Economic Disposal Quantity of Leftovers kept in storage: a Monte Carlo simulation method

  • R. Assis , P. Carmona Marques EMAIL logo , J. Oliveira Santos and R. Vidal
Published/Copyright: October 26, 2019
Become an author with De Gruyter Brill

Abstract

This article describes how to reach an item’s threshold, or in other words, the limit time for it to be retrieved from stock and sold for a different use, as well as the remaining foreseen period for this situation to occur. Once a minimum length, or weight, is reached, left quantities are more difficult to sell, as demand often exceeds the remaining parts or leftovers. The number of unfulfilled orders increases, as time goes by, until it becomes further cost effective to dispose the leftover and sell it for a lower price and alternative use. A Monte Carlo simulation model was built in order to consider the randomness of future transactions and quantifying consequences providing this way a simple and effective decision-making framework.

1 Introduction

In the retail trade activity, a particular situation might occur when a piece of a material in the form of a reel (e.g. electric cable, flexible tube, rope, wire, paper, or tape) or in the form of a rod or rigid tube is cut into different lengths to satisfy custom orders. Once reduced lengths become more difficult to sell, only entire pieces are acceptable by the end user, since joints are technically and/or economically unfeasible [1].

This type of subject can be better evaluated using simulation techniques. Which concerns Monte Carlo simulation there are several recent developments in literature that can be cited, e.g. articles on stochastic approach for dynamic of pricing [2, 3, 4], and papers about new approaches for random variable and process characterization [5, 6, 7].

Chen and Simchi-Levi (2004) analyzed a model of periodic review, unique product and infinite horizon, in which pricing decisions and production / inventory are simultaneously taken. The demands at different periods are randomly distributed variables that are independent of each other and their distributions depend on the price of the product. Price and order decisions are made at the beginning of each period and shortages are backlogged. The order cost also includes a fixed price and a variable cost proportional to the quantity ordered. The goal is to maximize the expected discount, or expected average, and profit over the infinite planning horizon. It has been shown that a stationary policy is optimal for both discounted and average profit models with general demand functions. In such policy, the stocking period is managed based on a classical (s, S) policy and the price is determined based on the stock position at the beginning of each period [2].

Chen, Ray and Song (2006) studied a problem of pricing and control of periodic inventory for a retailer, which faces stochastic demand prices, under very general modeling assumptions. Any unsatisfied demand is lost and any remaining inventory at the end of the finite sales horizon has a residual value. The cost component for the retailer includes exploration, scarcity, and both variable and fixed order costs. The retailer’s goal is to maximize its expected discounted profit over the sales horizon by dynamically deciding on optimal pricing and replacement policy for each period. Authors showed that, under an assumed additive demand function, at the beginning of each period, a (s, S) policy is optimal for replenishment, and the price value depends on the stock level after the replenishment decision. Their numerical study also suggested that for a sufficiently long sales horizon, optimal policy is almost stationary. In addition, the fixed order cost plays a role in authors’ modeling framework. On the other hand, the impact on profit of dynamically changing the retail price, as opposed to a single fixed price across the entire sales horizon, also increases with the fixed cost of ordering [3].

Levin, McGill and Nediak (2012) have presented a dynamic pricing model for oligopolistic firms that sell differentiated consumable products to multiple finite segments of strategic consumers who are aware that price is dynamic and can delay their purchases accordingly. This model encompasses the strategic behavior of both firms and consumers in a dynamic stochastic game in which the objective of each firm is to maximize its expected total revenues, and each consumer responds according to a consumer choice model of intensity purchasing allocation. The model provides awareness about equilibrium price dynamics under different levels of competition, asymmetry between firms and multiple market segments with variable properties. Authors have shown that strategic consumer behavior can have serious revenue impacts if companies ignore this behavior in their dynamic pricing policies. In addition, optimal balance responses to consumer strategic behavior can recover only part of the lost revenue. A key conclusion is that companies can benefit more from limiting the information available to consumers than from allowing full information and responding to strategic behavior in an ideal way [4].

