Simulation model for resource-constrained construction project

  • Sławomir Biruk EMAIL logo and Łukasz Rzepecki
Published/Copyright: July 20, 2019
Become an author with De Gruyter Brill

Abstract

Repetition of the same processes on different objects or units of a construction project and their concurrent execution makes it necessary to use the same limited resources at the same time. Managers prefer simple heuristic priority rules to scheduling construction activities, but there is not one the best for all projects. In addition that the experience from deterministic scheduling problems and priority-rule methods cannot always be directly transferred to stochastic environment.

The paper presents the pure reactive simulation model for planning construction projects in random conditions, taking into account the availability of renewable resources. Conducting simulation tests allows for various priority rules to determine the distribution of construction project duration and evaluate the robustness of the schedule.

The paper analyzes the effectiveness of the selected priority rules in a pipe line project. In the analyzed project, the Dynamic Minimum Slack rule ensures the lowest average duration of the project in random conditions and the highest quality robustness. The analysis of the simulation results can help the construction manager to choose the procedure ensuring the timely completion of the construction project in the stochastic environment.

1 Introduction

The schedule and budget of the project can be analyzed from two separate points of view. The investor’s goal is to minimize the time and cost of the project, while the goal of the construction contractor is to look for such a scenario (resource allocation) so that the total costs incurred by him were as low as possible. The construction planning should therefore take into account the random nature of the processes’ duration and resource availability.

There are three strategies for including uncertainty in the project planning process: proactive, reactive, and stochastic scheduling. In the proactive approach, a robust schedule is created for possible execution disruptions. A common way to protect the schedule against possible disturbances is incorporating time buffers [1, 23, 4]. The reactive scheduling consists of revising the schedule in response to an emerging disruption [2, 5]. When an unexpected event occurs the baseline schedule is repaired or completely new reschedule is generated for activities planned for execution after a disruption. In stochastic project scheduling, no baseline schedule is created. Subsequent activities are added to the partial schedule previously determined based on the so-called scheduling policy, which in every decision point adds new activities taking precedence and resource constraints into consideration. The scheduling policy can use information contained in the network, information about activity planned durations, a partial schedule created for the decision point, or the activities resource usage [6].

The construction processes are subjected to many risk factors, e.g., weather, site and geological conditions, organizational problems or poor safety procedures [7], therefore, the initial schedule becomes outdated quickly and the management of the project course requires the selection of the order in which activities are started, taking into account the level of resource availability at the time of making the decision. Managers prefer simple heuristic priority rules (PRs) rather than the use of complex optimization methods that are often incomprehensible to them [8]. The resource-based policies are a direct adaptation of the PRs and the parallel schedule generation scheme in deterministic environment to stochastic resource-constrained project scheduling (SRCPS). The PRs require low computational effort and therefore, they can be used to analyze large scale projects.

The effectiveness of the PRs application in deterministic environment was analyzed by many researchers for the single or multi-project scheduling, e.g. in papers [9, 10, 11, 12, 13].

The research was aimed at comparing the effectiveness of the PRs (influence on the project completion time). For this purpose, the test sets [14] or computer generated networks were used. The generators allow to carry out the full factorial experiment due to the network complexity, lower and upper limit of the resources, and activity resource requirements, etc. [15].

The literature analysis indicates that there is not one the best PR in the scheduling resource-constrained project. It is recommended to examine different PRs, in particular when the optimal solution is not known or project duration cannot be estimated by other, more accurate methods. The effectiveness of PRs depends primarily on the project complexity, the degree of resource contention, and resource distribution [9, 12]. Different objectives of project managers and portfolio managers may cause their preference for other decision rules [9].

Kanit et al. [16] analyzed the effectiveness of three PRs: the Maximum Remaining Path Length (MRPL), Latest Finish Time (LFT), and Minimum Slack Time (MSLK) in scheduling of ten Turkish housing estate projects. PRs with high performance were selected on the basis of the literature survey. Based on the research conducted, the authors found that in six cases the MRPL priority reduced the project duration, LFT in three, and MSLK in only one project.

