Contractor’s bid pricing strategy: a model with correlation among competitors’ prices

  • Piotr Jaśkowski und Agata Czarnigowska EMAIL logo
Veröffentlicht/Copyright: 27. Juni 2019
Veröffentlichen auch Sie bei De Gruyter Brill

Abstract

The approach used by construction companies to determine bid prices is an element of their strategy used to win jobs in competitive tenders. Such strategies build upon an analysis of the contactor’s potential and capabilities (am I able to deliver? am I eligible to participate in the tender?), and the analysis of the economic environment, including the expected behavior of competitors. The tender strategy sets out both the guidelines and the procedure in deciding whether or not to bid as well as the rules for determining the price. The price, on the one hand, should be high enough to cover expected direct and indirect costs as well as risk-adjusted profit. On the other hand, it needs to be low enough to be considered most attractive (typically: the lowest) among the prices offered by the competitors. The paper focuses on the price definition component of the bidding strategy. It provides a brief overview of the existing methods that support bidding decisions by comparing their demand for input and limitations in practical applications and presents a simulation-based method supporting the determination of the profit ratio. This probabilistic method assumes the existence of a positive correlation between the prices offered by the competitors. Its application is illustrated by means of a numerical example. The outcomes of the simulation prompt the amount of the profit margin that maximizes the expected value of the contractor’s profit.

1 Introduction

The procurement of construction works is expected to ensure that competitive bids are obtained and that the one that best meets the investor’s requirements is selected from among them. Bids may be evaluated according to a variety criteria, but the key one is typically the total price.

The low bid (LB) model treats the bid with the lowest price as the most beneficial to the client. This approach is believed to have its merits especially in the case of works procured in the traditional design-bid-build way, where the contractor is expected to deliver works defined by precise drawings and prescriptive specifications. If the client wishes to enforce completion time and conditions of payment, the circumstances leave little space for differentiating the bids according to criteria other than the price. Besides, clients from the public sector tend to use LB for momentary benefits of transparency, as selection based solely on the measurable criterion of price is unequivocal. However, the practice of the lowest price tendering is observed to result in the low quality of work, claims, disputes, and time overruns, especially in the times of economic down-turn when the orders are scarce [1]. It is also reported to promote bid rigging [2, 3]. Thus, the clients’ practice of “buying cheap” necessitates introducing strict controls to mitigate risks (e.g. to eliminate unreasonably low bids). It also results in increased cost, as concisely summarized by Constructing Excellence [4].

The average bid method and its variations, where the winner is determined by comparing the submitted bids to their average, was believed to be the answer to the key deficiency of LB, so the risk of selecting a bid of an unrealistically low price due to either underestimated cost or the bidder’s anticipation to win more money through claims and disputes [5]. This approach does not compromise the ease of use of a single criterion-based selection and, at least in theory, works well, though does not automatically exclude collusion [1, 6].

The best value or most economically advantageous tender model relies upon the optimum combination of the whole-life cost and quality to meet the user’s requirements. It enables the client to take account of criteria that reflect qualitative, technical, and environmental aspects of the bid as well as the price. Nevertheless, it involves much more effort of the client in selecting the set of criteria and their relative importance to reach the desired effect [3, 7, 8, 9].

Regardless of the procurement strategy adopted by the clients, the price for the construction works belongs to the most important criteria of bid assessment. Current public procurement regulations in Poland (as for 2019) may serve as an example. In 2014 and 2016, following EU directives, Polish regulations switched from the lowest price to multicriteria bid selection. The price stays an obligatory criterion (it may be replaced by the whole life cost if justified by circumstances), but it can be used as a sole criterion or as a dominating criterion (with a weight greater than 60%) if specifications precisely define quality standards. Other criteria are to be related to the characteristics of the subject of the contract and not to the characteristics of the contractor; the latter can be verified at the preselection stage or the conditions of participation in the tendering procedure. The report on effects of changes in public procurement law [10] focuses solely on the number, the type and weights of the criteria in use, and not on the actual impact of using more bid assessment criteria on the efficiency of public spending. However, the overall picture (at least in tenders for construction works) is as follows: the lowest price is what the clients want the most. From the point of view of a bidder, it is therefore important to set the price at a level that ensures that the tender is won.

The paper investigates into models that could be used to support bidding decisions of contractors operating in local markets of specialty works who win their orders mostly through open tendering and bid against a relatively predictable set of local competitors. Contractors who operate in such market niches are, on the one hand, well informed on their competitors’ bidding practices. On the other hand, the price competition may be fierce, and the chance of reducing costs is not high: the competitors often rely on the same suppliers, draw from the same local pool of labor resources and apply the same construction methods. Therefore, the costs of such contractors become similar, and the markup becomes the key factor affecting the price and the chance of winning the job.