Additionally, Paola and Pinnola (2012) discussed the probabilistic representation of the probability density function (PDF) or the characteristic function (CF) in terms of complex fractional moments, showing that such complex moments are related to Riesz and complementary integrals of Riesz at the origin. According to the authors, discretization leads to the conclusion that with a few fractional moments, the entire PDF or CF can be restored.

Also, Alotta, Paola and Pinnola (2017) presented an approach that characterizes normal processes of multivariate stochastic vectors, based on the evaluation of complex spectral moments. The knowledge of these moments allows to obtain the power spectral densities providing a complete characterization of the processes of multivariate stochastic vectors [6]. These quantities are the generalization of the full-order spectral moments introduced by Vanmarcke (1971) [7]. For more general pioneered work see the contributions proposed by Arrow (1970, 1974) [8, 9].

Having reviewed some literature regarding the issue, we propose the following research objective:

The construct and use of a Monte Carlo simulation model for decision-making of randomness future transactions and quantifying costs.

In other words, one intends to understand what the limit time for an item is, to be retrieved from stock and sold for a different use, as well as the remaining foreseen period for this situation to occur.

At this point, two courses of action are possible: (i) sell immediately the remaining piece for an alternative use (e.g. for scrap) at a lower price than the market one; or (ii) wait in the expectation to sell it at the market price, despite uncertain it might be.

From an economical perspective, there must be a minimum length (orweight),where the expected marginal benefit from selling to the every-day market turns to be smaller than the expected marginal benefit from selling to an alternative use [10, 11].

This so called minimum or ‘optimal economic equilibrium quantity’, can be deduced by simulating the upcoming future, and assuming the following defined condition proposed earlier by Assis and Figueira [1]:

ERM<ERA

Where, ERM is the Expected Revenue from the Market and ERA is the Expected Revenue from an Alternative use.

2 Methods and Tools

To deal with the current problem an algorithm was developed by the authors using the constant price [1, 10]. As so, one defines the following:

2.1 Opportunity for ERM sales

The economic potential / mathematical expectation of sales - or the opportunity for ERM sales - at any time t (month, week, day), as an alternative to the ERA divestment opportunity at the same time t, can be calculated by summing all expected sales (weighted with probabilities) in time interval T-t, where T is the instance at which sales probability equals 0. This result can be expressed by the following Expression [1, 10]:

(1)ERMTt=tTPt,Q¯t,vt(1+i)t

Where,

Pt – Probability of selling the existing length at the end of period t;

Qt – Expected average sales rate during each period t;

vt –Net selling price supposed to remain valid during each period t;

i – Stock holding cost;

T – Analysis ending time (after which Pt = 0).

Making note that in previous Expression (1), the sum of expected (or potential) sales is discounted, making possible to compare ERMTt and ERAt at any time t.

The stock holding cost i is equal to the sum of the opportunity cost of tied up capital with warehousing costs [1, 10].

It is assumed that the frequencies of the dispatched lengths in recent past are known and remain constant over near future, according to Figure 1.

Figure 1 Absolute and relative frequencies (probabilities) of dispatched lengths.
Figure 1

Absolute and relative frequencies (probabilities) of dispatched lengths.

In this figure, L0 represents the maximum length ever delivered for an order fulfillment. As it can be seen, the probability (or success) of a sale is maximum - equal to 1 - until the piece reaches the length L0, i.e. for LL0.

From here on, the probability decreases progressively till 0, which occurs when the length of the piece reaches Lmin.

The average sales Qt, during each period t, can assume any value according to the forecasted sales profile within a time period of analysis and may consider the existence of eventual trend, seasonality, and random as depicted in next Figure 2.

Figure 2 Evolution of expected average sales profiles within each period t over the time period of analysis.
Figure 2

Evolution of expected average sales profiles within each period t over the time period of analysis.

Being likely the net price, vt sales might suffer a major change over different periods of analysis and the current price should be adopted instead. This will not change any calculation steps but contributes to increase complexity. In order to keep the case as simple as possible, the net selling price, vt is assumed constant and equal to v. Thus, previous Expression (1) can be rewritten as follows:

(2)ERMTτ=v,tTPt,Q¯t,(1+i)t

2.2 Opportunity for ERA sales

As an alternative, disposal for scrap or any other possible solution, might occur at the end of any time period t. The economic potential or the opportunity for disposal ERAt is calculated by the next Expression [1, 10]:

(3)ERAt=s.Lt.(1+j)t

Where:

s – Unit sales price (for scrap or any other solution);

Lt – Existing length at the end of period t; j – Opportunity cost of tied up capital.

