Startseite Identification of geodetic risk factors occurring at the construction project preparation stage
Artikel Open Access

Identification of geodetic risk factors occurring at the construction project preparation stage

  • Magdalena Kowacka EMAIL logo , Dariusz Skorupka , Artur Duchaczek und Paweł Zagrodnik
Veröffentlicht/Copyright: 31. Januar 2019
Veröffentlichen auch Sie bei De Gruyter Brill

Abstract

The work contains information on the implementation of surveying works in the road construction process. The aim of the research was to identify geodetic risk factors occurring at the stage of preparation of a construction project, the presence of which can greatly disrupt the undertaking such as the road construction. The research was carried out on the basis of expert knowledge, documentation obtained from various road construction projects and the analysis of disturbances at the initial stage of works.

1 Introduction

This work is a continuation of studies on the identification of risk factors in the process of implementing linear construction projects. As is known, their elimination is not possible, however their identification and subsequent quantification may allow for the reduction of the impact of these factors on the entire road construction process. It also increases the ability to respond more rapidly to unforeseen events that may occur. Geodetic works are one of the elements of construction works. These works include, among others, the establishment of a horizontal and vertical geodetic control network, inventory of the existing area, development of a road project and setting out the location of the road in the area. In order to avoid mistakes, construction works should be controlled as part of surveying work during the implementation of a given project. Identification of risk factors related to the execution of construction works forces us to undertake an in-depth review of the examined phenomenon, as the correct separation of these factors enables the correct risk assessment [1, 2, 3, 4, 5, 6]. The aim of the article was to identify geodetic risk factors occurring at the stage of preparation of a construction project. The paper is a continuation and an interesting extension of the issue discussed earlier [7, 8].

2 Methods

The analysis of the provided construction documentation, literature review and interviews with experts were conducted. In addition, the data obtained from previous research was verified as a continuation of the analysis. The tests were carried out based on real cases and verified in practice.

3 Results

During the implementation of the research at the initial stage of works related to the construction of roads, 5 factors have been identified as having a significant impact on the realization of this part of the undertaking.

These include:

  1. R1 - the incorrectly adopted horizontal layout;

  2. R2 - the altitude system that was incorrectly adopted for the development of data and terrain elevation;

  3. R3 - a failure to prepare a general plan, and later its update;

  4. R4 - no GESUT information obtained from the PODGiK resource;

  5. R5 - development of a numerical terrain / project model.

Taking into consideration the received data and identified risk factors, actions were taken to indicate in the documentation the moments in which a given factor occurred and to determine the consequences of its presence. Tables 1-5 set out examples of occurrence of risk factors at the specific moment of construction works. Adopted in the tables marked “S” means the date of commencement of work.

Table 1

Separated part of the schedule in which the R1 factor occurred, Source: own elaboration.

No.DateActivity
1Sdefining the scope of works
2S+1the scheduled start of humus removal
3S+1commencement of works related to the removal of humus
4S+12staking earthworks
5S+24completion of earthworks
6S+25staking out the indirect foundation (stakes) – finding the incorrect location of the trench in relation to the indicated stakes
7S+26as a result of the analysis, a discrepancy was found between the of DWG and PDF documentation - horizontal coordinates in the stake-out sheet were inconsistent with the editable version of the foundation contour
8S+27correct staking out of earthworks
9S+28earthworks - correction of the work performed
10S+34completion of earthworks
11S+35staking out the intermediate foundation - stakes
12S+35commencement of stake works
13S+83completion of stake works
14S+84commencement of foundation works
Table 2

Separate part of the schedule in which the R2 factor occurred, Source: own elaboration.

No.DateActivity
1S+1scheduled construction of the well together with road inlets
2S+4planned completion of works on the rainwater drainage system
3Ssetting the run of rainwater drainage system with two benchmarks
4S+1commencement of works on the rainwater drainage system
5S+5completion of work on the rainwater drainage system, reporting of the inventory before covering
6S+6carrying out the inventory of the notified scope
7S+6inconsistency with design ordinates was found during the analysis of the works performed
8S+7control measurement of the work performed, it was found that the work was not fully compliant with the design
9S+7- S+13works related to the reconstruction of the scope inconsistent with the project
Table 3

Separate part of the schedule in which the R3 factor occurred, Source: own elaboration.

No.DateActivity
1S+2planned commencement of works related to staking the foundation of cement stabilized aggregate
2Ssetting out the stabilization range
3S+2commencement of stabilization works
4S+3completion of stabilization works
5S+10positive testing of the layer strength after 7 days; permit for the performance of further construction layers
6S+15transport of material to the connectors of the rainwater drainage system
7S+16PW information of the rainwater drainage system with no transversal crossings (connectors)
8S+16setting out the run of the connectors, starting work related to cutting the stabilization made in the trace of the planned drainage
9S+17- S+22implementation of dewatering continuity
10S+22inventory of rainwater drainage works; positive analysis of its execution
11S+23supplementing the layer of cement stabilized aggregate in places of transverse crossings
12S+31obtaining the correct results of the layer’s strength, permit for the execution of subsequent construction layers
Table 4

Separate part of the schedule in which the R4 factor occurred, Source: own elaboration.

