Startseite Naturwissenschaften Procurement challenges analysis of Iraqi construction projects
Artikel Open Access

Procurement challenges analysis of Iraqi construction projects

  • Sadeq Abdul Hamza EMAIL logo , Sawsan Rasheed und Azhar Hussein
Veröffentlicht/Copyright: 29. April 2022

Abstract

Public procurement in Iraq plays an essential function in the development and recovery of the country's economy as well as providing the essential infrastructure for the growth of the private sector. The Coalition Provisional Authority's Government Procurement Legislation No. 87 (2004) is the final procurement law in effect in Iraq. Preparations are underway for new procurement legislation as of Oct. 2021. The objective of the paper is to determine the effectiveness of the public procurement process used in a construction project in Iraq, there is also a lack of procurement methods and policy consistency between government agencies. procurement techniques, tender documentation information, Advertising deadlines, and document management procedures, for example, vary amongst federal contracting agencies. Furthermore, there is no mandatory process for the definition and disclosure of tender evaluation criteria, providing room for subjectivity in the tender award process. This paper's major conclusion that is competitive tendering is open to everyone, tendering is not mandated as Iraq's general rule, despite the fact that it is considered best practice elsewhere. Direct invitation techniques are widely used in the construction project process tendering of Iraq and if not adequately managed, they can lead to bias, fraud, and corruption.

1 Introduction

According to government procurement is defined as a purchase of products, services, and construction firms’ Iraqi government operating via Ministries or government entities, governmental units such as Regions and Governorates, and any other entities of the Iraqi state that have the authority to spend public funds, in the Coalition Provisional Authority's Order No. 87 (2004) Public Procurement Law. Project procurement is defined as an organized approach, process, or procedure that allows clients to buy or acquire building materials [1]. Construction project procurement does have a broad reach since it requires bringing together and arranging a huge number of different individuals, corporations, and companies to plan, oversee, and build construction goods for specific customers or “customers” such as residences, commercial complexes, shopping centers, bridges, highways, and other structures. The organizational framework necessary to plan and develop building projects for a particular customer, per the end-user or client, is known as project procurement. In some ways, it's correct because the process of a customer “obtaining” a building entails bringing together such a set of people and arranging them properly in terms of their functions, duties, and interrelationships. In addition to the conventional approach, the construction industry now employs a variety of “fast-tracking” or “creative procurement” processes all over the world [2].

In terms of duties, activity Project delivery sequence, process, and procedure, as well as organizational approach, the various procurement systems differ from one another. These variances have always had an impact on the project's success. Project performance can be defined as “the level of achievement of a certain effort or undertaking” [3]. It has something to do with the project specifications declared aims and priorities [4].

The purpose of this research is to explore how different procurement procedures influence the outcomes of the project. Because there are so a variety of projects, it's difficult to keep track of them all. It's advisable to limit this research to the most common Iraq's procurement systems, for example, standard, design-build, contract Construction management, and management are two different types of management. This study is motivated by the idea that the procurement methods are chosen, the construction project procurement system is made up of these elements [5]. That has an impact on the structure of the project delivery system as shown in Figure 1.

Figure 1 The procurement and delivery mechanisms for projects are intertwined
Figure 1

The procurement and delivery mechanisms for projects are intertwined

2 Factors affecting procurement system selection

The project performance criteria were examined through [6] using the severity index method, the following factors were considered: construction cost, construction time, quality of the completed project, as well as worker health and safety, technological level, and environmental friendliness Contractor flexibility; workforce dependency; construction group/team/team quality; contractor project management; and contractor workforce capacity. According to [7,8,9,10], the criteria that were used were as follows: used to assess customer needs and expert opinions on each procurement method's advantages and disadvantages performance: Certainty (cost/price frames) and speed (throughout the stages of design and construction), as well as flexibility in accommodating changes: knowledge of how much the customer must pay at every stage of the construction phase); knowledge of how much the clients must pay at each stage of the construction phase); understanding of how much the consumer must spend at each stage of the project Complexity (customer may specify a specific subcontractor or perform a buildability analysis); performance (contractors’ reputation, aesthetics, and design confidence): Risk allocation and mitigation; accountability (program completion, pricing, product quality, design, and construction); price competitiveness (encompassing issues such as cost of maintenance, competitive bidding, and good value); and disputes and arbitration..