In Expression (3), the product s.Lt is discounted, being possible to compare ERMTt and ERAt at any period t. The discount rate j is, for this case, equal to the cost of capital held up, an opportunity cost.

2.3 Trade-off point

A trade-off point can be established with Expressions (2) and (3). This is graphically depicted in the following Figure 3.

Figure 3 Variation of ERMT−t vs. ERAt with remaining length or over time.
Figure 3

Variation of ERMTt vs. ERAt with remaining length or over time.

As it can be observed, the later the alienation is decided, the lower L is, as well as values for ERMTt and ERAt. While L > L0 is met, the probability of satisfying any request is 1. As soon as L < L0, the probability decreases progressively, until it reaches the value of 0 for L = Lmin, thus becoming a leftover. There is, however, a certain point where the two curves intercept, i.e., a point of economic indifference. This point corresponds to length L*, which represents an economic minimum length, and can be addressed as a point of change in the decision or economic disposal quantity. In fact:

  1. for Lt > L*, is more cost effective to keep the part, continuing the market sale as ERMTt > ERAt; and

  2. for Lt < L*, an immediate disposal becomes more cost effective as ERMTt < ERAt.

The value for L* can be deduced analytically by equalizing Expressions (2) and (3) and solving the following Equation for Lt [1],

(4)v.tTPt,Q¯t,(1+i)t=s.Lt,(1+j)t

Being manual calculations laborious, Monte-Carlo simulation method presents a valuable alternative [12, 13]. An example of application illustrates the use of the developed algorithm.

3 Results

A company trades alloy steels for the metal-mechanical industry in the form of rods, cut to different lengths. These rods, when new, have a standard length. When a rod reaches a minimum length, it becomes progressively more difficult to fulfill orders and to judge how long it should be retained before being sold for alternative use.

Let one assume a piece with 1,000 kg. This material is traded in the market at 5 €/kg, being sold immediately for an alternative use at 3 €/kg. Considering an opportunity cost of the capital to be held in stock equal to 15% and 20% as awarehouse costs, both per year, the following question arises: what is the minimal weight (to be sold) for an alternative use?

To answer this question, one needs to investigate sales history. Analyzing the sales of the last two years, it was possible to set a season component, an increasing trend component, and a random component. Then, it is also necessary to define, as a frequency, the amount of received orders and their respective size. Hence, Table 1 and 2 show an analysis of the last two months (since the rod’s cross section is constant, it is rather indifferent to use linear or mass units).

Table 1

Frequency of quantities supplied by order.*

Lower limit range (kg/order)Upper limit range (kg/order)Frequencies (%)Cumulative frequencies (%)
01555
15201015
20252035
25303570
30352595
35405100
  1. * the average value for this frequency distribution is 26.25 kg/order.

Table 2

Frequency of weekly orders.

Number of share/weeksFrequencies (%)Cumulative frequencies (%)
(average of week t) - 255
(average of week t) - 12530
(average of week t) *3060
(average of week t) + 12585
(average of week t) + 215100
  1. *closest multiple quotient: demand in week t/26.25

In order to solve this problem, a representative-simulation model was developed in MS-Excel©. In this simulation model, the time variable can progress in two ways: (1) by variable increments (for each moment of an order arrival), or (2) by fixed increments (days, weeks, etc.). In the last case, for each period, a random quantity of orders, as well as a random quantity (number of kg) for each order was simulated. The second alternative was chosen regarding simplicity.

This simulation model allowed ones to fix the difference between ERMTt and ERAt at the end of each period t and revealing at which time t* (or length L*) this difference is worthless. Denote that the parameters that characterized demand were trend, seasonality, and randomness, along with a time horizon of 300 weeks. Also, fixed data corresponded to selling price, disposal price, opportunity capital cost, storage cost, and quantity presently existing in stock.

The simulation model randomly generated, at each run, a demand profile over 300 weeks. Next Figure 4 beneath shows one of these profiles.