Construction companies inevitably strive to set the size of the markup at a level ensuring the maximum value of the expected profit in the long term. They also adjust its planned amount on an ongoing basis, according to the market situation, their current project portfolios, and attractiveness of a particular job. In the times of economic downturn, when orders become scarce, they are likely to undertake less profitable jobs and bid low to stay in the market. Since the same factors affect decisions of all competitors in the local market (as operating under similar conditions and participating in the same tender procedures), there are grounds to assume that their decisions on pricing are correlated. Therefore, while constructing a bidding decision support model intended for local market competitors, the authors attempt to account for a correlation between the competitors’ bid prices.

The remainder of the paper is structured as follows: Section 2 presents a concise literature review on mathematical models that support decisions in competitive bidding. Section 3 discusses the assumptions of the proposed simulation model and the methodology for determining the markup-related probability of winning the tender. Discussion on the impact of the scale of correlation between competitors’ bid values on the chances to win and the recommended markup is presented by means of a numerical example in Section 4. The concluding section points to directions for further research.

2 Competitive bidding models in construction

The body of literature on multifaceted aspects of auction theory is enormous. Therefore, the authors narrow down their scope to the models intended to support construction contractor in deciding on best price in single-stage sealed bids tendering, with the assumption that the price is the sum of estimated cost and the markup. The “best price” in this context is to maximize the expected monetary value of the job to the contractor [11, 12]. Hosny and Elhakeem [13] divide these models into three categories: probability theory and statistical models, multicriteria utility, and artificial intelligence, though it does not cover all techniques to capture the problem and provide a solution.

The probability theory-based models aim at defining probabilities of winning in competition. These probabilities are typically estimated on the basis of experimental distributions of the competitor’s past bidding behavior. Friedman [11] provided one of the first such models, defining the expected profit as a product of the contractor’s markup and the probability of winning under a set of simplifying assumptions. These assumptions were as follows: there exists a pattern in each competitor’s bidding defined by a particular probability density function, the competitor’s patterns are independent (thus the probability of winning in the lowest bid auction is a product of probabilities to beat each of the competitors); the competitors should be known in advance, though if the identity and number of competitors is unknown – as in real life – some more assumptions on the distribution on the number of bidders were to be made, and the “unknown” competitors’ pattern of bidding was advised to be described by averaging patterns of competitors observed in the past). A contrasting model was introduced by Gates in 1967 [14], who provided a different formula for assessing the probability of winning at a specified markup (proved later by Skitmore et al. [15] to hold only if the bidding patterns follow Weibull distribution). Carr [16] put more attention to the possible differences in the cost estimates between the tender participants – this model (rather unrealistically) assumed that the competitor’s cost estimates (and not only bid values) distributions can be estimated for all historic projects, and that the distributions of cost estimates and bid values are independent.

The above mentioned models reached much attention from other researchers and have been extensively modified. Solutions were proposed to be found either analytically or by means of simulations. For instance, King and Mercer’s [17] model was equivalent to Friedman’s but it accounted for the effect of an inaccurate cost estimate on the contractor’s expected profit. Hosny and Elhakeem’s simulation-based tool [13] allowed the user to select specific projects for eliciting bidding behaviors of competitors instead of using data on all historic projects available to better account for characteristics of the project in question. Bahman-Bijari [18] and Yuan [19, 20] provided analyses based on similar assumptions that those in Friedman’s model, but accounted for a correlation between the competitor’s bids.

As the competitors’ bidding pattern may be difficult to capture by the statistical models, many factors are likely to affect bidding decision in a particular case, and the objectives of bidding is not necessarily to maximize profits [12], some researchers propose tools that use fuzzy input to infer on the most suitable markup size, but base on a pre-defined range of the margin [e.g. 21, 22]. Models based on statistical regression and neural networks were also tried to account for more factors that characterize particular projects and are likely to affect both cost and bid values; neural networks are generally claimed to be an effective tool in the search for the optimal markup [23, 24, 25].

3 Proposed bidding model

3.1 Assumptions

The model presented in this chapter stems from Friedman’s model [11] with assumptions modified by adding correlation between the competitors’ bids.

Let us take the point of view of a bidder A0, who intends to bid against n competitors A1, A2, ..., An in a particular tendering procedure. The bid price bi of each competitor Ai is established on the basis of the sum of individually estimated costs ci and profit mi:

(1)bi=ci+mi,

The costs comprise the direct costs of works cid(materials ciM(including their buying costs), labor ciLand plant ciP), and indirect costs ciind. Let us assume that these can be calculated as a “true commercial cost” adjusted for risks of delivering the work to the client.

The profit is often expressed as a percentage of costs. In Poland it is usual to present it as a percentage of the sum of labor, plant and indirect costs, but not materials [26, 27]. Such percentage is used in market reports prepared by Polish construction price book publishers. Adhering to this convention:

(2)mi=wimciL+ciP+ciind=wimciciM

where wim – the markup percentage calculated by the contractor Ai, further referred to as markup.

