The selected roof covering technologies in the aspect of their life cycle costs

  • Magdalena Apollo EMAIL logo , Agata Siemaszko and Emilia Miszewska-Urbańska
Published/Copyright: November 21, 2018
Become an author with De Gruyter Brill

Abstract

In the article is presented an analysis of the life cycle costs calculation for selected roof coverings. The scope of research includes costs of construction, maintenance and demolition of the roof covering structure for two alternative technologies – the traditional and new generation. On the presented example of an industrial building with a roof area of 1000 m2, the above costs are taken to consideration for the roof covering made of two thermoplastic asphalt torching polymer membrane layers and a new generation PVC thermoplastic film with a reinforcing layer. The input data presented in the article comes from the investor (the owner of the future facility) and from property managers responsible for the maintenance of facilities in regard to the purpose, volume and applied method.

The subject of the research is the analysis of the range of impact of the selected roof covering technology on the long-term costs of its maintenance. The aim of the research conducted by the authors is to indicate the possibility of reducing the costs related to the maintenance and elimination of a selected building structure (roof covering) in the assumed period of its operation for 70 years.

1 Research problem

Roofs and flat roofs of large surfaces, due to their design and shape (including small roof slopes), require special solutions of covering materials, hoods details and edge treatments. All these elements must ensure complete tightness and failure-free drainage of the roof surface. An important element that provides the above features is the material used to make the roof covering. There are many possibilities in this area. In practice, the roof covering is made of roofing membrane, foil, plastic (PVC), rubber membranes (EPDM), etc. In many cases, after considering several variants of the object’s creation technology, the investor is faced with the need to make an investment decision. At this stage, he analyzes the advantages and disadvantages of various solutions such as their durability and reliability, but also economics. From the owner’s and /or user’s of the facility point of view, the cost of maintaining the roofing material in a proper technical and aesthetic condition is important. In any case, roof covering requires periodic maintenance and renovation. Its frequency mainly depends on the operating conditions [1, 2]. The repair of coverings and roof flashings on a large roof surface in the facility being operated is often associated with numerous technological, logistical and organizational difficulties. Therefore, it is important to design and build the roof covering that it is reliable (durable and tight) for as long as possible (it is assumed that it will be up to 70 years) [3, 4].

From the perspective of the investor and/or user of the facility, it is important to compare the costs incurred at the stage of covering the costs generated during its maintenance [5]. The entire life cycle cost of a given roof covering includes the cost of its implementation (initial investment) and the costs of repairs, ongoing renovations (in a defined range), winter maintenance (snow removal), general renovations (full coverage) and elimination.

2 The life cycle cost

According to [1, 7] the cost of a building’s life cycle is the process of economic analysis covering the sum of costs of purchase, use, maintenance and demolition of a building. According to [6, 7, 8]:

  • the purchase cost includes costs related to construction works being the subject of the order including the cost of equipment permanently associated with the building, the cost of design documentation for technical specifications and acceptance of construction works (Specifications for Construction Work Accomplishment and Acceptance) and service costs during the warranty period granted by the contractor,

  • the cost of use includes costs related to the consumption of energy or energy carriers and water,

  • costs of maintenance are related to the operation of the building and include mainly the costs of renovations, replacements, repairs and maintenance, which allows to maintain the building in a proper technical and aesthetic condition,

  • the demolition costs are related to the liquidation of the facility and include demolition of the building, export, development, utilization and recycling of waste.

It should be emphasized that [6] project primarily refers to the life cycle costs of a building. The example presented in the article refers to the selected element of the object – roof covering. Therefore, the costs of use were omitted in the calculation of life cycle costs for the two analyzed variants. The costs of purchase, maintenance and demolition of roofing are included.

According to [6, 9] the costs of purchasing an element are presented in the offer submitted by the contractor.

According to [6] maintenance costs are calculated as the sum of unit maintenance costs of products during the calculation period, reduced by the value of the contractor’s warranty for a given product, accordingly with formula (1).