Figure 4 A run of the simulation model showing future orders over 300 weeks with trend, seasonality and randomness.
Figure 4

A run of the simulation model showing future orders over 300 weeks with trend, seasonality and randomness.

Subsequently data from Table 1 and 2 along with the desired number of runs were set. One should note that the number of runs depends on the desired outputs’ accuracy. A confidence level of 90% was set. After 500 runs, the simulation model provided the following statistics:

  1. Economic Disposal Quantity = 5.97 ± 0.37 kg with a sampling error of 6.2 %;

  2. Present value of ERM = 4,698 ± 1.79 € with a sampling error of 0.04%;

  3. Present value of ERA = 3,000 €; and

  4. Remaining time until L* is reached = 30 ± 1.51 weeks with a sampling error of 4.98%.

As matter of fact, for the existing quantity of 1,000 kg, the following results were found:

  1. ERM = 4,698 €, and

  2. ERA = 3,000 €.

Once ERM > ERA (or 1,000 kg > 5.97 kg) the remaining piece should be retained, as ERM is far higher than ERA. In addition, the simulation model also provided a 30 week-long estimate as time span left, until the moment for disposal arrives. Following Table 3 and 4 depict results from one of the numerous runs performed by the simulation model, i.e.:

Table 3

Simulated demand obtained in one specific run of the simulation model.

WeekSimulated demandAverage number of deliversSimulated number of delivers1st deliver2nd deliver3rd deliverTotal of delivers
(1)(2)(3)(4)(5)(6)(7)(8)
1054.372228.30421.573-49.877
1160.5012227.19421.451-48.645
1254.8212221.48633.748-55.235
1360.8462328.34633.82134.21196.378
1456.0822233.90827.623-61.531
1554.1042234.19939.981-74.180
1658.2972127.866--27.866
1752.3792121.081--21.081
1851.5312320.80915.28034.00970.098
1955.2102227.87627.592-55.469
2059.3632121.644--21.644
2157.3022227.52027.252-54.773
2257.2302321.52621.12815.38058.034
2359.5612315.48328.11627.62471.223
2450.9392327.70721.38234.54183.631
2558.022220.6430.597-1.240
2651.2072228.06234.096-62.157
2753.6552327.62227.45233.60088.673
2853.3892215.61415.391-31.006
2959.0912227.58833.809-61.396
3055.7912227.85527.000-54.855
Table 4

Snap values resulting from one of the simulator iterations

WeekInitial stockForeseen orders (kg)ERMTt in the week (€)ERMTt discounted (€)ERMTt discounted and accumulated (€)ERAt in the week (€)ERAt discounted (€)
(1)(9)(10)*(11)(12)(13)(14)(15)
10515.40649.877249.385235.4002347.1861546.2171505.212
11465.52948.645243.225228.2642111.7861396.5861355.900
12416.88455.235276.174257.6951883.5221250.6511210.957
13361.64996.378481.891447.0591625.8261084.9461047.692
14265.27161.531307.655283.7751178.767795.812766.423
15203.74074.180370.899340.142894.992611.219587.067
16129.56027.866139.330127.040554.850388.679372.319
17101.69421.081105.40695.556427.810305.081291.455
1880.61370.098350.491315.908332.254241.838230.416
1910.5140.0000.0000.00016.34631.54329.973
2010.5140.0000.0000.00016.34631.54329.892
2110.5140.0000.0000.00016.34631.54329.812
2210.5140.0000.0000.00016.34631.54329.732
2310.5140.0000.0000.00016.34631.54329.652
2410.5140.0000.0000.00016.34631.54329.573
2510.5141.2406.2015.36816.34631.54329.493
269.2740.0000.0000.00010.97827.82225.945
279.2740.0000.0000.00010.97827.82225.875
289.2740.0000.0000.00010.97827.82225.806
299.2740.0000.0000.00010.97827.82225.736
309.2740.0000.0000.00010.97827.82225.667
  1. * = column (8) of Table 3

  1. Table 3 shows the orders profile from week 10 through week 30, based on the parameters and the frequency distributions from Table 1 and 2; and

  2. Table 4 shows the level of stock and values of ERM sales and ERA disposal, verified at the end of weeks 10 to 30.

Column (3) was obtained by the ratio between column (1) / 26.25, where 26.25 is the mean value of each order delivered (see Table 1). The result was rounded to the nearest multiple. Column (4) was obtained by interpolating the frequency distribution of the weekly number of delivers represented on Table (2), by Monte-Carlo simulation, taking as mean values those in column (3). Columns (5), (6) and (7) were obtained by interpolating the frequency distribution of the delivered quantities shown in Table 1 and according to Monte-Carlo simulation. Column (8) is equal to the sum of columns (5), (6) and (7).