No.DateActivity
1Ssetting the scope of work
2S+3scheduled commencement of work relating to the trench excavation
3S+4commencement of work relating to the trench
4S+7interruption of work, damage to an unidentified underground utilities network
5S+7inventory of a damaged sanitary network
6S+10notifying the Engineer about the location of underground utilities not included in the project documentation
7S+34receiving a collision solution for a sanitary sewage system
8S+35the analysis of the received documentation for compliance with the road construction project
9S+41staking out the designed sanitary sewage system
10S+41commencement of sewerage works
11S+47completion of works; registration for inventory
12S+47inventory of works, confirmation of compliance with project documentation
13S+49resumption of works related to road trench excavation
Table 5

Separate part of the schedule in which the R5 factor occurred, Source: own elaboration.

No.DateActivity
1Ssetting the scope of work supplementing the slope excavator control system with the correct model
2S+3scheduled commencement of works related to performing of the embankment
3S+3commencement of works related to performing of the embankment
4S+4inventory of work - control measurement of the body width, inclination of slopes, identification of the inclination slope compliance failure, required 1: 1.5
5S+34discrepancy analysis, 3D model coherence check with cross-sections of executive documentation - model construction error
6S+35performance of the correct 3D model
7S+36supplementing the slope excavator control system with the correct model
8S+38- S+39works relating to correction of the slope inclination
9S+41control measurements of works performed, confirmation of compliance with design documentation
10S+43commencement of works relating to strengthening the slope with 20cm humus layer

The R1 factor tells us about the wrongly accepted horizontal layout that was detected during the works listed in Table 1.

Referring to the data depicted in Table 1, it was found that unfortunately the initial start date S + 78 for foundation works is delayed by 6 days due to the mistakenly adopted horizontal layout in the editable version of the detailed design, which means that the designer’s drawing in the local layout is moved by 2.7 m, which consequently necessitates the correction of earthworks, and therefore also the delay in the implementation of stake works.

Table 2 presents the scope of work in which the R2 factor occurred. The scheduled completion of sewerage works on the day S + 4 enabled the implementation of works related to earthworks (embankment), the need to comply with the project caused a delay by 8 days, the work front moved to the neighboring section causing additional costs related to the moving of road construction machinery.

The incorrect performance of the part of the rainwater drainage system was caused by the erroneous installation of the benchmark. The geodetic team performing the stake out had mistakenly adopted the Kronsztadt 60 system from the topographical description instead of the Kronsztadt 86 ordinate.

The team performing the inventory adopted the correct data based on the control network established to the proper system.

The R3 risk factor, i.e. the lack of preparation of the general plan, has a very major impact on the implementation of the road construction project. The scope of works performed during the occurrence of this risk factor is presented in Table 3.

Any delay in the implementation of subsequent construction layers due to lack of coordination of work could improve the conduct of the general plan, which would be caused by a message when reporting the staking of the cement stabilized aggregate and non-performance of underground utilities.

GESUT, or Geodetic Register of Land Utilities Network, allows for the identification of its individual elements in the field. The delay in the implementation of the road trench excavation was caused by the lack of information about the existing underground utilities. The surveying services used the data only from the submitted design documentation,which resulted in a damaged sanitary sewage system located in the GESUT PODGiK database. Such damage shifted the work presented in Table 4 and affected the costs of works.

Table 5 presents works during which the R5 risk factor occurred. The delay in the implementation of the road embankment was caused by a wrongly developed 3D model being a batch file for both control systems in construction machines and measuring instruments. Lack of control of the developed model resulted in the construction of a slope with the incorrect inclination. Generation of cross sections would reveal erroneously connected points of the top of the slope with the outer edge of the ditch (the correct connection should be with the inner edge of the ditch). The error in the development of the model resulted in a longer construction time of the embankment.

4 Discussion

The effect of the analyzes carried out is a summary of the schedules of completed construction projects along with verified risk factors that may occur at the initial stage of work, as well as the consequences of their occurrence. As a result of these activities, factors that have a real impact on the duration of the work have been presented. This identification will allow for the transition to the next stage of works, i.e. their quantification.