(1)Cut=k=1nAnBn

where:

Cut - the cost of maintenance,

An – the cost of maintaining the nth product in the calculation period,

Bn – the value of the contractor’s warrantyfor the nth product.

According to [6] the cost of maintaining the nth product during the calculation period is determined by the formula (2).

(2)An=I×K×N

where:

I – the number of product units,

K - the cost of replacing the unit of the product,

N – the number of cycles of product use in the calculation period.

According to [6], the value of the contractor’s warranty for the nth product is calculated from formula (3).

(3)Bn=An×OgO

where:

Og – the contractor’s warranty period expressed in years,

O – the calculation period.

It should be emphasized that in a broad approach, the LCC analysis provides an important data that is crucial in the process of designing, development, operation and the liquidation of object, a product, and a construction element [10, 11]. Estimating life cycle costs can also be effectively applied to compare and assess the operating costs of an object construction element for alternative variants [12, 13].

Providers of various technologies and products can optimize their projects by assessing various alternative solutions [14, 15]. At the stage of selecting an investment variant, the investor also has the opportunity to optimize its decision based on the calculation of the life cycle cost of an object or construction element and the analysis of various strategies for their use, maintenance and liquidation [16].

The cost of making and maintaining roofing, while maintaining its reliability condition depends on many factors. These include the scope of the technical design, the quality of the roofing’s coverage, as well as the scope of works related to its maintenance [17].

Determining the amount of the investor’s reasonable expenses, in terms of the life cycle cost of roof covering, requires the definition and consideration of the above issues at the stage of preparing the project documentation. In practice, in many cases, investors analyze only the initial capital expenditure [18, 19, 20, 21], omitting the long-term expenditure on the operation of the roof covering material [22, 23].

3 The analysis of the life cycle cost for two variants of roof coverings

In the article are taken in to consideration two technologies for roof covering:

  • made from two layers of asphalt polymer-weldable roofing membrane,

  • made from a new generation PVC thermoplastic film with a reinforcing layer.

The LCC analysis is carried out accordingly to the methodology contained in [6]. For the purposes of the analysis was defined the time horizon - 70 years were adopted, and then the cost components were determined. The analyzed costs were established based on the knowledge of experts: the investor (the owner of the future facility), property managers responsible for the maintenance of facilities of similar nature and current price publications. According to [24], 70 years occupation time has been adopted (category of performance period: 4/5, designed performance period: 50/100 years). The assumed occupation time was also adopted based on the knowledge of experts - property managers, based on the assessment of the technical deterioration degree of the building made with the use of the Ross method taking into account the scope and frequency of renovations and maintenance of the facility. The discount rate was based on the current NBP information.

In order to carry out the cost analysis, the following assumptions were made:

  • the calculation of roof covering costs was made for a roof with an area of 1000 m2 (Figure 1),

  • a 70-year calculation period has been adopted,

  • for initial costs (purchase costs) only works related to the roof covering - without the insulation layers mounted on the roof structure panel and without flashings, gutters and downpipes were taken into consideration,

  • the initial investment (purchase cost) includes the purchase cost of all materials necessary to make the roof covering and the costs related to their transport to the building site,

  • average unit prices were determined based on the information contained in the price publication [25], information obtained from the market and individual calculations,

  • a discount rate of 1.75% was adopted.

Figure 1 The view of the roof area with an area of 1000m2 selected for conducting this analysis.
Figure 1

The view of the roof area with an area of 1000m2 selected for conducting this analysis.

Based on the experience of managers responsible for maintaining facilities of a similar nature, the following strategy for maintaining roof covering was adopted:

  1. with two layers of asphalt polymer-weldable roofing membrane:

  • winter maintenance - snow removal will be carried out twice a season,

  • periodic renovations will be carried out every 5 years on 10% of the roof surface; the assumed number of renovations: 13,

  • general repairs will be carried out every 30 years on 100% of the roof surface; a number of renovations: 2,

  • waste utilization and disposal: every 5 years - material removed from 10% roof area (13 times) and every 30 years - material removed from 100% of roof area (2 times).