Biruk [17] has proposed a computer-based Renewable Resource Management System for a Construction Company (RRMSCC), which is applicable to planning and monitoring the progress of the construction project portfolio. The decision managers are assisted by dispatching rules, and not as it is in practice, on their experience and intuition.

To evaluate different rules for the allocation of limited resources in stochastic conditions, simulation tests are most often used. The simulation method allows to determine the distribution of the total project duration and, consequently, to evaluate the risk of meeting the project due date agreed with the owner.

Chen et al. [18] analyzed 12 PRs commonly used in the deterministic resource-constrained project scheduling problem (RCPSP) and five new simulation-based PRs. Analysis of the examples showed that the experience from using PRs in the RCPSP cannot always be directly transferred to the project scheduling in stochastic environment. Authors have developed guidelines for managers to choose the most appropriate rule in the RCPSP.

Wang et al. [19] carried out the full factorial experiment in order to examine the PRs for the stochastic resource-constrained multi-project scheduling problem. The data set included 420 project portfolios, each consisting of three individual projects. The portfolios were examined at randomly generated 42 unique combinations of the resource parameters. Studies may be the basis for selecting the right priority rule from both a project and portfolio managers perspective.

Yang [8] examined 13 dispatching rules for resource-constrained projects with and without well-estimated activity durations. To assess the impact of the estimation accuracy of the activity duration on the dispatching rule effectiveness, three sets of estimated activity durations were used. The examples analyzed showed that the minimum average duration of the project is generated using:Most Immediate Successors, Rank Positional Weight, Greatest Cumulative Resource Demand, and the Minimum Slack Time PRs.

Li et al. [20] developed a procedure based on common random numbers for comparison of feasible sequences obtained by the simulation method using different PRs for scheduling projects with random activities duration. The feasibility schedules meeting the precedence and the resource constraints are generated using simulation strategy based on activity scanning method. Alternatives were assessed using the average project duration.

To describe the complex dependencies between project activities, the Design Structure Matrix (DSM) was used instead of a precedent relationship [21, 22]. The use of DSM allows modeling the impact of reworks activities, learning effect, and concurrency in performing the activities. The simulation based model allows determining distribution of total project durations with complex dependencies between projects activity.

Depending on the aim of the project manager, the ranking alternatives (schedules generated using different PRs) can be created based on: average time of project completion (quality metrics) or quality robustness measures. Herroelen and Leus [2] defined quality robustness as an insensitivity of the project due date on the occurrence of disruption. Robustness measures can be derived from the simulation examination of a project. Wang et al. [19] proposed the relative deviation metric RMi based on the comparison simulation and the exact project duration:

(1)RMi=STiDTiDTi

where: STi is the mean project duration calculated by the Monte Carlo simulation method for the i PR; DTi – project duration calculated using deterministic estimates for the duration of the activities.

Sadeghi et al. [23] presented the original method of projects planning in random conditions, considering limited availability of resources named by authors as the DE-SPEL (Discrete Event Simulation with Probabilistic Event List). It allows determining the distribution of the project duration in only one simulation run. This method is similar to the network analysis in the PERT method, because it only takes into account the dates of the event on the longest path which is determined on the basis of the availability of resources. Different PRs were used in the DESPEL system.

Ghomi and Ashjari [24] presented a simulation model for the implementation of three projects connected by shared resources. The model was programmed in the GPSS (General Purpose Simulation Language). Only a random resource allocation rule was applied and the aim of the analyses was to obtain the probability density function of the project’s completion time of each of the three projects depending on the availability of resources and to evaluate a resources utilization degree.

Hu and Mohamed [25] proposed a two-step algorithm for dynamic allocation of resources while ensuring the continuity of construction processes. The authors believe that too many resources (work teams, construction machines) carrying out work on working sites can lead to a decrease in productivity and increase the risk of accidents.

Li et al. [20] presented a model with the availability of different resources. Due to the computer implementation, the precedence and resource constraints were presented in the form of an incidence matrix and resource matrix. The authors used different PRs for dispatching resources (Shortest Processing Time, Minimum Slack Time, Latest Finish Time, Greatest Resource Demand, and the Most Immediate Successors) to find the solution with the shortest average execution time. The common random numbers were used to compare the variants.