Comparing Table 4 to Table 3, one can notice that in weeks 10 to 30, many orders (columns (5), (6) and (7) of Table 3), cannot be satisfied due to insufficient stock. In fact, delivers are satisfied until week 19, where L* is attained. More precisely, in week 18, ERM (332.254) > ERA (230.416) and in week 19, ERM (16.346) < ERA (29.973). For this case, the economic disposal quantity is found to be approximately 10.514 kg, being reached in week 19. In the appendix of this paper a print screen of the constructed Monte Carlo model is presented.

4 Discussion and Conclusion

The used calculation algorithm provided the threshold quantity of any piece of material when it became costlier effective to sell it, for an alternative use, at a lower price. This quantity, compared with the existing balance, when ever a transaction takes place, provides a simple and effective way for decision-making, as established previously as a research objective of this paper. It is also important to notice that the described analysis can be easily implemented on a computer, automatically triggering a warning, as soon as the threshold is reached. In this case, the variables-based decision must be updated on a time basis or whenever a change in data occurs, such as the number of transactions of items in stock. Finally, and to increase the level-headedness of the present simulation model, one is in condition to access for example forecast values of QT, once the model is properly connected to a dedicated-app for past-sales and future prediction analyses.


Tel.: +351 217 515 500

Acknowledgement

This work has received funding from the European Union’s Horizon 2020 research and innovation programme under the Marie Sklodowska-Curie grant agreement 690968.

References

[1] Assis R., Figueira, M. (1994). Microinvest - Projetos de Investimento-Avaliação e Planeamento, Lisbon: IAPMEI (in Portuguese)Search in Google Scholar

[2] Chen, X., Simchi-Levi, D. (2004). Coordinating Inventory Control and Pricing Strategies with Random Demand and Fixed Ordering Cost: The Infinite Horizon Case. Math Oper Res, 29, 698-72310.1287/moor.1040.0093Search in Google Scholar

[3] Chen, Y., Ray, S., Song, Y. (2006). Optimal Pricing and Inventory Control Policy in Periodic-Review Systems with Fixed Ordering Cost and Lost Sales. Naval Res Logistics, 53, 117-13610.1002/nav.20127Search in Google Scholar

[4] Levin, Y., McGill, J., Nediak, M. (2009). Dynamic Pricing in the Presence of Strategic Consumers and Oligopolistic Competition. Manag Sci, 55, 32-4610.1287/mnsc.1080.0936Search in Google Scholar

[5] Di Paola, M., Pinnola, F. (2012). Riesz fractional integrals and complex fractional moments for the probabilistic characterization of random variables. Prob Eng Mech, 29, 149-15610.1016/j.probengmech.2011.11.003Search in Google Scholar

[6] Alotta, G., Di Paola, M., Pinnola, F. (2017). Cross-correlation and cross-power spectral density representation by complex spectral moments. Int J Non-Lin Mech, 94, 20-2710.1016/j.ijnonlinmec.2017.02.001Search in Google Scholar

[7] Vanmarcke, E. (1972). Properties of Spectral Moments with Applications to Random Vibration, J Eng Mech, 98, 425-446.10.1061/JMCEA3.0001593Search in Google Scholar

[8] Arrow, K. (1970). Essays in the theory of risk-bearing, Amsterdam: North-Holland Pub. Co.Search in Google Scholar

[9] Arrow, K., (1974). General Economic Equilibrium: Purpose, Analytic Techniques, Collective Choice. American Econ Rev, 64, 253–7210.21236/AD0757100Search in Google Scholar

[10] Sullivan, W., White, J. (1996). Capital Investment Analysis for Engineering and Management, New Jersey: Prentice HallSearch in Google Scholar

[11] Thuesen, F., (1989). Engineering Economy, Prentice-Hall International EditionsSearch in Google Scholar

[12] Law, A., Kelton, W. (1982). Simulation Modelling and Analysis, New York: McGraw-HillSearch in Google Scholar

[13] A. Pritsker, A., Alan, B. (1986). Introduction to Simulation and SLAM-II, New York: John WileySearch in Google Scholar

Appendix

Print screen of the Monte Carlo model (in Portuguese).