3 Iraq methodology of traditional procurement

According to [11], the provisions of Clause 1/Section, 14/Order of the Coalition Provisional Authority (Dissolved) No. 87 for the year 2004 issued the Instruction No 1 for 2014 Instructions on Executing Government Contract that included Contracting Methods in section three as follows:

3.1 General tender

This strategy will be implemented by issuing a global tender to all interested parties. in participating in the execution of all types of contracts, who meet the conditions for participation. The procedures, in applying this method, shall be general, fair, competitive, open, and clear, and shall take into consideration the financial ceilings approved in the Instructions on the Execution of Government Budget.

3.2 Limited tender

When commodities, consulting services, or contracts are involved, this strategy is used. to which the goods, consulting services, or contracts are subject of the tender are available with limited, as to competent, bodies for the purpose of submitting their offers according to the specifications, designs, and conditions set up by the contracting bodies. It shall be made through an announcement to all those interested in participation through submitting their offers, and who meet the conditions of participation, for a price.

3.3 General contract with the technical qualification method

This method is made through the announcement of the tender to all those who are interested in participation through submitting their technical and commercial offers, in two separate envelopes.

3.4 Tender in two phases

This method is implemented in the following two phases. The implementation of this method the pre-qualification procedure could be used before it. initially. This method is used in the contracts where it is difficult for the contracting body to set up their technical specifications or designs and in the contract of sophisticated technology and the specialized contracts of advanced scientific nature

3.5 Direct invitation

This method is implemented through serving, free of charge, a direct invitation to at least three (3) contractors, suppliers or consultants, who are known for their rationality, ability, as well as technical and financial capabilities, to carry out official body projects and contracts

3.6 Single offer (the only offer)

It is through serving invitation, free of charge, to one competent supplier, contractor, or consultant for contract execution, with the approval by the central committee on reviewing and approval of an award.

3.7 Direct contract

It is done by sending a free invitation within one body to carry out this type of contract, with the consent of the Council Ministers’ competent sectoral committee and a recommendation from the central committee on the revision and approval of importation or local contracts for the provision of non-monopolistic goods or services of a specialized nature provided the fulfillment.

3.8 Direct purchase

Direct Purchase from rational manufacturers

3.9 Committees of purchasing

This method is used for providing the government departments with services, goods, and works, as per the regulations stated in the Instructions on the Execution of Federal Budget.

3.10 Amana regulation

The contracting parties, in the event of adopting the implementation method as trust when implementing their projects financed from the current budget or from the investment budget, must take into account the financial ceiling specified for the purposes of implementing this method which does not exceed $170,000, it's similar to cost plus fixed or Force account.

3.11 Direct implementation

Establishment of centrally funded state departments: Execution, installation, maintenance, procurement, and provision of materials and equipment necessary for the implementation the project and the materials and equipment included in it until its operation, examination, and final delivery

According to [12], traditional procurement is appropriate in some situations, such as when a schedule permits for consultant design is required, sample time; and a client wishes to engage designers and contractors separately. Before building begins, price certainty is wanted; product quality is necessary, and a risk balance between both the client and the constructor must be created. systems of Procurement have become a big concern in the construction industry due to two considerations. To begin, the procurement of a construction project comprises a series of interconnected and sequential actions [1]. The procurement method is described as the organization of the complete process of project construction delivery [13]. The importance of focusing procurement strategies on optimizing all project delivery objectives, particularly time, money, and quality, was underlined. Project procurement has remained a difficulty for the design team, subcontractors, and investment businesses under these constraints such as references [14] and [15]. According to the references [16] and [17], the primary varieties of the classical procurement process are bills of definite quantities, bills of approximate amounts, drawings, and specifications. Schedule of rates, expense reimbursement, and labor only The conventional approach is a project procurement process in which the three consecutive stages of concept, bid, and construction are designated as independent activities, as the name implies.

A properly bid contract is what it's known as. This strategy allows all qualified contractors to bid on projects in a competitive, yet non-competitive, setting, much like a competitive market. The client makes the project and writes a written scope statement, stating the project's goals and requesting that the scope definition be verified by the architect [17]. The architect is in charge of establishing the scope so that clear duties can be established and scope project modifications can be tracked with the project team. The design team prepares the entire design documentation before engaging the contractor, which frequently degrades quality by failing to address buildability, buildability, and life-cycle costing [18,19,20].