AbouRizk and Wales [26] proposed an approach combining the discrete and continuous simulation method. The first module of their model (discrete simulation) maps the course of a construction project using a network model, while the second one (continuous simulation) imitates the environmental conditions affecting the duration of activities.

The Qualitative Simulation Graphs (QSG) model proposed by Ingalls and Morrice [27] maps the PERT networks with resources in the form of an acyclic graph, which represents all acceptable schedules, regardless of the adopted strategy of resource allocation and randomness of activities duration.

2 Description of the simulation model

A construction project is modeled using the activity on node network. The activities duration can be modeled by a triangular or uniform distribution. The triangular distribution is simple and understood by practitioners – it is a good approximation of the beta distribution used in the PERT method, and differences in the risk assessment when using both distributions are insignificant [28, 29]. The uniform distribution can be used in cases where it is easy to estimate only extreme values, while it is difficult to estimate the mode of the process duration. It is also necessary to specify activity resource requirements, the limit of their availability and their weight (cost of use).

In each simulation run, the activities duration are drawn from probability distributions using the inverse transform method [30]. The activities start time are calculated in accordance with the Critical Path Method. Processes are started in the earliest dates after meeting the precedence and resource constraints. The choice of processes takes place in accordance with the parallel scheduling scheme [31]. In every decision point, which is the activity finish date, the level of resources availability resulting from the release of renewable resources by the completed process is updated. Then a list of processes that can be started is ordered in accordance with the assumed PR. After updating the partial schedule, the level of resource availability is adjusted and selection is repeated until the set of processes possible to start is empty. In the case where there are several processes possible to start and the selected PR does not decide which one should be chosen, then the process is selected based on the random rule.

In the simulation model the following PRs were incorporated:

  • Shortest Processing Time (SPT),

  • Most Immediate Successors (MIS),

  • Greatest Resource Demand (GRD) – the product of the duration and a weighted sum of the resource requirements,

  • Greatest Resource Utilization (GRU) – gives priority to that combination of activities which maximizing weighted sum of resources usage (requires the use of a 0-1 integer linear programming),

  • Minimum Slack Time (MSLK) – slack is calculated for planned activities duration (mean values of duration) based on the resource-unconstrained CPM method,

  • First Come First Served Rule (FCFS),

  • Most Delay Process (MDP) – process delay is calculated as the difference between the planned start date (calculated for the deterministic model with no resource constraints) and the current resource allocation date,

  • Dynamic Earliest Finish Time (EFTD) – for each process, the finish date is calculated as the start date determined on a partial schedule, increased by the planned duration,

  • Dynamic Minimum Slack (MSLKD) – the slack time of an unscheduled activity is based on partial schedule and planned activities duration,

  • Dynamic Latest Start Time (LSTD) – the earliest start time of an unscheduled activity depends on the finish times of the scheduled activities.

In the simulation model, the event-based approach [30] was used. Changes in the state of the system (decision points) are observed only in the dates of starting and ending of activities. Conducting of k independent simulation runs allows determining the total expected project duration on a specified confidence level (1-α) with the availability of resources and the distribution of the project duration for each PR. As a consequence, it gives the opportunity to estimate the risk of meeting the deadline set with the owner and estimate the project robustness. The PRs verified by simulation method can be a valuable hint for the project and portfolio managers. The simulation model was programmed in Java standard edition 8, using Eclipse IDE.

3 An analysis of pipe line project in stochastic environment – an example

The example analyzes the impact of PRs on piping project duration and robustness of schedules in stochastic environment. The project was divided into 8 pipeline sections between 9 manholes. The scope of works in five sections includes line excavation with timber pilling, manholes, pipe laying, and backfilling. On the other three sections, the pipeline was made with trenchless technology (Figure 1). A precedence relations among activities of the examined project is shown in Figure 2.