  1. with a new generation PVC thermoplastic film with a reinforcing layer:

  • winter maintenance - snow removal will be carried out twice a season,

  • periodic renovations will be carried out every 10 years on 10% of the roof surface; a number of renovations: 6,

  • general repairs will be carried out every 40 years on 100% of the roof surface; number of renovations: 1,

  • waste utilization and disposal: every 10 years - material removed from 10% roof area (6 times) and every 40 years - material removed from 100% of roof area (once).

In both cases, the maintenance costs of the roof covering were reduced by the value of the warranty granted by the contractor to perform a new covering on the entire roof surface. The value of works performed by the contractor during the 5-year period (the warranty period granted by the contractor) was set as 5% of the value of the initial covering implementation.

According to the assumption adopted at the design stage, both proposed variants of roof covering should meet the leak tightness requirements for a period of 30 years (for roof membrane covering) and 40 years (for foil covering), and the roof structure should ensure safe operating conditions of the facility by the facility assumed lifetime, i.e. 70 years.

The reparation of old layers of roof covering membrane consists of repairing existing damages, such as loosening, blisters, folds, lumps, cracks, etc. Separation and blisters should be cut, inverted and dried, and then welded or glued with an asphalt stick. Folds and bulges should be felled and leveled. With extensive damage, it is advisable to cut them down to the ground, and then patches should be pasted with a new roofing membrane.

In the event of moisture found under the old cover, which is the case for most repaired roofs, it is recommended to make an insulation system composed of perforated roofing membrane and ventilation chimneys in the amount of 1 chimney on the 40 - 60 m2 of the roof.

In order to enable effective moisture removal, the surface of the old roofing membrane should be unsealed up to the moist layer, for example by making holes with a drill or cutting the old substrate.

After calculations based on formulas (1), (2), (3), individual components of life cycle costs were calculated for the technologies of roof covering and are summarized in Table 1.

Table 1

Components of life cycle costs for two alternative technologies of production, maintenance in the period of 70 years and elimination of roof covering.

Type of roof coveringInitial expenditureCurrent maintenanceCurrent repairs [PLN/1000m2]General repairs Utilization of wasteLCC
Coverage of two layers of thermo-weldable asphalt polymer roofing membrane29854,7878387,924657,9892541,0710480,7235922,4
Cover made of a new generation PVC thermoplastic film with a rein forcing layer41750,2178387,916854,2167231,764231,76208455,8

A graphical comparison of initial expenditure, maintenance costs over 70 years, liquidation and total LCC values for two roof covering technologies is presented in Figure 2.

Figure 2 LCC analysis for two variants of roofing (source: own study).
Figure 2

LCC analysis for two variants of roofing (source: own study).

It should be emphasized that the comparison of initial expenditure with the costs generated during the roof covering exploitation period (Figure 3) gives the investor a full picture of the actual expenses that he will be forced to incur during the assumed lifetime of the facility (and coverage). These expenses are a result of carrying out repair works for the roof covering at specified intervals, but also redoing the roof structure protection in full range – accordingly to the manufacturer’s instructions for the given type of covering.

Figure 3 Percentage of individual components in the life cycle costs of roof covering for two variants. source: own study
Figure 3

Percentage of individual components in the life cycle costs of roof covering for two variants. source: own study

In the light of the above analysis, it can be concluded that taking into account only the initial investment, the more expensive variant is the implementation of a new generation PVC thermoplastic film with a reinforcing layer. The cost of making the cover made of two layers of asphalt polymer-welded roof membrane accounts for 12.65%of the total life cycle costs.