4 Methodology of analysis

Several approaches were considered in order to determine the optimum technique for gathering data in order to make certain that the Benchmark Study added In the Iraqi context, value Information was gathered using sources from Iraqi ministries, particularly the Ministry of Planning, and numerous international organizations working in Iraq. To aid data collecting, we created a draft questionnaire. The draft questionnaire, titled “Procurement Challenge Analysis in Construction of Iraq” was distributed to key stakeholders and experts, as well as being translated into Arabic in order to reach a larger pool of Iraqi specialists. Using a practical sampling technique, A total of 100 (one hundred) questionnaires were distributed to the targeted professions, yielding 73 integers eligible for analysis. The surveys were separated into two parts: the first dealt with the respondents’ demographic characteristics, and the second dealt with the performance of various procurement methods used in the Iraqi construction sector. as well as Iraqi control institutions including the Inspector General (internal audit), the Supreme Audit Board (external audit), and the Integrity Commission (anti-corruption agency). On the one hand, responsibilities may overlap affecting methods of procurement.

There are nine major factors to consider when evaluating procurement methods, From the literature, fifteen factors relating to the performance of control institutions were identified, and some were added after they were established through a pilot survey. Interviewees were requested to rank the importance of these criteria on a scale of one to ten. On a 5-point Likert scale, 1 was very low, 2 was low, 3 was neutral, 4 was high, and 5 was very high, with 1 being very low, 2 being low, 3 being neutral, 4 being high, and 5 being very high. The following formula is used to calculate the average rank of a group of people:

(1) MS=(F*S)N

Where

  • MS = Score of mean

  • F = Frequency of response

  • S = The score assigned to the criteria, which ranges from 1 to 5

  • N = The overall number of the respondents.

5 Results and discussion

Table 1 shows the respondents’ experience, with 7 percent having 1 to 5 experience years of 25 percent having 6 to 10 experience years, 27 percent having 11 to 16 years of experience, 38 percent having 16 to 20 years of experience in the construction industry, and 38 percent having more than 20 years of experience, indicating that these professionals have current experiences and training in the examined systems. Table 2 shows the analysis of the procurement system that was applied in construction projects in Iraq.

Table 1

Respondents’ years of experience

Years of experience Response (%)
1–5 7
6–10 25
11–15 27
16–20 38
Above 20 3
Total 100
Table 2

Procurement system methods

No. Assessment criteria Mean score
1 General tender 4.5
2 Limited tender 3.1
3 General contract with the technical qualification method 2.3
4 Tender in two phases 3.7
5 Direct Invitation 4.1
6 Single offer 2.2
7 Direct contract 2.9
8 Direct Purchase from rational manufacturers 2.8
9 Purchasing committees 3.1
10 Amana regulation 2.1
11 Direct implementation 2.4
Table 3

Legislation procedure and process that was applied in construction projects in Iraq

No. Assessment criteria Mean score
1 Public Procurement Law No. 87 (2004) 2.7
2 Condition of Contracts for Civil Works 3.2
3 Condition of Contracts for Electrical, Mechanical and Process Works 3.6
4 Standard Bidding Documents 4.1
5 Federal Iraqi Budget regulation 4.7
6 Regulations for Implementing Government Contracts, 2014 4.9

It is fundamental to rate all factors [18] after completing the questionnaires and analyzing the results and gathering data, The objective was for the Table 4 of factors found to be significant and comprehensive and believed that the factors mentioned in this study were appropriate in the setting of Iraq. All factors were classified into three groups, the first group is the “Experience Years of Respondents”, the second group is the “Procurement System methods.”, the third group is “legislation procedure and process that was applied in construction projects in Iraq”. A technique called relative importance index (RII) was used to determine the grade of these factors based on classification given the transparency. The formula for calculating the RII for each factor is shown in Eq. (2)

(2) RII%=5(n5)+4(n4)+3(n3)+2(n2)+n15n*100

Where N means the total number of responses received, and n1, n2, n3, n4, and n5 denote the number of responses received in each of the five categories of respondents who chose 5 for “highest rating”, 4, for “high”, 3, for “neutral”, 2, for “low”, and 1 for “very low”.

Table 4

Factors are listed in order of their importance

No. Factor RII OR (N)
Procurement methods

1 General tender 94 1
2 Limited tender 88 3
3 General Contract with the technical qualification method 73 9
4 Tender in two phases 84 4
5 Direct invitation 91 2
6 Single offer 69 10
7 Direct contract 80 6
8 Direct purchase from rational manufacturers 78 7
9 Purchasing committees 81 5
10 Amana regulation 68 11
11 Direct implementation 75 8

legislation factors procedure

1 Public Procurement Law No. 87 (2004) 77 6
2 Condition of Contracts for Civil Works 81 5
3 Condition of contracts for electrical, mechanical and process works 84 4
4 Standard bidding documents 88 3
5 Federal Iraqi budget regulation 91 2
6 Regulations for implementing government contracts, 2014 95 1

Table 4 displays the two groups are ranked, the 11 factors, which are arranged according to their own particular group Show the factors’ overall ranking. as well. The three most procurement methods based on the respondents were “General Tender”, “Direct Invitation”, and “Limited Tender”. The least factors had in the four groups “Amana Regulation”. It is interesting to note that these factors primarily come under the methods of procurement. The second group shows the legislation 6 factors procedure and process that was applied in construction projects in Iraq.