Figure 1 Sewage system diagram
Figure 1

Sewage system diagram

Figure 2 Activities relationships in piping project
Figure 2

Activities relationships in piping project

4 types of resource were examined: two excavators (R1), two cranes (R2), 3 working crews (R3), and one thrust boring machine (R4). The activities resource requirements are included in Table 1. For the GRU rule, the values of activities weights are equal respectively: w1 = 0.1667, w2 = 0.1667, w3 = 0.0555, w4 = 0,2222, w5 = 0.1111, w6 = 0.2778.

Table 1

Duration, type, and number of resources for individual activities

ActivityDuration [days]Resource requirements
tatbtcR1R2R3R4
Excavation59161020
Manhole79140120
Boring1317240011
Pipe lying79110120
Pipe thrusting1012170011
Backfilling57121010

The triangular activities probability distribution were assumed based on optimistic ta, pessimistic tb, and the most likely estimates tc (Table 1).

10 000 simulation runs were carried out for each priority rule, based on which the average duration of the piping project STi, the average overrun of the project due date, and the probability of meeting the project deadline were calculated. The due date which was agreed upon with the owner for 229 days. The results are shown in Table 2. The robustness of schedules generated using the different PRs was determined using the relative deviation metric (Eq. 1), in which DTi was determined using the proposed simulation model for the resource-constrained construction project, assuming deterministic activity duration with an expected value of random variables. Figure 3 presents distribution functions of project duration with all tested PRs.

Figure 3 The cumulative distribution function for the project deadline
Figure 3

The cumulative distribution function for the project deadline

Table 2

Simulation results

NoPriority ruleDTi deterministic project duration [days]STi mean of project duration [days]Probability of meeting the project deadline [%]Average exceeding the project deadline [days]RMi relative deviation metric [%]
1LSTD193.0199.2100.00.03.2
2MSLKD193.0198.7100.00.02.9
3EFTD199.0226.259.311.813.7
4FCFS196.5208.899.51.46.2
5MIS193.0200.3100.00.03.8
6MDP193.0213.091.53.910.4
7GRD197.0220.571.67.311.9
8GRU197.0222.569.79.612.9
9MSLK193.0202.599.91.54.9
10SPT200.0227.854.812.113.9

The construction manager, when choosing the scheduling policy must take into account the average time of the project implementation, the probability of meeting the project deadline, and quality robustness. If several criteria are considered at the same time, he should decide of using Multi-Criteria Decision Making Methods. In the analyzed project, the best choice is the Dynamic Minimum Slack (MSLKD) rule – this rule ensures the shortest time of implementation in deterministic conditions, the lowest average duration of the project (calculated using the Monte Carlo method) in random conditions, the highest probability of meeting the deadline date and the lowest value of the relative deviation metric. The schedule obtained using the Dynamic Latest Start Time (LSTD) rule is more sensitive to random factors than solution generating using the MSLKD rule – the RMi metric grows from 2.9 to 3.2. The solution created by the MIS rule has a relatively low RMi equal to 3.8, additionally the MIS is a deterministic rule, it does not need to be recalculated during the implementation of processes and therefore it can be preferred by a construction managers.

4 Conclusions

The construction projects are realized under risk conditions. For this reason, schedules developed for deterministic conditions are quickly becoming obsolete. Construction managers taking the corrective actions most often rely on their own experience and intuition. Scheduling optimization algorithms are incomprehensible by them, and often they do not have access to the right optimization tools. A stochastic project scheduling (purely reactive/online strategy) most accurately describes the decision situation: a construction manager is to choose the order of activities (dispatching resources) taking into account the level of resource availability at decision points (activities’ start dates), to minimize the project completion time. The indication may be the scheduling policy, which was verified by simulation method before the implementation of the project.

The paper analyzed the effectiveness of selected PRs during the implementation of the pipe line project. Based on the research, it was found that the most effective PR for the analyzed example is the MSLKD rule. Its use leads to the shortest average duration of the project and ensures the lowest value of relative deviation metric (robustness measure for schedule). The construction manager can, however, choose the MIS rule, which gives similar results. However, it is simpler to use because priorities have constant values during the implementation of the entire project (priority of activities are simply calculated only once).