Received: 2019-04-15
Accepted: 2019-09-30
Published Online: 2019-10-26

© 2019 R. Assis et al., published by De Gruyter

This work is licensed under the Creative Commons Attribution 4.0 International License.

Articles in the same Issue

  1. Regular Article
  2. Exploring conditions and usefulness of UAVs in the BRAIN Massive Inspections Protocol
  3. A hybrid approach for solving multi-mode resource-constrained project scheduling problem in construction
  4. Identification of geodetic risk factors occurring at the construction project preparation stage
  5. Multicriteria comparative analysis of pillars strengthening of the historic building
  6. Methods of habitat reports’ evaluation
  7. Effect of material and technological factors on the properties of cement-lime mortars and mortars with plasticizing admixture
  8. Management of Innovation Ecosystems Based on Six Sigma Business Scorecard
  9. On a Stochastic Regularization Technique for Ill-Conditioned Linear Systems
  10. Dynamic safety system for collaboration of operators and industrial robots
  11. Assessment of Decentralized Electricity Production from Hybrid Renewable Energy Sources for Sustainable Energy Development in Nigeria
  12. Seasonal evaluation of surface water quality at the Tamanduá stream watershed (Aparecida de Goiânia, Goiás, Brazil) using the Water Quality Index
  13. EFQM model implementation in a Portuguese Higher Education Institution
  14. Assessment of direct and indirect effects of building developments on the environment
  15. Accelerated Aging of WPCs Based on Polypropylene and Plywood Production Residues
  16. Analysis of the Cost of a Building’s Life Cycle in a Probabilistic Approach
  17. Implementation of Web Services for Data Integration to Improve Performance in The Processing Loan Approval
  18. Rehabilitation of buildings as an alternative to sustainability in Brazilian constructions
  19. Synthesis Conditions for LPV Controller with Input Covariance Constraints
  20. Procurement management in construction: study of Czech municipalities
  21. Contractor’s bid pricing strategy: a model with correlation among competitors’ prices
  22. Control of construction projects using the Earned Value Method - case study
  23. Model supporting decisions on renovation and modernization of public utility buildings
  24. Cements with calcareous fly ash as component of low clinker eco-self compacting concrete
  25. Failure Analysis of Super Hard End Mill HSS-Co
  26. Simulation model for resource-constrained construction project
  27. Getting efficient choices in buildings by using Genetic Algorithms: Assessment & validation
  28. Analysis of renewable energy use in single-family housing
  29. Modeling of the harmonization method for executing a multi-unit construction project
  30. Effect of foam glass granules fillers modification of lime-sand products on their microstructure
  31. Volume Optimization of Solid Waste Landfill Using Voronoi Diagram Geometry
  32. Analysis of occupational accidents in the construction industry with regards to selected time parameters
  33. Bill of quantities and quantity survey of construction works of renovated buildings - case study
  34. Cooperation of the PTFE sealing ring with the steel ball of the valve subjected to durability test
  35. Analytical model assessing the effect of increased traffic flow intensities on the road administration, maintenance and lifetime
  36. Quartz bentonite sandmix in sand-lime products
  37. The Issue of a Transport Mode Choice from the Perspective of Enterprise Logistics
  38. Analysis of workplace injuries in Slovakian state forestry enterprises
  39. Research into Customer Preferences of Potential Buyers of Simple Wood-based Houses for the Purpose of Using the Target Costing
  40. Proposal of the Inventory Management Automatic Identification System in the Manufacturing Enterprise Applying the Multi-criteria Analysis Methods
  41. Hyperboloid offset surface in the architecture and construction industry
  42. Analysis of the preparatory phase of a construction investment in the area covered by revitalization
  43. The selection of sealing technologies of the subsoil and hydrotechnical structures and quality assurance
  44. Impact of high temperature drying process on beech wood containing tension wood
  45. Prediction of Strength of Remixed Concrete by Application of Orthogonal Decomposition, Neural Analysis and Regression Analysis
