlin. Sci., 2017, 2(1), 61-72.10.21042/AMNS.2017.1.00005Search in Google Scholar

[21] Shen Y., Zhao N., Xia M., Du X., A deep q-learning network for ship stowage planning problem, Polish Maritime Res., 2017, 24(SI), 102-109.10.1515/pomr-2017-0111Search in Google Scholar

Received: 2018-10-24
Accepted: 2018-11-14
Published Online: 2018-12-31

© 2018 Zhuo Wang and RD Rohmat Saedudin, published by De Gruyter

This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 License.

Articles in the same Issue

  1. Regular Articles
  2. A modified Fermi-Walker derivative for inextensible flows of binormal spherical image
  3. Algebraic aspects of evolution partial differential equation arising in the study of constant elasticity of variance model from financial mathematics
  4. Three-dimensional atom localization via probe absorption in a cascade four-level atomic system
  5. Determination of the energy transitions and half-lives of Rubidium nuclei
  6. Three phase heat and mass transfer model for unsaturated soil freezing process: Part 1 - model development
  7. Three phase heat and mass transfer model for unsaturated soil freezing process: Part 2 - model validation
  8. Mathematical model for thermal and entropy analysis of thermal solar collectors by using Maxwell nanofluids with slip conditions, thermal radiation and variable thermal conductivity
  9. Constructing analytic solutions on the Tricomi equation
  10. Feynman diagrams and rooted maps
  11. New type of chaos synchronization in discrete-time systems: the F-M synchronization
  12. Unsteady flow of fractional Oldroyd-B fluids through rotating annulus
  13. A note on the uniqueness of 2D elastostatic problems formulated by different types of potential functions
  14. On the conservation laws and solutions of a (2+1) dimensional KdV-mKdV equation of mathematical physics
  15. Computational methods and traveling wave solutions for the fourth-order nonlinear Ablowitz-Kaup-Newell-Segur water wave dynamical equation via two methods and its applications
  16. Siewert solutions of transcendental equations, generalized Lambert functions and physical applications
  17. Numerical solution of mixed convection flow of an MHD Jeffery fluid over an exponentially stretching sheet in the presence of thermal radiation and chemical reaction
  18. A new three-dimensional chaotic flow with one stable equilibrium: dynamical properties and complexity analysis
  19. Dynamics of a dry-rebounding drop: observations, simulations, and modeling
  20. Modeling the initial mechanical response and yielding behavior of gelled crude oil
  21. Lie symmetry analysis and conservation laws for the time fractional simplified modified Kawahara equation
  22. Solitary wave solutions of two KdV-type equations
  23. Applying industrial tomography to control and optimization flow systems
  24. Reconstructing time series into a complex network to assess the evolution dynamics of the correlations among energy prices
  25. An optimal solution for software testing case generation based on particle swarm optimization
  26. Optimal system, nonlinear self-adjointness and conservation laws for generalized shallow water wave equation
  27. Alternative methods for solving nonlinear two-point boundary value problems
  28. Global model simulation of OH production in pulsed-DC atmospheric pressure helium-air plasma jets
  29. Experimental investigation on optical vortex tweezers for microbubble trapping
  30. Joint measurements of optical parameters by irradiance scintillation and angle-of-arrival fluctuations
  31. M-polynomials and topological indices of hex-derived networks
  32. Generalized convergence analysis of the fractional order systems
  33. Porous flow characteristics of solution-gas drive in tight oil reservoirs
  34. Complementary wave solutions for the long-short wave resonance model via the extended trial equation method and the generalized Kudryashov method
  35. A Note on Koide’s Doubly Special Parametrization of Quark Masses
  36. On right-angled spherical Artin monoid of type Dn
  37. Gas flow regimes judgement in nanoporous media by digital core analysis
  38. 4 + n-dimensional water and waves on four and eleven-dimensional manifolds
  39. Stabilization and Analytic Approximate Solutions of an Optimal Control Problem
  40. On the equations of electrodynamics in a flat or curved spacetime and a possible interaction energy
  41. New prediction method for transient productivity of fractured five-spot patterns in low permeability reservoirs at high water cut stages
  42. The collinear equilibrium points in the restricted three body problem with triaxial primaries
  43. Detection of the damage threshold of fused silica components and morphologies of repaired damage sites based on the beam deflection method