The cost of making PVC covering consists of 20.03% of the life cycle cost (Figure 3). It is anticipated that activities related to the ongoing maintenance of roof covering for both variants (including winter snow removal) are associated with spending the same amount by the invertor. Significant differences can be seen in relation to the costs associated with maintaining the roof covering in the long term. Taking into account the discounted costs of maintaining the roof covering in the assumed period of 70 years, including general and ongoing repairs, the more expensive solution is coating with thermo-weldable roofing membrane. Faster aging time of this covering, the loss of flexibility and resistance to weather conditions cause a significant reduction in its durability in the analyzed period. In practice, this means that every 30 years the labor-intensive and costly replacement process must be repeated. The use of roof membrane, in the course of operation also means more frequent undertaking of costly activities related to ongoing repairs.

Taking into account the total life cycle cost, i.e. initial investment, 70-year maintenance and disposal period for two analyzed variants, it can be concluded that the cheaper solution is a new generation PVC thermoplastic film with a reinforcing layer. In the long-term, it generates lower expenses incurred by the owner and/or user of the facility.

4 Conclusions

The conducted analysis and own authors experience justifies the formulation of the following conclusions and recommendations.

  1. In the article is indicated the possibility of using a new approach based on estimating life cycle costs in the process of choosing the technology of roof covering material implementation. It allows to indicate the investor the optimal variant,which with reduced roof maintenance costs (resulting from limiting the scope and frequency of renovation work), ensures that certain safety, quality and aesthetics standards are maintained. Therefore, it is possible to significantly reduce the costs incurred by the investor during the operation period of the facility.

  2. The presented analysis confirms the long-term financial benefits for the investor and/or the user of the facility, resulting from the application of a cover made of a new generation PVC thermoplastic film with a reinforcing layer. It also justifies applying in practice mainly in the process of designing a new cover or replacing an existing one, which results from the LCC analysis. It allows to indicate the optimal solution in terms of the total life cycle cost, taking into account initial costs and costs incurred in the course of maintenance and liquidation of a given element or the entire facility (considered in the long term).

  3. In any case, regardless of the applied type of roofing technology, apart from the financial aspects taken into account by the investor, the cover must meet all the requirements. It should be therefore characterized by adequate resistance to external environment impacts, proper mechanical resistance and full tightness of all joint connections as well as other accompanying elements (flashings, etc.). This means that the construction and use of the roof covering as well as flat roofing must be fully adequate with the manufacturer’s instructions. In the above context, the LCC analysis assumes the option of choosing a variant with a lower life cycle cost, but assuming the proper use of the covering (savings can not be the result of negligence in works related to maintaining the covering).

  4. Experience from the practice indicates that the LCC analysis is not widely use in the design process of construction works. One of the reasons is the lack of a simple model of life cycle costs calculation, which is a tool for supporting investment decisions and indicating the optimal solution already at the design stage. The obligatory application of the methodology contained in [6] will contribute, among others, to the increase of efficiency in using funds being at the investor’s disposal.

References

[1] Grzyl B., Apollo M., Miszewska-Urbańska E., Kristowski A., Zarządzanie eksploatacją obiektu w ujęciu kosztów cyklu życia, Acta Scientiarum Polonorum. Architectura, 2017, 16(2), 85-8910.22630/ASPA.2017.16.2.11Search in Google Scholar

[2] Apollo M., Miszewska-Urbańska E., Analysis of the increase of construction costs in urban regeneration projects, Adv. in Sc. and Tech. – R. J. 9, 2015, 28, 68–7410.12913/22998624/60786Search in Google Scholar

[3] Dziaduch I., Analiza kosztów okresu istnienia (LCC) obiektu technicznego w aspekcie jego niezawodności, Logistyka, 2011, 2, 139-150Search in Google Scholar

[4] Orłowski Z.,Wybrane aspekty właściwości użytkowych budynku w okresie jego eksploatacji, Przegląd Budowlany, 2011, 82, 36-43Search in Google Scholar

[5] Grzyl B., Kristowski A., Jamroz K., Gobis A., Methods of estimating the cost of traflc safety equipment’s life cycle, in: MATEC Web of Conferences (Vol. 122, p. 02003). EDP Sciences, 201710.1051/matecconf/201712202003Search in Google Scholar