6 Conclusions

The aim of this research was to analyze the current conceptualizations of the problem for action to modernize Iraq's procurement system. The Proposals are based on talks with contractual entities in Iraq and focus on improving transparency and integrity and accountability of Iraq's public procurement system

  1. Ensure that effective procurement system guarantees are in place and that they are applied in all tendering and construction projects of Iraq;

  2. Increasing the capacity of city workers as well as the employees in the contractual department to manage the procurement process; and

  3. Ensure that control systems are coordinated with existing regulations and applied through each tendering phase.

  1. Funding information:

    The authors state no funding involved.

  2. Author contributions:

    All authors have accepted responsibility for the entire content of this manuscript and approved its submission.

  3. Conflict of interest:

    The authors state no conflict of interest.

References

[1] Ashworth A, Hogg K. Willis's Practice and Procedure for Quantity Surveyor. Oxford, UK: Blackwell Publishing Ltd; 2007.Suche in Google Scholar

[2] Masterman JW. An Introduction to Building Procurement Systems. 2nd ed. London: Spon Press; 2002.10.4324/9780203246764Suche in Google Scholar

[3] Project Management Institute. A Guide to the Project Management Body of Knowledge. 3rd ed. PMI; 2004.Suche in Google Scholar

[4] Chitkara W. On the Development of Project Management Research: Schools of Thought and Critique. Int J Proj Manag. 2005;8:20–31.Suche in Google Scholar

[5] Kumaraswamy MM. Industry development through creative project packaging and integrated management. Eng Construct Architect Manag. 1998;5(3):228–37.10.1108/eb021077Suche in Google Scholar

[6] Arazi I, Mahmoud S, Mohamad HH. Prioritizing Project Performance Criteria within Client Perspective. Res J Appl Sci Eng Technol. 2011;3:1142–51.Suche in Google Scholar

[7] Love PE, Skitmore MR, Earl G. Selecting an appropriate procurement method for the construction process: an empirical study. Construct Manag Econ. 1998;16:221–33.10.1080/014461998372501Suche in Google Scholar

[8] National Economic Development Oflce (NEDO). Think About Building. London: NEDC; 1985.Suche in Google Scholar

[9] R.M. Skitmore and D.E. Marsden. Which procurement system? Towards a universal procurement selection technique. Constr Manag Econ. 1988;6(1):71–89.10.1080/01446198800000008Suche in Google Scholar

[10] Singh S. Selection of appropriate project delivery system for building construction projects. In: Ireland V, editor. Proceedings of CIB W-90 International Symposium on Building Economics and Construction Management; 1990 Mar 14–20; Sydney, Australia. CIB, 1990. p. 469–480.Suche in Google Scholar

[11] Ministry of Planning. Regulations to Implement Governmental Contracts for 2014 and Attached Guidelines. Revised ed. Directorate of General Governmental Contracts; 2017.Suche in Google Scholar

[12] Turner A. Building Procurement. UK: Macmillan; 1990. https://doi.org/10.1007/978-1-349-21159-3.10.1007/978-1-349-21159-3Suche in Google Scholar

[13] Daniel WH. Construction Management. USA: John Wiley & Sons Inc; 2006.Suche in Google Scholar

[14] Adesanya O. Project Procurement Paths. J Financial Manag Prop Constr Ind. 2008;2(3):6–21.Suche in Google Scholar

[15] Seeley IH. Quantity Surveying Practice. London: Macmillan Publishers Ltd; 1997. https://doi.org/10.1007/978-1-349-14402-0.10.1007/978-1-349-14402-0Suche in Google Scholar

[16] Kadiri DS, Odusami KT. Comparative Study of Time and Cost Performance of Direct Labour and Labour Only Procurement System. Journal of the Nigerian Institute of Quantity Surveyors. 2003;44(3).Suche in Google Scholar