Therefore, the markup can be expressed as:

(3)wim=biciMciciM1

In the considered tender, the contractor A0 naturally does not know the cost estimates ci, bid prices bi nor markups mi of their competitors. Therefore, let us treat them as random variables further referred to as Ci, Bi and Wim.

Let us assume that the distribution of each competitor’s markup Wimcan be estimated on the basis of historic records of the competitor’s bid prices noted down by the contractor A0 at each public bid opening in the past. It is thus assumed that there exists some pattern in the bidding behavior of the competitors that can be inferred from these records.

As construction prices change naturally over time, each project involves different costs, and the cost estimates of the competitors stay unknown to contractor A0, the historic markups of the competitors can only be estimated and expressed with reference to costs calculated by the contractor A0 for the respective tenders in a “standardized” form:

(4)wi,km=bi,kc0,kMc0,kc0,kM1,i=1,2,,n,k=1,2,,s,

where:

wi,km – estimated standardized markup of competitor Ai at

tender k,

bi,k – bid price offered by competitor Ai at tender k, as announced at bid opening,

c0,k – total cost of works calculated by contractor A0 to define their bid price for tender k,

c0,kM – material cost calculated by contractor A0 to define their bid price for tender k,

s – the number of historic tenders providing insight into the competitor’s bidding patterns.

The optimal markup w0m,would correspond to the highest expected value of profit:

(5)maxEV=Pwin|w0m,,nc0c0Mw0m,

where the probability of the contractor’s A0 winning the current job with the markup of w0mequals the probability of winning against all n competitors who decided to participate in the tender:

(6)Pwin|w0m,n=PW1m>womW2m>womWnm>wom

3.2 Procedure for determining the optimum markup

Once a database of estimated markups wi,kmof the competitors’ historic tenders is prepared, it can be used in the following steps:

  1. Establish bidding patterns of the competitors from the sample recorded in the database: define distribution type and parameters of the random values of their standardized markups Wim;

  2. Establish correlation coefficients among Wim.

  3. Generate (simulate) correlated random values according patterns established in 1. and 2. to serve as bidding profiles of the competitors and the basis for inference on the relationship between the markup value and the probability of winning and the expected value of profit.

  4. On the basis of the above mentioned dependencies, determine of the optimum value of the markup, corresponding to the maximum expected profit.

3.3 Correlation between the contractors’ bid prices

The correlation between random variables means interdependence or association between them. This relationship may be functional or statistical. A functional relationship is characterized by the fact that each value of one independent variable corresponds to only one unambiguously defined value of a dependent variable. A statistical relationship is the fact that specific values of one variable correspond to precisely defined average values of the other variable. Correlation does not mean that there is a cause and effect relationship between the variables in question. The co-existence of two variables may result from the influence of another variable on both of them.

A contractor’s decision on the markup size is affected by many factors: perceived risk, project complexity, type of work, current workload (affecting the desire to get a new order), an expected rate of return, location, etc. [28]. Considering that some factors are characteristic for the market and the project, they affect all competitors in a particular tender. Though the scale of this impact is subjectively assessed by each competitor, it is likely that there exists a positive correlation between markups in the same tender: if one of the bidders decides to use a higher markup as justified by the circumstances, other competitors, basing on the same input, would probably also bid higher. A similar relationship occurs in the case of the cost: the competitors are likely to resort to the same/similar methods and materials because they are at least partially enforced by the specification, and as they may have access to the same pool of subcontractors and suppliers.

There exist many measures of the strength of the relationship between random variables. The authors resorted to the most popular one, the Pearson coefficient of linear correlation, applicable to variables that are normally distributed; it assumes values between −1 (the total negative linear correlation), through 0 (no linear correlation), up to 1 (the total positive linear correlation). A number of analyses of tender results presented in the literature prompt that markupsWimmay follow a normal distribution [18, 19, 20, 29].

The Pearson coefficient of correlation between random variables X and Y is estimated on the basis of relationships discovered in a sample of observations:

ρXY=1sXsYi=1mxix¯yiy¯,

where: (xi , yi) – observed values of variables X and Y, m – the number of observed pairs, x¯,y¯ – the sample means, sX, sY – the standard deviations of observations.

The coefficient calculated on the basis of the sample is an estimator of the correlation coefficient of the population. Its reliability depends on the sample size.

In practical cases, the sample of usable tender results may occur small: even if the number of tenders was significant, not all competitors participated in each of them.

If the data are missing due to the fact that a particular competitor did not participate in a particular tender, the case-wise elimination technique should not be used as it considerably limits the sample size and, as a result, increases the estimation error and reduces the significance level of the tests. Pairwise elimination is a more efficient approach - cases are removed when there are no values for the pair of variables for correlation. An alternative approach is to substitute missing data [29]:

  • with the means of the whole sample or a subset of the sample,

  • by pattern matching,

  • by expectation-maximization algorithm.