[6] Projekt Rozporządzenia Ministra Infrastruktury i Budownictwa z dn. 10 listopada 2017 r. w sprawie metody kalkulacji kosztów cyklu życia budynków oraz sposobu przedstawiania informacji o tych kosztach.Search in Google Scholar

[7] Márquez A. C., Márquez C. P., Fernández J. F. G., Campos M. L., Díaz V. G. P., Life cycle cost analysis, in: Asset Management, Springer, Dordrecht, 2012, 81-9910.1007/978-94-007-2724-3_6Search in Google Scholar

[8] Norris G. A., Integrating life cycle cost analysis and LCA. The international journal of life cycle assessment, 2001, 6.2, 118-12010.1007/BF02977849Search in Google Scholar

[9] Kembłowski M. W., Grzyl B., Siemaszko A., Game Theory Analysis of Bidding for a Construction Contract, IOP Conference Series: Materials Science and Engineering 245/6, IOP Publishing 2017, http://iopscience.iop.org/article/10.1088/1757-899X/245/6/062047/meta10.1088/1757-899X/245/6/062047Search in Google Scholar

[10] Plebankiewicz E., Zima K., Wieczorek D., Review of methods of determining the life cycle cost of buildings, Creative Construction Conference Proceedings, 2015, 21-24 June, Krakow, 309-316Search in Google Scholar

[11] Breidenbach D. P., Life cycle cost analysis, In Aerospace and Electronics Conference, 1989. NAECON 1989, Proceedings of the IEEE 1989 National, 1216-122010.1109/NAECON.1989.40363Search in Google Scholar

[12] PN-EN 63300-3-3 Zarządzanie niezawodnością część 3-3: Przewodnik zastosowań. Szacowanie kosztu cyklu życia, 2006.Search in Google Scholar

[13] ISO 15686-5:2008 Buildings and constructed assets: Service - life planning. Part 5: Life-cycle costing.Search in Google Scholar

[14] Plebankiewicz E., Zima K., Wieczorek D., Life cycle cost modelling of buildings with consideration of the risk, Archives of Civil Engineering, 2016, 62.2, 149-16610.1515/ace-2015-0071Search in Google Scholar

[15] Plebankiewicz E., Zima K., Wieczorek D., Quantification of the risk addition in life cycle cost of a building object, Technical Transactions, 2017, 5, 35-4510.4467/2353737XCT.17.067.6424Search in Google Scholar

[16] Grzyl B., Kristowski A., Proces kontroli kosztów w kolejnych fazach inwestycji budowlanej, TTS Technika Transportu Szynowego, 2013, 10, 1663-1668Search in Google Scholar

[17] Kristowski A., Koncepcja modelu procesu eksploatacji obiektówbudowlanych. Zeszyty Naukowe Politechniki Gdańskiej, Budownictwo Lądowe 61, 2007, 193-201Search in Google Scholar

[18] Kowalski D., Grzyl B., Kristowski A., The Cost Analysis of Corrosion Protection Solutions for Steel Components in Terms of the Object Life Cycle Cost, Civil and Environmental Engineering Reports, 2017, 26.3, 5-1310.1515/ceer-2017-0031Search in Google Scholar

[19] Fabrycky W. J., Blanchard B. S., Life-cycle cost and economic analysis, 1991.Search in Google Scholar

[20] Ciambrone D. F., Environmental life cycle analysis. CRC Press, 201810.1201/9780203757031Search in Google Scholar

[21] Frangopol D. M., Liu M., Maintenance and management of civil infrastructure based on condition, safety, optimization, and life-cycle cost. Structure and infrastructure engineering, 2007, 3(1), 29-4110.1080/15732470500253164Search in Google Scholar

[22] Grzyl B., Miszewska-Urbańska E., Apollo M. The life cycle cost of a building from the point of view of environmental criteria of selecting the most beneficial offer in the area of competitive tendering, E3S Web of Conferences 17/ 00028, 2017.10.1051/e3sconf/20171700028Search in Google Scholar