Further work should be guided in two directions. The first includes the extension of the simulation model, primarily by implementing a larger number of scheduling policies, not just PRs. The simulation model should also take into account the impact of various risk factors, e.g., dynamic changes in renewable resource level caused by work absences or equipment failures, weather impact, rework, changes in project scope, or dynamic new project arrival. It is also advisable to include other types of time distribution of activities, primarily the beta-PERT distribution,which is widely used in the construction industry. The simulation analysis of the project will allow to understand the causes of delays and facilitate management of its course in uncertainty conditions.

The second direction of further research should focus on the literature survey on the use of scheduling policies in construction projects and on the study of efficiency of different PRs for real construction projects. Creating a database and categorization of construction projects based on characteristics such as: project complexity, degree of resource contention, and resource distribution can be a helpful tool for both the project and the portfolio managers in the understanding and management of uncertainty.

Acknowledgement

This work was financially supported by Ministry of Science and Higher Education in Poland. The authors gratefully acknowledges the support.

References

[1] Goldratt E., Critical Chain. The North River Press Publishing Corporation, 1997, Great Barrington, MA.Search in Google Scholar

[2] Herroelen W., Leus R., Project scheduling under uncertainty: Survey and research potentials, European Journal of Operational Research, 2005, 165(2), 289-306.10.1016/j.ejor.2004.04.002Search in Google Scholar

[3] Jaśkowski P., Biruk S., The method for improving stability of construction project schedules through buffer allocation, Technological and Economic Development of Economy, 2011, 17(3), 429-444.10.3846/20294913.2011.580587Search in Google Scholar

[4] Połoński M., Pruszyński K., Impact of baseline terms on the course of critical paths and time buffers in the modified Goldratt’s method, Archives of Civil Engineering, 2013, 59(3), 313-320.10.2478/ace-2013-0017Search in Google Scholar

[5] Chtourou H., Haouari M., A two-stage-priority-rule-based algorithm for robust resource-constrained project scheduling, Computers & Industrial Engineering, 2008, 55(1), 183-194.10.1016/j.cie.2007.11.017Search in Google Scholar

[6] Rostami S., Creemers S., Leus R., New strategies for stochastic resource-constrained project scheduling, Journal of Scheduling, 2018, 21(3), 349-365.10.1007/s10951-016-0505-xSearch in Google Scholar

[7] Tomczak M., Jaśkowski P., Application of type-2 interval fuzzy sets to contractor qualification process, KSCE Journal of Civil Engineering, 2018, 22(8), 2702-2713.10.1007/s12205-017-0431-2Search in Google Scholar

[8] Yang K. K., A comparison of dispatching rules for executing a resource-constrained project with estimated activity durations, Omega, 1998, 26(6), 729-738.10.1016/S0305-0483(98)00021-8Search in Google Scholar

[9] Browning T. R., Yassine A. A., Resource-constrained multi-project scheduling: Priority rule performance revisited, International Journal of Production Economics, 2010, 126(2), 212-228.10.1016/j.ijpe.2010.03.009Search in Google Scholar

[10] Davis E. W., Patterson J. H., A comparison of heuristic and optimum solutions in resource-constrained project scheduling, Management Science, 1975, 21(8), 944-955.10.1287/mnsc.21.8.944Search in Google Scholar

[11] Kolisch R., Efficient priority rules for the resource-constrained project scheduling problem, Journal of Operations Management, 1996, 14(3), 179-192.10.1016/0272-6963(95)00032-1Search in Google Scholar

[12] Kurtulus I., Davis E. W., Multi-project scheduling: Categorization of heuristic rules performance, Management Science, 1982, 28(2), 161-172.10.1287/mnsc.28.2.161Search in Google Scholar

[13] Ulusoy G., Özdamar L., Heuristic performance and network/resource characteristics in resource-constrained project scheduling, Journal of the Operational Research Society, 1989, 40(12), 1145-1152.10.1057/jors.1989.196Search in Google Scholar