With small samples, to enhance the reliability of Pearson coefficient estimation, the Bayesian inference may be adopted [31]; this approach was used e.g. by Yuan [19, 20] in his correlated competitive bidding model being an extension to the Friedman’s model.

Ultimately, if the input is insufficient, the correlation coefficient may be subjectively assumed. Touran [32] recommended using expert opinions of correlation between two random variables expressed in an ordinal scale (weak, moderate, strong) that are arbitrarily assigned values of Pearson coefficient of, respectively, 0.15, 0.45 and 0.8. The same approach was used by Chau [33] to assess relationships between cost of processes. Cho [34] employed the concept of concordance probability by Gokhale and Press [34] to estimating correlation coefficient between normally distributed random values of process durations; the concordance probability is a monotone increasing function of correlation coefficient whose parameters are assessed by experts according to the fraction of expected cases where a random variable Y takes values greater than its expected value, given that random variable X is greater than its expected value.

3.4 Generating correlated random variables

Two distinct approaches have been proposed to generate correlated random variables. The first approach is applicable in cases where the joint multivariate distribution of the random variables is fully specified. The other approach is applied if the joint distribution is not fully specified, but the marginal distributions and correlations between the variables are known.

A survey on methods and applications of multivariate simulation can be found in Johnson [36]. In particular, methods developed for one-dimension random variables, i.e. acceptance-rejection, composition and convolution, are applied to generating multivariate variables [37]. In the case of a multivariate normal distribution with n marginal variables Xi of a normal distribution N (μi , σi) with the meanμi, i = 1, 2, . . . , n, the standard deviation ofσi , i = 1, 2, . . . , n, and the covariance matrix of Σ=covXi,Xj=ρXiXjσXiσXj, a following transformation may be applied: Σ = CCT, where C is a Cholesky factor of Σ [37]. The covariance matrix ought to be semipositive definite, otherwise the elements of C matrix are imaginary. If Touran subjective correlation coefficients [32] are intended to be used and the covariance matrix is not positive definite, it is advised that the estimated correlation coefficients are incrementally reduced by 1% until the values of C matrix become real. A full description of Cholesky’s transformation algorithm can be found in the literature on numerical methods. The process of generating correlated normally distributed random values Xi is as follows:

  1. Generate a sample of standardized normal values Zi ~‘N(0, 1): Z=[z1, z2, ..., zn]T.

  2. On its basis, calculate Xi = [x1, x2, ..., xn]T = μ + CZ.

If the correlated random values to be generated are to be of a distribution other than normal, the NORmal-To Anything (NORTA) transformation can be applied [38, 39]. With this transformation, the samples of random values can be obtained from a partially specified distribution by transforming the elements of a sample from a multivariate standard normal distribution according to the desired marginal distribution, where the correlations of the elements of the deriving normally distributed random vector are set to generate the desired correlations in the transformed random vector.

4 Numerical example

The input for the example is purely notional, though the range of input values (distribution parameters of estimated markups) are suggested by the survey of Mielec et al. [29] conducted on a local market of external thermal insulation contractors.

A local contractor A0 competes usually against two local competitors Ai (i={1,2}). To discover patterns in their bidding, the contractor keeps records of competitor’s bid values and estimates their markups Wimrelative to the contractor’s own cost estimates. The distribution of estimated markups of Competitor 1 was found to be N(0.102;0.014), and for Competitor 2, N(0.098;0.012). Let us assume that, due to the small size of the contractor’s database and incomplete data (the competitors did not always participate in all tenders), the correlation coefficients cannot be reliably estimated.

Therefore, simulations are going to be repeated for a number of arbitrarily assumed Pearson correlation coefficient values only to assess the scale of impact of correlation on the optimum markup.

The results of simulations are shown in Figures 1 and 2 presenting, respectively, the probability of the contractor’s A0 winning versus the markup and the expected profit to cost ratio versus the markup.

Figure 1 Simulation results: probability of winning against bid markup at different levels of correlation between the competitor’s bids (Pearson correlation coefficient ρ = {0, 0.2, 0.4, 0.6, 0.8, 1.0})
Figure 1

Simulation results: probability of winning against bid markup at different levels of correlation between the competitor’s bids (Pearson correlation coefficient ρ = {0, 0.2, 0.4, 0.6, 0.8, 1.0})

Figure 2 Simulation results: the expected profit to cost ratio EVc0−c0M$\frac{{E\left( V \right)}}{{{c_0} - c_0^M}}$against bid markup at different levels of correlation between the competitor’s bids (Pearson correlation coefficient 0, 0.2, 0.4, 0.6, 0.8, 1.0)
Figure 2

Simulation results: the expected profit to cost ratio EVc0c0Magainst bid markup at different levels of correlation between the competitor’s bids (Pearson correlation coefficient 0, 0.2, 0.4, 0.6, 0.8, 1.0)

If there exist a high correlation between the competitor’s bids (ρ > 0.6) then the optimal markup level, corresponding to the highest expected profit index, is about 8%. Lower correlation shifts the maximum expected profit index to the left, and the optimum markup is prompted to be about 7.5%. The probability of winning a tender with a markup close to the optimum differs significantly according to correlation: it is clearly greater in the case that the competitors’ bids are uncorrelated. Correlation-related differences in expected profit are also noticeable. Therefore, if correlation was observed between the competitor’s bids, a contractor using the proposed method of analysis to support their bidding decision would be prompted to submit a bid with a higher markup.