[17] Mohammed SR, Jasim AJ. Study and analysis of the delay problems in Iraqi construction projects. Int J Sci Res. 2017.Suche in Google Scholar

[18] Hasan S. Analysis the implementation of Standard Bidding Documents and Their Impact on Contractors and Contracting Entities [dissertation]. Baghdad: University of Baghdad; 2020.Suche in Google Scholar

[19] Private Sector Development in the Middle East and North Africa. Improving Transparency within Government Procurement Procedures in Iraq, OECD Benchmark Report; 2010.Suche in Google Scholar

[20] Coalition Provisional Authority Order Number 87. Public Contracts (CPA/ORD/14 May 2004/87). Available from: https://govinfo.library.unt.edu/cpa-iraq/regulations/20040516_CPAORD_87_Public_Contracts.pdfSuche in Google Scholar

Received: 2022-03-13
Accepted: 2022-03-21
Published Online: 2022-04-29

© 2022 Sadeq Abdul Hamza et al., published by De Gruyter

This work is licensed under the Creative Commons Attribution 4.0 International License.

Artikel in diesem Heft

  1. Research Articles
  2. Calcium carbonate nanoparticles of quail’s egg shells: Synthesis and characterizations
  3. Effect of welding consumables on shielded metal arc welded ultra high hard armour steel joints
  4. Stress-strain characteristics and service life of conventional and asphaltic underlayment track under heavy load Babaranjang trains traffic
  5. Corrigendum to: Statistical mechanics of cell decision-making: the cell migration force distribution
  6. Prediction of bearing capacity of driven piles for Basrah governatore using SPT and MATLAB
  7. Investigation on microstructural features and tensile shear fracture properties of resistance spot welded advanced high strength dual phase steel sheets in lap joint configuration for automotive frame applications
  8. Experimental and numerical investigation of drop weight impact of aramid and UHMWPE reinforced epoxy
  9. An experimental study and finite element analysis of the parametric of circular honeycomb core
  10. The study of the particle size effect on the physical properties of TiO2/cellulose acetate composite films
  11. Hybrid material performance assessment for rocket propulsion
  12. Design of ER damper for recoil length minimization: A case study on gun recoil system
  13. Forecasting technical performance and cost estimation of designed rim wheels based on variations of geometrical parameters
  14. Enhancing the machinability of SKD61 die steel in power-mixed EDM process with TGRA-based multi criteria decision making
  15. Effect of boron carbide reinforcement on properties of stainless-steel metal matrix composite for nuclear applications
  16. Energy absorption behaviors of designed metallic square tubes under axial loading: Experiment-based benchmarking and finite element calculation
  17. Synthesis and study of magnesium complexes derived from polyacrylate and polyvinyl alcohol and their applications as superabsorbent polymers
  18. Artificial neural network for predicting the mechanical performance of additive manufacturing thermoset carbon fiber composite materials
  19. Shock and impact reliability of electronic assemblies with perimeter vs full array layouts: A numerical comparative study
  20. Influences of pre-bending load and corrosion degree of reinforcement on the loading capacity of concrete beams
  21. Assessment of ballistic impact damage on aluminum and magnesium alloys against high velocity bullets by dynamic FE simulations
  22. On the applicability of Cu–17Zn–7Al–0.3Ni shape memory alloy particles as reinforcement in aluminium-based composites: Structural and mechanical behaviour considerations
  23. Mechanical properties of laminated bamboo composite as a sustainable green material for fishing vessel: Correlation of layer configuration in various mechanical tests
  24. Singularities at interface corners of piezoelectric-brass unimorphs
  25. Evaluation of the wettability of prepared anti-wetting nanocoating on different construction surfaces
  26. Review Article
  27. An overview of cold spray coating in additive manufacturing, component repairing and other engineering applications
  28. Special Issue: Sustainability and Development in Civil Engineering - Part I
  29. Risk assessment process for the Iraqi petroleum sector
  30. Evaluation of a fire safety risk prediction model for an existing building
  31. The slenderness ratio effect on the response of closed-end pipe piles in liquefied and non-liquefied soil layers under coupled static-seismic loading
  32. Experimental and numerical study of the bulb's location effect on the behavior of under-reamed pile in expansive soil
  33. Procurement challenges analysis of Iraqi construction projects
  34. Deformability of non-prismatic prestressed concrete beams with multiple openings of different configurations
  35. Response of composite steel-concrete cellular beams of different concrete deck types under harmonic loads
  36. The effect of using different fibres on the impact-resistance of slurry infiltrated fibrous concrete (SIFCON)