[14] Patterson J. H., A comparison of exact approaches for solving the multiple constrained resource, project scheduling problem, Management Science, 1984, 30(7), 854-867.10.1287/mnsc.30.7.854Search in Google Scholar

[15] Kolisch R., Schwindt C., Sprecher, A., Benchmark instances for project scheduling problems, In Project Scheduling, 1999, 197-212, Springer, Boston, MA.10.1007/978-1-4615-5533-9_9Search in Google Scholar

[16] Kanit R., Gunduz M., Ozkan O., Investigating the effectiveness of certain priority rules on resource scheduling of housing estate projects. Journal of Construction Engineering and Management, 2009, 135(7), 609-613.10.1061/(ASCE)CO.1943-7862.0000021Search in Google Scholar

[17] Biruk S., A computer-based renewable resource management system for a construction company. Open Engineering, 2018, 8(1), 440-446.10.1515/eng-2018-0062Search in Google Scholar

[18] Chen Z., Demeulemeester E., Bai S., Guo Y, Efficient priority rules for the stochastic resource-constrained project scheduling problem, European Journal of Operational Research, 2018, 270(3), 957-967.10.1016/j.ejor.2018.04.025Search in Google Scholar

[19] Wang Y., He Z., Kerkhove L.P., Vanhoucke M., On the performance of priority rules for the stochastic resource constrained multi-project scheduling problem, Computers & Industrial Engineering, 2017, 114, 223-234.10.1016/j.cie.2017.10.021Search in Google Scholar

[20] Li S., Jia Y., Wang J., A discrete-event simulation approach with multiple-comparison procedure for stochastic resource-constrained project scheduling, The International Journal of Advanced Manufacturing Technology, 2012, 63(1-4), 65-76.10.1007/s00170-011-3885-2Search in Google Scholar

[21] Abdelsalam H.M., Rasmy M.H., Mohamed, H.G., A simulation-based time reduction approach for resource constrained design structure matrix, International Journal of Modeling and Optimization, 2014, 4(1), 51.10.7763/IJMO.2014.V4.346Search in Google Scholar

[22] Cho S.H., Eppinger S.D., A simulation-based process model for managing complex design projects, IEEE Transactions on Engineering Management, 2005, 52(3), 316-328.10.1109/TEM.2005.850722Search in Google Scholar

[23] Sadeghi N., Fayek A.R., Ingolfsson A., Simulation-based approach for estimating project completion time of stochastic resource–constrained project networks, Journal of Computing in Civil Engineering, 2012, 26(4), 558-560.10.1061/(ASCE)CP.1943-5487.0000165Search in Google Scholar

[24] Ghomi S.F., Ashjari B., A simulation model for multi-project resource allocation, International Journal of Project Management, 2002, 20(2), 127-130.10.1016/S0263-7863(00)00038-7Search in Google Scholar

[25] Hu D., Mohamed Y., (2013). Time-stepped, simulation-based scheduling system for large-scale industrial construction projects, In: Proceedings of the 2013 Winter Simulation Conference: Simulation: Making Decisions in a Complex World, 2013, IEEE Press, 3249-3256.10.1109/WSC.2013.6721690Search in Google Scholar

[26] AbouRizk S.M., Wales R.J., Combined discrete-event/continuous simulation for project planning, Journal of Construction Engineering and Management, 1997, 123(1), 11-20.10.1061/(ASCE)0733-9364(1997)123:1(11)Search in Google Scholar

[27] Ingalls R.G., Morrice D.J., PERT scheduling with resource constraints using qualitative simulation graphs, Project Management Journal, 2004, 35(3), 5-14.10.1177/875697280403500303Search in Google Scholar

[28] Johnson D., The triangular distribution as a proxy for the beta distribution in risk analysis, Journal of the Royal Statistical Society: Series D (The Statistician), 1997, 46(3), 387-398.10.1111/1467-9884.00091Search in Google Scholar

[29] Kotz S., Van Dorp J.R., Beyond beta: other continuous families of distributions with bounded support and applications, 2004, World Scientific.10.1142/5720Search in Google Scholar

[30] Law A.M., Kelton W.D., Simulation modeling and analysis, (2nd ed.), 1991, New York: McGraw-Hill.Search in Google Scholar

[31] Kolisch R., Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation, European Journal of Operational Research, 1996, 90(2), 320-333.10.1016/0377-2217(95)00357-6Search in Google Scholar

Received: 2019-02-04
Accepted: 2019-05-19
Published Online: 2019-07-20

© 2019 S. Biruk and Ł. Rzepecki, published by De Gruyter

This work is licensed under the Creative Commons Attribution 4.0 International License.