Figures 3 and 4 illustrate the impact of the number of competitors on the probability ow winning and expected profits by comparing simulation results for a theoretical case of two (i={1,2]}) and three (i={1,2,3}) competitors whose bids Wimfollow normal distributions of identical parameters: N(0,102;0,014). For the sake of brevity, only two options of correlation level were considered: no correlation (ρ = 0) and ρ = 0.5 between all pairs of competitors. As expected, the probability of winning drops with a growing number of competitors. The optimal markup (corresponding to the highest expected value of profit) is prompted to be 7.5% for three other bidders, and 8% for two bidders. An important observation is that, with the greater number of competitors, there are greater differences in the probability of winning a tender with a given markup in the case of no correlation and considerable correlation between the competitors’ bids.

Figure 3 Simulation results: probability of winning against markup for different number of competitors and at different correlation level (description in the text)
Figure 3

Simulation results: probability of winning against markup for different number of competitors and at different correlation level (description in the text)

Figure 4 Simulation results: expected profit to cost ratio EVc0−c0M$\frac{{E\left( V \right)}}{{{c_0} - c_0^M}}$against markup for different number of competitors and at different correlation levels (description in the text)
Figure 4

Simulation results: expected profit to cost ratio EVc0c0Magainst markup for different number of competitors and at different correlation levels (description in the text)

5 Conclusions

The presented approach – the modified Friedman’s model with correlations – may be difficult to apply in practice if there is little historical data from past tenders. As illustrated by the example, the impact of correlation on the probability of winning a tender and the expected profit is considerable. Therefore, relying on subjective expert estimates of correlation may generate large errors and, if overestimated, significantly reduce the chances of winning a tender. Moreover, the number of competitors, which is in practice unpredictable, has a profound impact on the estimates. Actual complexity of the problem makes simple models based on a handful of input unreliable. It is thus advisable to develop methods enabling the planner to account for a variety of factors affecting the bid price, as well as their uncertainty.

References

[1] Ioannou, P.G., Leu S.-S., Average-Bid Method – Competitive Bidding Strategy, J. Constr. Eng. Manage., 1993, 119(1), 131–14710.1061/(ASCE)0733-9364(1993)119:1(131)Suche in Google Scholar

[2] OECD (Organization for Economic Cooperation and Development), Guidelines for fighting bid rigging in public procurement, 2009. Retrieved from www.oecd.org/competitionSuche in Google Scholar

[3] Ballesteros-Pérez, P., Skitmore, M., Pellicer, E., González-Cruz, M.C., Scoring rules and abnormally low bids criteria in construction tenders: a taxonomic review, Constr. Manage. Econ., 2015, 33(4), 259–278,10.1080/01446193.2015.1059951Suche in Google Scholar

[4] Constucting Excellence, The business case for lowest price tendering? 2011. Retrieved from http://constructingexcellence.org.uk.Suche in Google Scholar

[5] Ho, S. P., Liu, L. Y., Analytical model for analyzing construction claims and opportunistic bidding, J. Constr. Eng. Manage., 2004, 130(1), 94–10410.1061/(ASCE)0733-9364(2004)130:1(94)Suche in Google Scholar

[6] Chang, W.-S., Chen, B., Salmon T.C., An Investigation of the Average Bid Mechanism for Procurement Auctions, Manage. Sci., 2015, 61(6), 1237–125410.1287/mnsc.2013.1893Suche in Google Scholar

[7] Simmonds, K., Competitive bidding: deciding the best combination of non-price features, J. Oper. Res. Soc., 1968, 19(1), 5–1410.1057/jors.1968.20Suche in Google Scholar

[8] Abdelrahman, M., Zayed, T., Elyamany, A., Best-Value Model Based on Project Specific Characteristics, J. Constr. Eng. Manage., 2008, 134(3), 17910.1061/(ASCE)0733-9364(2008)134:3(179)Suche in Google Scholar

[9] Bergman, M.A. and Lundberg, S., Tender evaluation and supplier selection methods in public procurement, J. Purch. Supply Manage., 2013, 19(2), 73–8310.1016/j.pursup.2013.02.003Suche in Google Scholar

[10] Report on bid evaluation criteria - impact of changes introduced by amendments to the Public Procurement Law of 29 August 2014 and 22 June 2016 on the application of non-price bid criteria in public procurement procedures), 2017, Warszawa: Urząd Zamówień Publicznych. Retrieved from www.uzp.gov.pl/baza-wiedzy/analizy-systemowe/raporty/ (in Polish)Suche in Google Scholar