References

[1] Ghorbani M., Sharifzadeh M., Yasrobi S., Daiyan M., Geotechnical, structural and geodetic measurements for conventional tunnelling hazards in urban areas – The case of Niayesh road tunnel project, Tunnelling and Underground Space Technology, 2012, 31, 1–810.1016/j.tust.2012.02.009Suche in Google Scholar

[2] Kuburić M., Lero M., Surveying works in road designing and construction, Journal of Applied Engineering Science (Istraživanja i projektovanja za privredu), 2011, 9, 393-400Suche in Google Scholar

[3] Leśniak A., Plebankiewicz E., Opóźnienia w robotach budowlanych, Zeszyty Naukowe Wyższej Szkoły Oficerskiej Wojsk Lądowych, 2010, 3 (157), 332 – 339Suche in Google Scholar

[4] Perera B. A. K. S., Dhanasinghe I., Rameezdeen R., Risk management in road construction: the case of Sri Lanka. International Journal of Strategic Property Management, 2009, 13 (2), 87-10210.3846/1648-715X.2009.13.87-102Suche in Google Scholar

[5] Sturk R., Olsson L., Johansson J., Risk and decision analysis for large underground projects, as applied to the Stockholm ring road tunnels. Tunnelling and Underground Space Technology, 1996, 11(2), 157-16410.1016/0886-7798(96)00019-3Suche in Google Scholar

[6] Vose D., Risk analysis: a quantitative guide, 3rd ed., John Wiley & Sons, England, 2008Suche in Google Scholar

[7] Skorupka D., Duchaczek A., Kowacka M., Determining the Hierarchy of Selected Geodetic Risk Factors for Linear Ventures, W: Proceedings of the International Conference on Numerical Analysis and Applied Mathematics 2017, Thessaloniki, Greece, 2017, 25-30 (2017)10.1063/1.5043869Suche in Google Scholar

[8] Skorupka D., Kowacka M., Identification of risk factors of development and operation of roads in the light of surveying work. Archives of Civil Engineering, 2016, 62 (2),183-19010.1515/ace-2015-0073Suche in Google Scholar

Received: 2018-05-15
Accepted: 2018-10-04
Published Online: 2019-01-31

© 2019 M. Kowacka et al., published by De Gruyter

This work is licensed under the Creative Commons Attribution 4.0 International License.