[23] Grzyl, B., Kristowski, A., Miszewska-Urbańska, E.. Analysis and Risk Evaluation on the Case of Alteration, Revitalization and Conversion of a Historic Building in Gdańsk. In IOP Conference Series: Materials Science and Engineering (245/ 8, p. 082049). IOP Publishing, 2017.Search in Google Scholar

[24] EN 1990:2002 Basis of structural design.Search in Google Scholar

[25] Bulletin of BRB construction works price, Sekocenbud I quarter 2018.Search in Google Scholar

Received: 2018-05-25
Accepted: 2018-07-19
Published Online: 2018-11-21

© 2018 M. Apollo et al., published by De Gruyter

This work is licensed under the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 License.

Articles in the same Issue

  1. Regular Article
  2. Real-scale comparison between simple and composite raw sewage sampling
  3. 10.1515/eng-2018-0017
  4. The risks associated with falling parts of glazed facades in case of fire
  5. Implementation of high speed machining in thin-walled aircraft integral elements
  6. Evaluating structural crashworthiness and progressive failure of double hull tanker under accidental grounding: bottom raking case
  7. Influence of Silica (SiO2) Loading on the Thermal and Swelling Properties of Hydrogenated-Nitrile-Butadiene-Rubber/Silica (HNBR/Silica) Composites
  8. Statistical Variations and New Correlation Models to Predict the Mechanical Behavior and Ultimate Shear Strength of Gypsum Rock
  9. Analytic approximate solutions to the chemically reactive solute transfer problem with partial slip in the flow of a viscous fluid over an exponentially stretching sheet with suction/blowing
  10. Thermo-mechanical behavior simulation coupled with the hydrostatic-pressure-dependent grain-scale fission gas swelling calculation for a monolithic UMo fuel plate under heterogeneous neutron irradiation
  11. Optimal Auxiliary Functions Method for viscous flow due to a stretching surface with partial slip
  12. Vibrations Analysis of Rectangular Plates with Clamped Corners
  13. Evaluating Lean Performance of Indian Small and Medium Sized Enterprises in Automotive Sector
  14. FPGA–implementation of PID-controller by differential evolution optimization
  15. Thermal properties and morphology of polypropylene based on exfoliated graphite nanoplatelets/nanomagnesium oxide
  16. A computer-based renewable resource management system for a construction company
  17. Hygrothermal Aging of Amine Epoxy: Reversible Static and Fatigue Properties
  18. The selected roof covering technologies in the aspect of their life cycle costs
  19. Influence of insulated glass units thickness and weight reduction on their functional properties
  20. Structural analysis of conditions determining the selection of construction technology for structures in the centres of urban agglomerations
  21. Selection of the optimal solution of acoustic screens in a graphical interpretation of biplot and radar charts method
  22. Subsidy Risk Related to Construction Projects: Seeking Causes
  23. Multidimensional sensitivity study of the fuzzy risk assessment module in the life cycle of building objects
  24. Planning repetitive construction projects considering technological constraints
  25. Identification of risk investment using the risk matrix on railway facilities
  26. Comparison of energy parameters of a centrifugal pump with a multi-piped impeller in cooperation either with an annular channel and a spiral channel
  27. Influence of the contractor’s payment method on the economic effectiveness of the construction project from the contractor’s point of view
  28. Special Issue Automation in Finland
  29. Diagnostics and Identification of Injection Duration of Common Rail Diesel Injectors
  30. An advanced teaching scheme for integrating problem-based learning in control education
  31. A survey of telerobotic surface finishing
  32. Wireless Light-Weight IEC 61850 Based Loss of Mains Protection for Smart Grid
  33. Smart Adaptive Big Data Analysis with Advanced Deep Learning
  34. Topical Issue Desktop Grids for High Performance Computing