[11] Friedman, L., A competitive bidding strategy, Oper. Res., 1956, 4(1), 104-112.10.1287/opre.4.1.104Suche in Google Scholar

[12] Boughton, P.D., The competitive bidding process: Beyond probability models, Ind. Market. Manage., 1987, 16(2), 87–9410.1016/0019-8501(87)90013-7Suche in Google Scholar

[13] Hosny, O., Elhakeem, A., Simulating the winning bid: A generalized approach for optimum markup estimation, Autom. Constr., 2012, 22, 357–36710.1016/j.autcon.2011.09.014Suche in Google Scholar

[14] Crowley, L.G., Friedman and Gates – Another Look, J. Constr. Eng. Manage., 2000, 126(4), 306–312.10.1061/(ASCE)0733-9364(2000)126:4(306)Suche in Google Scholar

[15] Skitmore, R.M., Pettitt, A.N., McVinish R., Gates Bidding Model, J. Constr. Eng. Manage., 2007, 133(11), 855–863.10.1061/(ASCE)0733-9364(2007)133:11(855)Suche in Google Scholar

[16] Carr, R., General Bidding Model, ASCE J. Constr. Div., 1982, 108, (4), 639–50.10.1061/JCCEAZ.0001070Suche in Google Scholar

[17] King, M., Mercer, A., The optimum markup when bidding with uncertain costs, Eur. J. Oper. Res., 1990, 47(3), (1990) 348–36310.1016/0377-2217(90)90221-VSuche in Google Scholar

[18] Bahman-Bijari, H., A competitive bidding decision-making model considering correlation (MSc Thesis), 2010, Ontario, Canada: Ryerson University.Suche in Google Scholar

[19] Yuan, X.-X., A correlated bidding model for markup size decisions, Constr. Manage. Econ., 2011, 29(11), 1101–1119.10.1080/01446193.2011.637568Suche in Google Scholar

[20] Yuan, X.-X., Bayesian method for the correlated competitive bidding model, Constr. Manage. Econ., 2012, 30(6), 477–49110.1080/01446193.2012.666802Suche in Google Scholar

[21] Fayek, A., Competitive bidding strategy model and software system for bid preparation, J. Constr. Eng. Manage., 1998, 124(1), 1–1010.1061/(ASCE)0733-9364(1998)124:1(1)Suche in Google Scholar

[22] Plebankiewicz, E., Modelling decision-making process in bidding procedures with the use of fuzzy sets theory, Int. J. Strateg. Prop. Manage., 2014, 18(3), 307–31610.3846/1648715X.2014.943332Suche in Google Scholar

[23] Li, H., Neural network models for intelligent support of mark-up estimation, Eng. Constr. Archit. Manage., 1996, 3(1/2), 69–8110.1108/eb021023Suche in Google Scholar

[24] Liu, M., Ling, Y.Y., Modeling a contractor’s markup estimation, J. Constr. Eng. Manage, 2005, 131(4), 391–39910.1061/(ASCE)0733-9364(2005)131:4(391)Suche in Google Scholar

[25] Polat, G., Bingol, B.N., Gurgun, A.P., Yel, B., Comparison of ANN and MRA Approaches to Estimate Bid Mark-up Size in Public Construction Projects, Procedia Eng., 2016, 164, 331-33810.1016/j.proeng.2016.11.627Suche in Google Scholar

[26] Sielewicz O., Traczyk J., Powszechne standardy kosztorysowania (Common estimating standards). 2015, Warszawa: WACETOBSuche in Google Scholar

[27] Biruk, S., Jaśkowski, P., Czarnigowska, A., Modelling contractor’s bidding decision, Eng. Manage. Prod. Serv., 2017, 9(1), 64–7310.1515/emj-2017-0007Suche in Google Scholar

[28] Shash, A.A., Abdul-Hadi, N.H., Factors affecting a contractor’s mark-up size decision in Saudi Arabia, Constr. Manage. Econ., 1992, 10(5), 415–42910.1080/01446199200000039Suche in Google Scholar

[29] Mielec, A., Jaśkowski, P., Biruk, S., Ustalenie wskaznika narzutu zysku w strategii przetargowej przedsiebiorstwa budowlanego [Determining profit level: the contractor’s bidding strategy], Przegląd Budowlany, 2009, 6, 50–53Suche in Google Scholar

[30] Dempster, A.P., Laird, N.M. Rubin, D.B., Maximum likelihood from incomplete data via the EM algorithm, J. R. Stat. Soc., 1977, 39, 1–3810.1111/j.2517-6161.1977.tb01600.xSuche in Google Scholar

[31] Schisterman, E. F., Moysich, K. B., England, L. J., Rao, M., Estimation of the correlation coefficient using the Bayesian Approach and its applications for epidemiologic research. BMC Med. Res. Method., 2003, 3(1), 510.1186/1471-2288-3-5Suche in Google Scholar