  37. Effect of microbial-induced calcite precipitation (MICP) on the strength of soil contaminated with lead nitrate
  38. The effect of using polyolefin fiber on some properties of slurry-infiltrated fibrous concrete
  39. Typical strength of asphalt mixtures compacted by gyratory compactor
  40. Modeling and simulation sedimentation process using finite difference method
  41. Residual strength and strengthening capacity of reinforced concrete columns subjected to fire exposure by numerical analysis
  42. Effect of magnetization of saline irrigation water of Almasab Alam on some physical properties of soil
  43. Behavior of reactive powder concrete containing recycled glass powder reinforced by steel fiber
  44. Reducing settlement of soft clay using different grouting materials
  45. Sustainability in the design of liquefied petroleum gas systems used in buildings
  46. Utilization of serial tendering to reduce the value project
  47. Time and finance optimization model for multiple construction projects using genetic algorithm
  48. Identification of the main causes of risks in engineering procurement construction projects
  49. Identifying the selection criteria of design consultant for Iraqi construction projects
  50. Calibration and analysis of the potable water network in the Al-Yarmouk region employing WaterGEMS and GIS
  51. Enhancing gypseous soil behavior using casein from milk wastes
  52. Structural behavior of tree-like steel columns subjected to combined axial and lateral loads
  53. Prospect of using geotextile reinforcement within flexible pavement layers to reduce the effects of rutting in the middle and southern parts of Iraq
  54. Ultimate bearing capacity of eccentrically loaded square footing over geogrid-reinforced cohesive soil
  55. Influence of water-absorbent polymer balls on the structural performance of reinforced concrete beam: An experimental investigation
  56. A spherical fuzzy AHP model for contractor assessment during project life cycle
  57. Performance of reinforced concrete non-prismatic beams having multiple openings configurations
  58. Finite element analysis of the soil and foundations of the Al-Kufa Mosque
  59. Flexural behavior of concrete beams with horizontal and vertical openings reinforced by glass-fiber-reinforced polymer (GFRP) bars
  60. Studying the effect of shear stud distribution on the behavior of steel–reactive powder concrete composite beams using ABAQUS software
  61. The behavior of piled rafts in soft clay: Numerical investigation
  62. The impact of evaluation and qualification criteria on Iraqi electromechanical power plants in construction contracts
  63. Performance of concrete thrust block at several burial conditions under the influence of thrust forces generated in the water distribution networks
  64. Geotechnical characterization of sustainable geopolymer improved soil
  65. Effect of the covariance matrix type on the CPT based soil stratification utilizing the Gaussian mixture model
  66. Impact of eccentricity and depth-to-breadth ratio on the behavior of skirt foundation rested on dry gypseous soil
  67. Concrete strength development by using magnetized water in normal and self-compacted concrete
  68. The effect of dosage nanosilica and the particle size of porcelanite aggregate concrete on mechanical and microstructure properties
  69. Comparison of time extension provisions between the Joint Contracts Tribunal and Iraqi Standard Bidding Document
  70. Numerical modeling of single closed and open-ended pipe pile embedded in dry soil layers under coupled static and dynamic loadings
  71. Mechanical properties of sustainable reactive powder concrete made with low cement content and high amount of fly ash and silica fume
  72. Deformation of unsaturated collapsible soils under suction control
  73. Mitigation of collapse characteristics of gypseous soils by activated carbon, sodium metasilicate, and cement dust: An experimental study
  74. Behavior of group piles under combined loadings after improvement of liquefiable soil with nanomaterials
  75. Using papyrus fiber ash as a sustainable filler modifier in preparing low moisture sensitivity HMA mixtures
  76. Study of some properties of colored geopolymer concrete consisting of slag
  77. GIS implementation and statistical analysis for significant characteristics of Kirkuk soil
  78. Improving the flexural behavior of RC beams strengthening by near-surface mounting
  79. The effect of materials and curing system on the behavior of self-compacting geopolymer concrete
  80. The temporal rhythm of scenes and the safety in educational space
  81. Numerical simulation to the effect of applying rationing system on the stability of the Earth canal: Birmana canal in Iraq as a case study
  82. Assessing the vibration response of foundation embedment in gypseous soil
  83. Analysis of concrete beams reinforced by GFRP bars with varying parameters
  84. One dimensional normal consolidation line equation
Heruntergeladen am 12.12.2025 von https://www.degruyterbrill.com/document/doi/10.1515/jmbm-2022-0012/html
Button zum nach oben scrollen