Articles in the same Issue

  1. Regular Article
  2. Exploring conditions and usefulness of UAVs in the BRAIN Massive Inspections Protocol
  3. A hybrid approach for solving multi-mode resource-constrained project scheduling problem in construction
  4. Identification of geodetic risk factors occurring at the construction project preparation stage
  5. Multicriteria comparative analysis of pillars strengthening of the historic building
  6. Methods of habitat reports’ evaluation
  7. Effect of material and technological factors on the properties of cement-lime mortars and mortars with plasticizing admixture
  8. Management of Innovation Ecosystems Based on Six Sigma Business Scorecard
  9. On a Stochastic Regularization Technique for Ill-Conditioned Linear Systems
  10. Dynamic safety system for collaboration of operators and industrial robots
  11. Assessment of Decentralized Electricity Production from Hybrid Renewable Energy Sources for Sustainable Energy Development in Nigeria
  12. Seasonal evaluation of surface water quality at the Tamanduá stream watershed (Aparecida de Goiânia, Goiás, Brazil) using the Water Quality Index
  13. EFQM model implementation in a Portuguese Higher Education Institution
  14. Assessment of direct and indirect effects of building developments on the environment
  15. Accelerated Aging of WPCs Based on Polypropylene and Plywood Production Residues
  16. Analysis of the Cost of a Building’s Life Cycle in a Probabilistic Approach
  17. Implementation of Web Services for Data Integration to Improve Performance in The Processing Loan Approval
  18. Rehabilitation of buildings as an alternative to sustainability in Brazilian constructions
  19. Synthesis Conditions for LPV Controller with Input Covariance Constraints
  20. Procurement management in construction: study of Czech municipalities
  21. Contractor’s bid pricing strategy: a model with correlation among competitors’ prices
  22. Control of construction projects using the Earned Value Method - case study
  23. Model supporting decisions on renovation and modernization of public utility buildings
  24. Cements with calcareous fly ash as component of low clinker eco-self compacting concrete
  25. Failure Analysis of Super Hard End Mill HSS-Co
  26. Simulation model for resource-constrained construction project
  27. Getting efficient choices in buildings by using Genetic Algorithms: Assessment & validation
  28. Analysis of renewable energy use in single-family housing
  29. Modeling of the harmonization method for executing a multi-unit construction project
  30. Effect of foam glass granules fillers modification of lime-sand products on their microstructure
  31. Volume Optimization of Solid Waste Landfill Using Voronoi Diagram Geometry
  32. Analysis of occupational accidents in the construction industry with regards to selected time parameters
  33. Bill of quantities and quantity survey of construction works of renovated buildings - case study
  34. Cooperation of the PTFE sealing ring with the steel ball of the valve subjected to durability test
  35. Analytical model assessing the effect of increased traffic flow intensities on the road administration, maintenance and lifetime
  36. Quartz bentonite sandmix in sand-lime products
  37. The Issue of a Transport Mode Choice from the Perspective of Enterprise Logistics
  38. Analysis of workplace injuries in Slovakian state forestry enterprises
  39. Research into Customer Preferences of Potential Buyers of Simple Wood-based Houses for the Purpose of Using the Target Costing
  40. Proposal of the Inventory Management Automatic Identification System in the Manufacturing Enterprise Applying the Multi-criteria Analysis Methods
  41. Hyperboloid offset surface in the architecture and construction industry
  42. Analysis of the preparatory phase of a construction investment in the area covered by revitalization
  43. The selection of sealing technologies of the subsoil and hydrotechnical structures and quality assurance
  44. Impact of high temperature drying process on beech wood containing tension wood
  45. Prediction of Strength of Remixed Concrete by Application of Orthogonal Decomposition, Neural Analysis and Regression Analysis