[32] Touran, A., Probabilistic cost estimating with subjective correlations, J. Constr. Eng. Manage., 1993, 119(1), 58–7110.1061/(ASCE)0733-9364(1993)119:1(58)Suche in Google Scholar

[33] Chau, K., Monte Carlo simulation of construction costs using subjective data, Constr. Manage. Econ., 1995, 13(5), 369–38310.1080/01446199500000042Suche in Google Scholar

[34] Cho, S., An exploratory project expert system for eliciting correlation coefficient and sequential updating of duration estimation, Expert Syst. Appl., 2006, 30(4), 553–56010.1016/j.eswa.2005.07.024Suche in Google Scholar

[35] Gokhale, D. V., Press, S. J., Assessment of a prior distribution for the correlation coefficient in a Bivariate normal distribution, J. R. Stat. Soc., 1982, 145(2), 237–24910.2307/2981537Suche in Google Scholar

[36] Johnson, M.E., Multivariate Statistical Simulation, 1987, New York: Wiley.10.1002/9781118150740Suche in Google Scholar

[37] Gentle, J.E., Random number generation and Monte Carlo methods (2nd ed.), 2003, New York: Springer.Suche in Google Scholar

[38] Cairo, M.C., Nelson, B.L., Modeling and generating random vectors with arbitrary marginal distributions and correlation matrix, Technique Report, 1997, Department of Industrial Engineering and Management Science, Northwestern University, EvanstonSuche in Google Scholar

[39] Chen, H., Initialization for NORTA: generation of random vectors with specified marginals and correlations, INFORMS J. Comput., 2001, 13, 312–33110.1287/ijoc.13.4.312.9736Suche in Google Scholar

Received: 2019-02-11
Accepted: 2019-04-18
Published Online: 2019-06-27

© 2019 P. Jaśkowski and A. Czarnigowska, published by De Gruyter

This work is licensed under the Creative Commons Attribution 4.0 International License.