  44. On the bivariate spectral quasi-linearization method for solving the two-dimensional Bratu problem
  45. Ion acoustic quasi-soliton in an electron-positron-ion plasma with superthermal electrons and positrons
  46. Analysis of projectile motion in view of conformable derivative
  47. Computing multiple ABC index and multiple GA index of some grid graphs
  48. Terahertz pulse imaging: A novel denoising method by combing the ant colony algorithm with the compressive sensing
  49. Characteristics of microscopic pore-throat structure of tight oil reservoirs in Sichuan Basin measured by rate-controlled mercury injection
  50. An activity window model for social interaction structure on Twitter
  51. Transient thermal regime trough the constitutive matrix applied to asynchronous electrical machine using the cell method
  52. On the zagreb polynomials of benzenoid systems
  53. Integrability analysis of the partial differential equation describing the classical bond-pricing model of mathematical finance
  54. The Greek parameters of a continuous arithmetic Asian option pricing model via Laplace Adomian decomposition method
  55. Quantifying the global solar radiation received in Pietermaritzburg, KwaZulu-Natal to motivate the consumption of solar technologies
  56. Sturm-Liouville difference equations having Bessel and hydrogen atom potential type
  57. Study on the response characteristics of oil wells after deep profile control in low permeability fractured reservoirs
  58. Depiction and analysis of a modified theta shaped double negative metamaterial for satellite application
  59. An attempt to geometrize electromagnetism
  60. Structure of traveling wave solutions for some nonlinear models via modified mathematical method
  61. Thermo-convective instability in a rotating ferromagnetic fluid layer with temperature modulation
  62. Construction of new solitary wave solutions of generalized Zakharov-Kuznetsov-Benjamin-Bona-Mahony and simplified modified form of Camassa-Holm equations
  63. Effect of magnetic field and heat source on Upper-convected-maxwell fluid in a porous channel
  64. Physical cues of biomaterials guide stem cell fate of differentiation: The effect of elasticity of cell culture biomaterials
  65. Shooting method analysis in wire coating withdrawing from a bath of Oldroyd 8-constant fluid with temperature dependent viscosity
  66. Rank correlation between centrality metrics in complex networks: an empirical study
  67. Special Issue: The 18th International Symposium on Electromagnetic Fields in Mechatronics, Electrical and Electronic Engineering
  68. Modeling of electric and heat processes in spot resistance welding of cross-wire steel bars
  69. Dynamic characteristics of triaxial active control magnetic bearing with asymmetric structure
  70. Design optimization of an axial-field eddy-current magnetic coupling based on magneto-thermal analytical model
  71. Thermal constitutive matrix applied to asynchronous electrical machine using the cell method
  72. Temperature distribution around thin electroconductive layers created on composite textile substrates
  73. Model of the multipolar engine with decreased cogging torque by asymmetrical distribution of the magnets
  74. Analysis of spatial thermal field in a magnetic bearing
  75. Use of the mathematical model of the ignition system to analyze the spark discharge, including the destruction of spark plug electrodes
  76. Assessment of short/long term electric field strength measurements for a pilot district
  77. Simulation study and experimental results for detection and classification of the transient capacitor inrush current using discrete wavelet transform and artificial intelligence
  78. Magnetic transmission gear finite element simulation with iron pole hysteresis
  79. Pulsed excitation terahertz tomography – multiparametric approach
  80. Low and high frequency model of three phase transformer by frequency response analysis measurement
  81. Multivariable polynomial fitting of controlled single-phase nonlinear load of input current total harmonic distortion
  82. Optimal design of a for middle-low-speed maglev trains
  83. Eddy current modeling in linear and nonlinear multifilamentary composite materials
  84. The visual attention saliency map for movie retrospection
  85. AC/DC current ratio in a current superimposition variable flux reluctance machine
  86. Influence of material uncertainties on the RLC parameters of wound inductors modeled using the finite element method
  87. Cogging force reduction in linear tubular flux switching permanent-magnet machines
  88. Modeling hysteresis curves of La(FeCoSi)13 compound near the transition point with the GRUCAD model