  46. Modelling a production process using a Sankey diagram and Computerized Relative Allocation of Facilities Technique (CRAFT)
  47. The feasibility of using a low-cost depth camera for 3D scanning in mass customization
  48. Urban Water Infrastructure Asset Management Plan: Case Study
  49. Evaluation the effect of lime on the plastic and hardened properties of cement mortar and quantified using Vipulanandan model
  50. Uplift and Settlement Prediction Model of Marine Clay Soil e Integrated with Polyurethane Foam
  51. IoT Applications in Wind Energy Conversion Systems
  52. A new method for graph stream summarization based on both the structure and concepts
  53. “Zhores” — Petaflops supercomputer for data-driven modeling, machine learning and artificial intelligence installed in Skolkovo Institute of Science and Technology
  54. Economic Disposal Quantity of Leftovers kept in storage: a Monte Carlo simulation method
  55. Computer technology of the thermal stress state and fatigue life analysis of turbine engine exhaust support frames
  56. Statistical model used to assessment the sulphate resistance of mortars with fly ashes
  57. Application of organization goal-oriented requirement engineering (OGORE) methods in erp-based company business processes
  58. Influence of Sand Size on Mechanical Properties of Fiber Reinforced Polymer Concrete
  59. Architecture For Automation System Metrics Collection, Visualization and Data Engineering – HAMK Sheet Metal Center Building Automation Case Study
  60. Optimization of shape memory alloy braces for concentrically braced steel braced frames
  61. Topical Issue Modern Manufacturing Technologies
  62. Feasibility Study of Microneedle Fabrication from a thin Nitinol Wire Using a CW Single-Mode Fiber Laser
  63. Topical Issue: Progress in area of the flow machines and devices
  64. Analysis of the influence of a stator type modification on the performance of a pump with a hole impeller
  65. Investigations of drilled and multi-piped impellers cavitation performance
  66. The novel solution of ball valve with replaceable orifice. Numerical and field tests
  67. The flow deteriorations in course of the partial load operation of the middle specific speed Francis turbine
  68. Numerical analysis of temperature distribution in a brush seal with thermo-regulating bimetal elements
  69. A new solution of the semi-metallic gasket increasing tightness level
  70. Design and analysis of the flange-bolted joint with respect to required tightness and strength
  71. Special Issue: Actual trends in logistics and industrial engineering
  72. Intelligent programming of robotic flange production by means of CAM programming
  73. Static testing evaluation of pipe conveyor belt for different tensioning forces
  74. Design of clamping structure for material flow monitor of pipe conveyors
  75. Risk Minimisation in Integrated Supply Chains
  76. Use of simulation model for measurement of MilkRun system performance
  77. A simulation model for the need for intra-plant transport operation planning by AGV
  78. Operative production planning utilising quantitative forecasting and Monte Carlo simulations
  79. Monitoring bulk material pressure on bottom of storage using DEM
  80. Calibration of Transducers and of a Coil Compression Spring Constant on the Testing Equipment Simulating the Process of a Pallet Positioning in a Rack Cell
  81. Design of evaluation tool used to improve the production process
  82. Planning of Optimal Capacity for the Middle-Sized Storage Using a Mathematical Model
  83. Experimental assessment of the static stiffness of machine parts and structures by changing the magnitude of the hysteresis as a function of loading
  84. The evaluation of the production of the shaped part using the workshop programming method on the two-spindle multi-axis CTX alpha 500 lathe
  85. Numerical Modeling of p-v-T Rheological Equation Coefficients for Polypropylene with Variable Chalk Content
  86. Current options in the life cycle assessment of additive manufacturing products
  87. Ideal mathematical model of shock compression and shock expansion
  88. Use of simulation by modelling of conveyor belt contact forces
Downloaded on 28.1.2026 from https://www.degruyterbrill.com/document/doi/10.1515/eng-2019-0062/html
Scroll to top button