Artikel in diesem Heft

  1. Regular Article
  2. Exploring conditions and usefulness of UAVs in the BRAIN Massive Inspections Protocol
  3. A hybrid approach for solving multi-mode resource-constrained project scheduling problem in construction
  4. Identification of geodetic risk factors occurring at the construction project preparation stage
  5. Multicriteria comparative analysis of pillars strengthening of the historic building
  6. Methods of habitat reports’ evaluation
  7. Effect of material and technological factors on the properties of cement-lime mortars and mortars with plasticizing admixture
  8. Management of Innovation Ecosystems Based on Six Sigma Business Scorecard
  9. On a Stochastic Regularization Technique for Ill-Conditioned Linear Systems
  10. Dynamic safety system for collaboration of operators and industrial robots
  11. Assessment of Decentralized Electricity Production from Hybrid Renewable Energy Sources for Sustainable Energy Development in Nigeria
  12. Seasonal evaluation of surface water quality at the Tamanduá stream watershed (Aparecida de Goiânia, Goiás, Brazil) using the Water Quality Index
  13. EFQM model implementation in a Portuguese Higher Education Institution
  14. Assessment of direct and indirect effects of building developments on the environment
  15. Accelerated Aging of WPCs Based on Polypropylene and Plywood Production Residues
  16. Analysis of the Cost of a Building’s Life Cycle in a Probabilistic Approach
  17. Implementation of Web Services for Data Integration to Improve Performance in The Processing Loan Approval
  18. Rehabilitation of buildings as an alternative to sustainability in Brazilian constructions
  19. Synthesis Conditions for LPV Controller with Input Covariance Constraints
  20. Procurement management in construction: study of Czech municipalities
  21. Contractor’s bid pricing strategy: a model with correlation among competitors’ prices
  22. Control of construction projects using the Earned Value Method - case study
  23. Model supporting decisions on renovation and modernization of public utility buildings
  24. Cements with calcareous fly ash as component of low clinker eco-self compacting concrete
  25. Failure Analysis of Super Hard End Mill HSS-Co
  26. Simulation model for resource-constrained construction project
  27. Getting efficient choices in buildings by using Genetic Algorithms: Assessment & validation
  28. Analysis of renewable energy use in single-family housing
  29. Modeling of the harmonization method for executing a multi-unit construction project
  30. Effect of foam glass granules fillers modification of lime-sand products on their microstructure
  31. Volume Optimization of Solid Waste Landfill Using Voronoi Diagram Geometry
  32. Analysis of occupational accidents in the construction industry with regards to selected time parameters
  33. Bill of quantities and quantity survey of construction works of renovated buildings - case study
  34. Cooperation of the PTFE sealing ring with the steel ball of the valve subjected to durability test
  35. Analytical model assessing the effect of increased traffic flow intensities on the road administration, maintenance and lifetime
  36. Quartz bentonite sandmix in sand-lime products
  37. The Issue of a Transport Mode Choice from the Perspective of Enterprise Logistics
  38. Analysis of workplace injuries in Slovakian state forestry enterprises
  39. Research into Customer Preferences of Potential Buyers of Simple Wood-based Houses for the Purpose of Using the Target Costing
  40. Proposal of the Inventory Management Automatic Identification System in the Manufacturing Enterprise Applying the Multi-criteria Analysis Methods
  41. Hyperboloid offset surface in the architecture and construction industry
  42. Analysis of the preparatory phase of a construction investment in the area covered by revitalization
  43. The selection of sealing technologies of the subsoil and hydrotechnical structures and quality assurance
  44. Impact of high temperature drying process on beech wood containing tension wood
  45. Prediction of Strength of Remixed Concrete by Application of Orthogonal Decomposition, Neural Analysis and Regression Analysis
  46. Modelling a production process using a Sankey diagram and Computerized Relative Allocation of Facilities Technique (CRAFT)
  47. The feasibility of using a low-cost depth camera for 3D scanning in mass customization
  48. Urban Water Infrastructure Asset Management Plan: Case Study
  49. Evaluation the effect of lime on the plastic and hardened properties of cement mortar and quantified using Vipulanandan model
  50. Uplift and Settlement Prediction Model of Marine Clay Soil e Integrated with Polyurethane Foam
  51. IoT Applications in Wind Energy Conversion Systems
  52. A new method for graph stream summarization based on both the structure and concepts
  53. “Zhores” — Petaflops supercomputer for data-driven modeling, machine learning and artificial intelligence installed in Skolkovo Institute of Science and Technology
  54. Economic Disposal Quantity of Leftovers kept in storage: a Monte Carlo simulation method
  55. Computer technology of the thermal stress state and fatigue life analysis of turbine engine exhaust support frames
  56. Statistical model used to assessment the sulphate resistance of mortars with fly ashes
  57. Application of organization goal-oriented requirement engineering (OGORE) methods in erp-based company business processes
  58. Influence of Sand Size on Mechanical Properties of Fiber Reinforced Polymer Concrete
  59. Architecture For Automation System Metrics Collection, Visualization and Data Engineering – HAMK Sheet Metal Center Building Automation Case Study
  60. Optimization of shape memory alloy braces for concentrically braced steel braced frames
  61. Topical Issue Modern Manufacturing Technologies
  62. Feasibility Study of Microneedle Fabrication from a thin Nitinol Wire Using a CW Single-Mode Fiber Laser
  63. Topical Issue: Progress in area of the flow machines and devices
  64. Analysis of the influence of a stator type modification on the performance of a pump with a hole impeller
  65. Investigations of drilled and multi-piped impellers cavitation performance
  66. The novel solution of ball valve with replaceable orifice. Numerical and field tests
  67. The flow deteriorations in course of the partial load operation of the middle specific speed Francis turbine
  68. Numerical analysis of temperature distribution in a brush seal with thermo-regulating bimetal elements
  69. A new solution of the semi-metallic gasket increasing tightness level
  70. Design and analysis of the flange-bolted joint with respect to required tightness and strength
  71. Special Issue: Actual trends in logistics and industrial engineering
  72. Intelligent programming of robotic flange production by means of CAM programming
  73. Static testing evaluation of pipe conveyor belt for different tensioning forces
  74. Design of clamping structure for material flow monitor of pipe conveyors
  75. Risk Minimisation in Integrated Supply Chains
  76. Use of simulation model for measurement of MilkRun system performance
  77. A simulation model for the need for intra-plant transport operation planning by AGV
  78. Operative production planning utilising quantitative forecasting and Monte Carlo simulations
  79. Monitoring bulk material pressure on bottom of storage using DEM
  80. Calibration of Transducers and of a Coil Compression Spring Constant on the Testing Equipment Simulating the Process of a Pallet Positioning in a Rack Cell
  81. Design of evaluation tool used to improve the production process
  82. Planning of Optimal Capacity for the Middle-Sized Storage Using a Mathematical Model
  83. Experimental assessment of the static stiffness of machine parts and structures by changing the magnitude of the hysteresis as a function of loading
  84. The evaluation of the production of the shaped part using the workshop programming method on the two-spindle multi-axis CTX alpha 500 lathe
  85. Numerical Modeling of p-v-T Rheological Equation Coefficients for Polypropylene with Variable Chalk Content
  86. Current options in the life cycle assessment of additive manufacturing products
  87. Ideal mathematical model of shock compression and shock expansion
  88. Use of simulation by modelling of conveyor belt contact forces
Heruntergeladen am 2.10.2025 von https://www.degruyterbrill.com/document/doi/10.1515/eng-2019-0021/html?srsltid=AfmBOopQeL8qEgmH-Owaz_3mL0tQHR3ePw2gucQe_xOaTBTIHjUesK01
Button zum nach oben scrollen