  89. Electro-magneto-hydrodynamic lubrication
  90. 3-D Electromagnetic field analysis of wireless power transfer system using K computer
  91. Simplified simulation technique of rotating, induction heated, calender rolls for study of temperature field control
  92. Design, fabrication and testing of electroadhesive interdigital electrodes
  93. A method to reduce partial discharges in motor windings fed by PWM inverter
  94. Reluctance network lumped mechanical & thermal models for the modeling and predesign of concentrated flux synchronous machine
  95. Special Issue Applications of Nonlinear Dynamics
  96. Study on dynamic characteristics of silo-stock-foundation interaction system under seismic load
  97. Microblog topic evolution computing based on LDA algorithm
  98. Modeling the creep damage effect on the creep crack growth behavior of rotor steel
  99. Neighborhood condition for all fractional (g, f, n′, m)-critical deleted graphs
  100. Chinese open information extraction based on DBMCSS in the field of national information resources
  101. 10.1515/phys-2018-0079
  102. CPW-fed circularly-polarized antenna array with high front-to-back ratio and low-profile
  103. Intelligent Monitoring Network Construction based on the utilization of the Internet of things (IoT) in the Metallurgical Coking Process
  104. Temperature detection technology of power equipment based on Fiber Bragg Grating
  105. Research on a rotational speed control strategy of the mandrel in a rotary steering system
  106. Dynamic load balancing algorithm for large data flow in distributed complex networks
  107. Super-structured photonic crystal fiber Bragg grating biosensor image model based on sparse matrix
  108. Fractal-based techniques for physiological time series: An updated approach
  109. Analysis of the Imaging Characteristics of the KB and KBA X-ray Microscopes at Non-coaxial Grazing Incidence
  110. Application of modified culture Kalman filter in bearing fault diagnosis
  111. Exact solutions and conservation laws for the modified equal width-Burgers equation
  112. On topological properties of block shift and hierarchical hypercube networks
  113. Elastic properties and plane acoustic velocity of cubic Sr2CaMoO6 and Sr2CaWO6 from first-principles calculations
  114. A note on the transmission feasibility problem in networks
  115. Ontology learning algorithm using weak functions
  116. Diagnosis of the power frequency vacuum arc shape based on 2D-PIV
  117. Parametric simulation analysis and reliability of escalator truss
  118. A new algorithm for real economy benefit evaluation based on big data analysis
  119. Synergy analysis of agricultural economic cycle fluctuation based on ant colony algorithm
  120. Multi-level encryption algorithm for user-related information across social networks
  121. Multi-target tracking algorithm in intelligent transportation based on wireless sensor network
  122. Fast recognition method of moving video images based on BP neural networks
  123. Compressed sensing image restoration algorithm based on improved SURF operator
  124. Design of load optimal control algorithm for smart grid based on demand response in different scenarios
  125. Face recognition method based on GA-BP neural network algorithm
  126. Optimal path selection algorithm for mobile beacons in sensor network under non-dense distribution
  127. Localization and recognition algorithm for fuzzy anomaly data in big data networks
  128. Urban road traffic flow control under incidental congestion as a function of accident duration
  129. Optimization design of reconfiguration algorithm for high voltage power distribution network based on ant colony algorithm
  130. Feasibility simulation of aseismic structure design for long-span bridges
  131. Construction of renewable energy supply chain model based on LCA
  132. The tribological properties study of carbon fabric/ epoxy composites reinforced by nano-TiO2 and MWNTs
  133. A text-Image feature mapping algorithm based on transfer learning
  134. Fast recognition algorithm for static traffic sign information
  135. Topical Issue: Clean Energy: Materials, Processes and Energy Generation
  136. An investigation of the melting process of RT-35 filled circular thermal energy storage system
  137. Numerical analysis on the dynamic response of a plate-and-frame membrane humidifier for PEMFC vehicles under various operating conditions
  138. Energy converting layers for thin-film flexible photovoltaic structures
  139. Effect of convection heat transfer on thermal energy storage unit
Downloaded on 12.2.2026 from https://www.degruyterbrill.com/document/doi/10.1515/phys-2018-0118/html
Scroll to top button