  46. Modelling a production process using a Sankey diagram and Computerized Relative Allocation of Facilities Technique (CRAFT)
  47. The feasibility of using a low-cost depth camera for 3D scanning in mass customization
  48. Urban Water Infrastructure Asset Management Plan: Case Study
  49. Evaluation the effect of lime on the plastic and hardened properties of cement mortar and quantified using Vipulanandan model
  50. Uplift and Settlement Prediction Model of Marine Clay Soil e Integrated with Polyurethane Foam
  51. IoT Applications in Wind Energy Conversion Systems
  52. A new method for graph stream summarization based on both the structure and concepts
  53. “Zhores” — Petaflops supercomputer for data-driven modeling, machine learning and artificial intelligence installed in Skolkovo Institute of Science and Technology
  54. Economic Disposal Quantity of Leftovers kept in storage: a Monte Carlo simulation method
  55. Computer technology of the thermal stress state and fatigue life analysis of turbine engine exhaust support frames
  56. Statistical model used to assessment the sulphate resistance of mortars with fly ashes
  57. Application of organization goal-oriented requirement engineering (OGORE) methods in erp-based company business processes
  58. Influence of Sand Size on Mechanical Properties of Fiber Reinforced Polymer Concrete
  59. Architecture For Automation System Metrics Collection, Visualization and Data Engineering – HAMK Sheet Metal Center Building Automation Case Study
  60. Optimization of shape memory alloy braces for concentrically braced steel braced frames
  61. Topical Issue Modern Manufacturing Technologies
  62. Feasibility Study of Microneedle Fabrication from a thin Nitinol Wire Using a CW Single-Mode Fiber Laser
  63. Topical Issue: Progress in area of the flow machines and devices
  64. Analysis of the influence of a stator type modification on the performance of a pump with a hole impeller
  65. Investigations of drilled and multi-piped impellers cavitation performance
  66. The novel solution of ball valve with replaceable orifice. Numerical and field tests
  67. The flow deteriorations in course of the partial load operation of the middle specific speed Francis turbine
  68. Numerical analysis of temperature distribution in a brush seal with thermo-regulating bimetal elements
  69. A new solution of the semi-metallic gasket increasing tightness level
  70. Design and analysis of the flange-bolted joint with respect to required tightness and strength
  71. Special Issue: Actual trends in logistics and industrial engineering
  72. Intelligent programming of robotic flange production by means of CAM programming
  73. Static testing evaluation of pipe conveyor belt for different tensioning forces
  74. Design of clamping structure for material flow monitor of pipe conveyors
  75. Risk Minimisation in Integrated Supply Chains
  76. Use of simulation model for measurement of MilkRun system performance
  77. A simulation model for the need for intra-plant transport operation planning by AGV
  78. Operative production planning utilising quantitative forecasting and Monte Carlo simulations
  79. Monitoring bulk material pressure on bottom of storage using DEM
  80. Calibration of Transducers and of a Coil Compression Spring Constant on the Testing Equipment Simulating the Process of a Pallet Positioning in a Rack Cell
  81. Design of evaluation tool used to improve the production process
  82. Planning of Optimal Capacity for the Middle-Sized Storage Using a Mathematical Model
  83. Experimental assessment of the static stiffness of machine parts and structures by changing the magnitude of the hysteresis as a function of loading
  84. The evaluation of the production of the shaped part using the workshop programming method on the two-spindle multi-axis CTX alpha 500 lathe
  85. Numerical Modeling of p-v-T Rheological Equation Coefficients for Polypropylene with Variable Chalk Content
  86. Current options in the life cycle assessment of additive manufacturing products
  87. Ideal mathematical model of shock compression and shock expansion
  88. Use of simulation by modelling of conveyor belt contact forces
Downloaded on 28.1.2026 from https://www.degruyterbrill.com/document/doi/10.1515/eng-2019-0037/html
Scroll to top button