Artikel in diesem Heft

  1. Regular Article
  2. Exploring conditions and usefulness of UAVs in the BRAIN Massive Inspections Protocol
  3. A hybrid approach for solving multi-mode resource-constrained project scheduling problem in construction
  4. Identification of geodetic risk factors occurring at the construction project preparation stage
  5. Multicriteria comparative analysis of pillars strengthening of the historic building
  6. Methods of habitat reports’ evaluation
  7. Effect of material and technological factors on the properties of cement-lime mortars and mortars with plasticizing admixture
  8. Management of Innovation Ecosystems Based on Six Sigma Business Scorecard
  9. On a Stochastic Regularization Technique for Ill-Conditioned Linear Systems
  10. Dynamic safety system for collaboration of operators and industrial robots
  11. Assessment of Decentralized Electricity Production from Hybrid Renewable Energy Sources for Sustainable Energy Development in Nigeria
  12. Seasonal evaluation of surface water quality at the Tamanduá stream watershed (Aparecida de Goiânia, Goiás, Brazil) using the Water Quality Index
  13. EFQM model implementation in a Portuguese Higher Education Institution
  14. Assessment of direct and indirect effects of building developments on the environment
  15. Accelerated Aging of WPCs Based on Polypropylene and Plywood Production Residues
  16. Analysis of the Cost of a Building’s Life Cycle in a Probabilistic Approach
  17. Implementation of Web Services for Data Integration to Improve Performance in The Processing Loan Approval
  18. Rehabilitation of buildings as an alternative to sustainability in Brazilian constructions
  19. Synthesis Conditions for LPV Controller with Input Covariance Constraints
  20. Procurement management in construction: study of Czech municipalities
  21. Contractor’s bid pricing strategy: a model with correlation among competitors’ prices
  22. Control of construction projects using the Earned Value Method - case study
  23. Model supporting decisions on renovation and modernization of public utility buildings
  24. Cements with calcareous fly ash as component of low clinker eco-self compacting concrete
  25. Failure Analysis of Super Hard End Mill HSS-Co
  26. Simulation model for resource-constrained construction project
  27. Getting efficient choices in buildings by using Genetic Algorithms: Assessment & validation
  28. Analysis of renewable energy use in single-family housing
  29. Modeling of the harmonization method for executing a multi-unit construction project
  30. Effect of foam glass granules fillers modification of lime-sand products on their microstructure
  31. Volume Optimization of Solid Waste Landfill Using Voronoi Diagram Geometry
  32. Analysis of occupational accidents in the construction industry with regards to selected time parameters
  33. Bill of quantities and quantity survey of construction works of renovated buildings - case study
  34. Cooperation of the PTFE sealing ring with the steel ball of the valve subjected to durability test
  35. Analytical model assessing the effect of increased traffic flow intensities on the road administration, maintenance and lifetime
  36. Quartz bentonite sandmix in sand-lime products
  37. The Issue of a Transport Mode Choice from the Perspective of Enterprise Logistics
  38. Analysis of workplace injuries in Slovakian state forestry enterprises
  39. Research into Customer Preferences of Potential Buyers of Simple Wood-based Houses for the Purpose of Using the Target Costing
  40. Proposal of the Inventory Management Automatic Identification System in the Manufacturing Enterprise Applying the Multi-criteria Analysis Methods
  41. Hyperboloid offset surface in the architecture and construction industry
  42. Analysis of the preparatory phase of a construction investment in the area covered by revitalization
  43. The selection of sealing technologies of the subsoil and hydrotechnical structures and quality assurance
  44. Impact of high temperature drying process on beech wood containing tension wood
  45. Prediction of Strength of Remixed Concrete by Application of Orthogonal Decomposition, Neural Analysis and Regression Analysis
  46. Modelling a production process using a Sankey diagram and Computerized Relative Allocation of Facilities Technique (CRAFT)
  47. The feasibility of using a low-cost depth camera for 3D scanning in mass customization
  48. Urban Water Infrastructure Asset Management Plan: Case Study
  49. Evaluation the effect of lime on the plastic and hardened properties of cement mortar and quantified using Vipulanandan model
  50. Uplift and Settlement Prediction Model of Marine Clay Soil e Integrated with Polyurethane Foam
  51. IoT Applications in Wind Energy Conversion Systems
  52. A new method for graph stream summarization based on both the structure and concepts
  53. “Zhores” — Petaflops supercomputer for data-driven modeling, machine learning and artificial intelligence installed in Skolkovo Institute of Science and Technology
  54. Economic Disposal Quantity of Leftovers kept in storage: a Monte Carlo simulation method
  55. Computer technology of the thermal stress state and fatigue life analysis of turbine engine exhaust support frames
  56. Statistical model used to assessment the sulphate resistance of mortars with fly ashes
  57. Application of organization goal-oriented requirement engineering (OGORE) methods in erp-based company business processes
  58. Influence of Sand Size on Mechanical Properties of Fiber Reinforced Polymer Concrete
  59. Architecture For Automation System Metrics Collection, Visualization and Data Engineering – HAMK Sheet Metal Center Building Automation Case Study
  60. Optimization of shape memory alloy braces for concentrically braced steel braced frames
  61. Topical Issue Modern Manufacturing Technologies
  62. Feasibility Study of Microneedle Fabrication from a thin Nitinol Wire Using a CW Single-Mode Fiber Laser
  63. Topical Issue: Progress in area of the flow machines and devices
  64. Analysis of the influence of a stator type modification on the performance of a pump with a hole impeller
  65. Investigations of drilled and multi-piped impellers cavitation performance
  66. The novel solution of ball valve with replaceable orifice. Numerical and field tests
  67. The flow deteriorations in course of the partial load operation of the middle specific speed Francis turbine
  68. Numerical analysis of temperature distribution in a brush seal with thermo-regulating bimetal elements
  69. A new solution of the semi-metallic gasket increasing tightness level
  70. Design and analysis of the flange-bolted joint with respect to required tightness and strength
  71. Special Issue: Actual trends in logistics and industrial engineering
  72. Intelligent programming of robotic flange production by means of CAM programming
  73. Static testing evaluation of pipe conveyor belt for different tensioning forces
  74. Design of clamping structure for material flow monitor of pipe conveyors
  75. Risk Minimisation in Integrated Supply Chains
  76. Use of simulation model for measurement of MilkRun system performance
  77. A simulation model for the need for intra-plant transport operation planning by AGV
  78. Operative production planning utilising quantitative forecasting and Monte Carlo simulations
  79. Monitoring bulk material pressure on bottom of storage using DEM
  80. Calibration of Transducers and of a Coil Compression Spring Constant on the Testing Equipment Simulating the Process of a Pallet Positioning in a Rack Cell
  81. Design of evaluation tool used to improve the production process
  82. Planning of Optimal Capacity for the Middle-Sized Storage Using a Mathematical Model
  83. Experimental assessment of the static stiffness of machine parts and structures by changing the magnitude of the hysteresis as a function of loading
  84. The evaluation of the production of the shaped part using the workshop programming method on the two-spindle multi-axis CTX alpha 500 lathe
  85. Numerical Modeling of p-v-T Rheological Equation Coefficients for Polypropylene with Variable Chalk Content
  86. Current options in the life cycle assessment of additive manufacturing products
  87. Ideal mathematical model of shock compression and shock expansion
  88. Use of simulation by modelling of conveyor belt contact forces
Heruntergeladen am 9.9.2025 von https://www.degruyterbrill.com/document/doi/10.1515/eng-2019-0002/html
Button zum nach oben scrollen