  35. A Bitslice Implementation of Anderson’s Attack on A5/1
  36. Efficient Redundancy Techniques in Cloud and Desktop Grid Systems using MAP/G/c-type Queues
  37. Templet Web: the use of volunteer computing approach in PaaS-style cloud
  38. Using virtualization to protect the proprietary material science applications in volunteer computing
  39. Parallel Processing of Images in Mobile Devices using BOINC
  40. “XANSONS for COD”: a new small BOINC project in crystallography
  41. Special Issue on Sustainable Energy, Engineering, Materials and Environment
  42. An experimental study on premixed CNG/H2/CO2 mixture flames
  43. Tidal current energy potential of Nalón river estuary assessment using a high precision flow model
  44. Special Spring Issue 2017
  45. Context Analysis of Customer Requests using a Hybrid Adaptive Neuro Fuzzy Inference System and Hidden Markov Models in the Natural Language Call Routing Problem
  46. Special Issue on Non-ferrous metals and minerals
  47. Study of strength properties of semi-finished products from economically alloyed high-strength aluminium-scandium alloys for application in automobile transport and shipbuilding
  48. Use of Humic Sorbent from Sapropel for Extraction of Palladium Ions from Chloride Solutions
  49. Topical Issue on Mathematical Modelling in Applied Sciences, II
  50. Numerical simulation of two-phase filtration in the near well bore zone
  51. Calculation of 3D Coordinates of a Point on the Basis of a Stereoscopic System
  52. The model of encryption algorithm based on non-positional polynomial notations and constructed on an SP-network
  53. A computational algorithm and the method of determining the temperature field along the length of the rod of variable cross section
  54. ICEUBI2017 - International Congress on Engineering-A Vision for the Future
  55. Use of condensed water from air conditioning systems
  56. Development of a 4 stroke spark ignition opposed piston engine
  57. Development of a Coreless Permanent Magnet Synchronous Motor for a Battery Electric Shell Eco Marathon Prototype Vehicle
  58. Removal of Cr, Cu and Zn from liquid effluents using the fine component of granitic residual soils
  59. A fuzzy reasoning approach to assess innovation risk in ecosystems
  60. Special Issue SEALCONF 2018
  61. Brush seal with thermo-regulating bimetal elements
  62. The CFD simulation of the flow structure in the sewage pump
  63. The investigation of the cavitation processes in the radial labyrinth pump
  64. Testing of the gaskets at liquid nitrogen and ambient temperature
  65. Probabilistic Approach to Determination of Dynamic Characteristics of Automatic Balancing Device
  66. The design method of rubber-metallic expansion joint
  67. The Specific Features of High-Velocity Magnetic Fluid Sealing Complexes
  68. Effect of contact pressure and sliding speed on the friction of polyurethane elastomer (EPUR) during sliding on steel under water wetting conditions
  69. Special Issue on Advance Material
  70. Effect of thermo-mechanical parameters on the mechanical properties of Eurofer97 steel for nuclear applications
  71. Failure prediction of axi-symmetric cup in deep drawing and expansion processes
  72. Characterization of cement composites based on recycled cellulosic waste paper fibres
  73. Innovative Soft Magnetic Composite Materials: Evaluation of magnetic and mechanical properties
  74. Statistical modelling of recrystallization and grain growth phenomena in stainless steels: effect of initial grain size distribution
  75. Annealing effect on microstructure and mechanical properties of Cu-Al alloy subjected to Cryo-ECAP
  76. Influence of heat treatment on corrosion resistance of Mg-Al-Zn alloy processed by severe plastic deformation
  77. The mechanical properties of OFHC copper and CuCrZr alloys after asymmetric rolling at ambient and cryogenic temperatures
Downloaded on 7.10.2025 from https://www.degruyterbrill.com/document/doi/10.1515/eng-2018-0053/html?lang=en&srsltid=AfmBOornKxz1_EVgZ8d7QHRn8wLBesN8IYc1HP00iUUIm2SmhDhM23UC
Scroll to top button